| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹89.0 LAccepted-Finance | L1 | Accepted-Finance Qualified | |
| 2 | L2₹95.8 L+₹6.8 L (7.65%)Accepted-Finance | L2 | Accepted-Finance Qualified | |
| 3 | L3₹96.3 L+₹7.3 L (8.17%)Accepted-Finance | L3 | Accepted-Finance Qualified | |
| 4 | Rejected-Technical RG 259 POCKET B RAGHUBIR NAGAR POCKET B RAGHUBIR NAGAR WEST DELHI DELHI 110027 UDYAM DL 03 0017275 | WEST DELHI | DELHI | 110027 | - | Rejected-Technical NonQualified | |
| 5 | Rejected-Technical | - | Rejected-Technical NonQualified |
Tender Value
Refer Docs
EMD Value
₹1 L
Closing Date
13 Apr 2021, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE ETC Jhansi
132KV S/S Hasari Jhansi
Dismantling Shifting of 315 MVA Transformer and Loading Carriage Unloading of 240 MVA T/F from 400 KV S/S Moti Ram Adda Gorakhpur to 400 KV S/S Orai and Shifting Erection of 240 MVA T/F at 400 KV S/S Orai Under Electricity 400KV S/S Division Orai
2021_UPTCL_580374_1
ETS-02/ETCJ/21-22
Open Tender
Electrical Works
Fixed-rate
60 days
Orai
As per PQR
2 documents required · 2 mandatory
₹7,080
SE ETC Jhansi
₹1 L
20 Apr 2021
7 Apr 2021
13 Apr 2021
7 Apr 2021
13 Apr 2021
7 Apr 2021
90 days
Amount
Dismantling, Shifting of 315 MVA Transformer and Loading, Carriage, Unloading of 240 MVA T/F from 400 KV S/S Moti Ram Adda, Gorakhpur to 400 KV S/S Orai & Shifting, Erection of 240 MVA T/F at 400 KV S/S Orai Under Electricity 400KV S/S Division Orai. NOTE:- Transit cum 45 days storage insurance of transformer to be carted shall be arranged by the contractor at his own cost which shall be reimburshed as actual by the department extra to the contractor.
Shifting and Erection of 400KV side and 220 KV Side, all 3 phase bushings for testing of Tan Delta of windings and SFRA. And after testing all the bushing to be Dismantled and proper Packing of 01 No. HV and 01 No. IV bushing for transportation.
Providing services for testing of 240MVA transformer for a. Tan Delta of different windings with variable frequency at motiram adda, Gorakhpur and Submission of report. b. SFRA at motiram adda before loading of the transformer. c. SFRA at 400Kv Orai after Erection of transformer and Submission/Analysis of the report
Dismantling all water all air pipe lines of Emulsifier System of 315 MVA Transformer and its shifting to safe place.
Complete dismantling of accessories of 315 MVA Transformer after, removal of earthing and opening of cable connection, removal of all radiator, conservator tank, oil pipe line, all bushings, fans, Marshaling box etc. Blanking the radiator, oil pipe lines, conservator tank etc. (Nut bolt and blanking plate shall be provided by the department). All necessary labour, Crane, T & P shall be arranged by the contractor at his own cost. And shifting to the storage place.
Shifting of main tank of 315 MVA T/F from Plinth to near safe place distances upto 20 mtr.
Additional shifting of transformer other than work specified at serial No.2.02 (one job defined as shifting of 5 mtr. or part thereof)
Draining out the complete transformer oil from 240MVA Transformer main tank at 400KV Gorakhpur
Create the Vacuum and filling of empty tank of transformer with -500C due point Nitrogen at 400 KV S/S Moti Ram Adda, Gorakhpur and maintain the Nitrogen at .25Kg/cm2 pressure upto 400 KV S/S Orai.
Loading of 240 MVA T/F main tank along with accessories, making the wooden sleeper platform, jacking the T/F tank up to trailer height, placing the rail under T/F tank and shifting up to trailer, removing the rail under T/F tank and proper tightening the main tank with trailer bed with the help of steel rope and turn-buckle at 400KV S/S Moti Ram Adda, Gorakhpur.
Carriage of 240 MVA T/F main tank from 400KV S/S Moti Ram Adda, Gorakhpur to 400KV S/S Orai (Approx. distance 475 Km) On Multi axle Hydraulic trailer
Safe Carriage of 240MVA Transformer accessories, including transformer oil from 400KV S/S Moti Ram Adda, Gorakhpur to 400KV S/S Orai (Approx. distance 475Km).
Unlashing of main tank of 240 MVA Transformer loaded on Trailer, jacking the tank for placingthe rail under the T/F tank and shifting it to wooden platform, Removing the rail under the T/F tank on wooden sleeper, lowering the tank towards ground by slowly and removing the wooden sleeper under the tank and unloading of various Transformer accessories of 240 MVA T/F, like oil filled drums, bushing, conservator tank, cooling fan etc. from Truck/ Trailer at site at 400 KV S/S Orai.
Shifting of main tank of 240 MVA T/F BHEL make from unloading place to plinth upto distance nearly 20mtr.
Dismantling of 198 KV L.A and 245KV Polycon insulators along with structure and its, jumpers, earthing, surge monitor, shifting these to safe place in the Switchyard for storage till erection. And erection of the same after erection of the 240MVA transformer and all other associated works.
Erection of 240MVA T/F Main Tank and providing and filling of dry air of dew point -400C or better, at the time of opening of blanking plates for completion of work. The work shall include connecting pipes as required for measuring dew point values of dry air.
Arrangement of 1No.20-35 Ton capacity mobile crane along with crane operator of work at site, with all cost of material ,consumable such as Diesel, Lubricating oil etc. till the completion of gasket replacement work.
Lifting of Main Tank Body of the transformer , the scope of works involves opening of nuts ,bolts of Rim Gasket of main tank body , jacking & lifting of top cover, Fixing of limiters and pipe stoppers between top cover and winding during replacement of gaskets ,then refitting the top cover after completion of the Replacement of gasket as per details at SL No. 6.05 along with other associated works.
Replacement of Rim Gaskets. The scope of works involves removals of damaged Gaskets ,Cleaning of Rim surface , Fabrication of Rim Gasket out of 20mm thick Rubber Gasket of Kotrika / Torborze / Nu-cork make having temperature bearing capacity around 380°C. and fixing the Gaskets with adhesive at Rim surface.
Replacement of all new gasket of radiators, HV/LV/tertiary/Neutral bushing and all turret, 1’, 3’,4’,6’ dia oil pipe lines, buchholz, PRVs, NRVs, Surge Relay, oil pump, oil flow indicator, Diverter switch gasket, diverter value , air releasing Teflon washer etc. excluding main tank.( Crain shall be arrange by the Contactor).
Overhauling of diverter switch after removing of oil and dirty T/F oil from its chamber filling the fresh centrifuged T/F oil its centrifuged circulation as per norms of T/F.
Complete evacuation of 240MVA Transformer Main Tank and filling of dry air of dew point -500C or better in vacuum and then pressure upto 0.25 kg/Cm2 and again evacuation of the Transformer tank after required time interval (Approx. 12 to 24 Hrs) using vacuum plant. The work shall include connecting pipes of machine as required, measuring dew point value of Dry Air during every cycle(1 Job is defined as complete cycle of evacuation, filling and maintaining of dry air in the T/F main tank), till the required value is achieved under supervision of Supervising Engineer.
Complete erection of 240MVA T/F, including erection of radiator, conservator tank, bushings, their turrets, connecting oil pipe line, cooling fans, motor drive mechanism of tap changer, RTCC panel, oil pump and associated pipe line etc.to complete the job satisfactorily including first filling of oil in tank, radiator, oil pipe lines, conservator tank etc. and attending the oil leakage if any for satisfactory completion of work.
Filling the T/F oil in oil tanker from Drums by centrifuging machine to increase the BDV value, and water content value less than 05 PPM. (Two No. 22KL Tankers shall be provided by the department free of cost.) And Circulation of T/F oil of 240 MVA T/F in transformer tank or oil tanker by connecting centrifuging machine to be provided by the contractor. Taking BDV values of oil and IR values periodically till the required value. The water content value less than 05 PPM is achieved as per direction of the Supervising Engineer.
Create the vacuum inside the transformer tank & stand at 24Hrs. filling the oil step by step in 240 MVA T/F
Fresh earthing with 75x10/50x6mm M.S flat 1200mm deep of 240 MVA T/F body at two points and neutral bushing of T/F including painting by green paint in two coats (Flat to be provided by the Department.)
Inter-Connection of 240 MVA transformer with laying of cable and termination in between turrets, WTI, OTI, Buchholz relays, PRV, cooling fans, pumps, OLTC, Marshaling box etc with proper ferruling as per drawing.
Jumpering between 400/220KV different equipments and HV, IV side bushings of 240MVA T/F including associated work to complete the job. (Different connectors, conductor for jumpers and PG clamps etc to be provided by the department)
Installation of Emulsifier System for 240MVA Transformer
Fire water pipe line /support as per IS specification (IS code-1239)as per drawing enclosed .complete with elbow tee, socket reducer etc. with anticorrosive treatment with details as below.
Supply and laying of different size of GI pipe ‘B’ class for fire detection /water pipe line as per specification (IS code-1239) as per drawing enclosed complete with elbow , tee socket, reducer.
Supply and installation of flanges as per IS-1538 of different sizes as per drawing work include proper but welding with pipe & proper packing nd coupling with nut & bolt (1 set =2No. flanges) (in set)
Supply & installation & commissioning of high velocity water spray nozzles flow capacity 3.5kg/Cm2.
Supply & installation & commissioning of Quartzite bulb detectors (QBD) operate at 79 Degree Celcius sensing at rated temp for actuation of the element 10-12 sec.
Modification of mulsifire Pipe line for Exiting 315 MVA transformer to compatibility of 240 MVA transformer including cutting, bending, welding painting, cleaning of QBD/Nozzles and fitting of different type of pipe.
Preeti Enterprises
Perfect Power Transformer Associates
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .