Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
Tender Value
Refer Docs
Closing Date
10 Aug 2021, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC-II ALIGARH
ALIGARH
EDC2A-05/2021-22
2021_DVVNL_590045_3
EDC2A-05/2021-22
Open Tender
Electrical Works
Item Rate
60 days
KHAIR
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
DVVNL AGRA WEBSITE
26 Aug 2021
5 Aug 2021
10 Aug 2021
5 Aug 2021
10 Aug 2021
5 Aug 2021
45 days
Amount
Cartage of following PCC/ST poles Store centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 50 Kms.).
PCC poles 8.5 Mtr.
ST Pole 11 Mtr. Long
Cartage of line material viz Conductor/LT Cable, AB Cable, GI earth wire, Cross Arm, Angle, Channel, Insulator, Clamps & other line material from Store centre or from any other place to the respective site of work through the Kachha Pacca road including the work of its loading & unloading at the respective ends also including the work of dragging etc. and also including the cost of labour, T&P carrier etc. required for proper completion of work. (Dist. 0 to 50 Kms.).
Erection of single support including complete H.T/L.T fittings as per RESPO manual and as per direction of Engineer incharge including the cost of labour, T & P and carrier etc. required for proper completion of work.
PCC poles 8.5 Mtr.
ST Pole 11 Mtr. Long
Erection of double pole on PCC pole/ST pole including the work of complete line as per RESPO norm manual and as per direction of Engineer Incharge including the cost of labour, T & P and carrier etc. required for proper completion of work.
PCC poles 8.5 Mtr/9 Mtr.
Installation & fixing of 11 KV TPMO.
Laying, sagging, stringing, binding and jumpering etc. of new/old line conductor on the newly erected pole as per RESPO manual and as per direction of supervising engineer, including the cost of arrangement of labour, T&P carrier etc. required for proper completion of work.
ACSR Weasal Conductor
Grouting of poles as per RESPO norms including cost of grouting material (cement: sand: brick ballast) size as per RESPO norms. This qty also includes the additional work of old & existing LT line which has to be converted into HT line. Presently the supports of old line do not have grouting.
PCC poles 8.5 Mtr.
ST Pole 11 Mtr. Long
Making the plinth of ST pole 9/11 Mtr.
Chopping of tree branches which are touching to 11 KV/LT lines.
Dismantling and removal of existing conductor/cable/GI Wire from the various area preparing their coils and then stacking in the respective JE’s (Store) as per direction of Supervising Engineer. It includes the work of cartage, cost of labour, T&P carrier etc. required for proper completion of work.
ACSR Weasal Conductor/ GI Wire
Laying of 4x16/3.50x70 Sq.mm. LT Cable Jumphering from L.T. Site transformer to Line.
Re-sagging of loose HT/LT line conductor as per direction of supervising engineer. It includes the cost of labour T&P carrier etc. required for proper completion of work.
ACSR Weasol Condutor
Carriage and installation of site to Store of following capacity transformer due to damage of PCC poles including the work of its loading & unloading, dragging etc. and also including the cost of labour and T&P etc. required for proper completion of work.
25 KVA T/F
Fixing of earthing rod as per RESPO manual and as per direction of supervising engineer including the cost of labour, T&P etc. Required for proper completion of work.
Erection and grouting of stay set including the work of nozzling etc. as per RESPO manual and also including the cost of arrangement of all grouting material, labour, T&P etc. required for proper completion of work.
Providing and fixing of stay insulator.
Fixing of following accessories:-
11 KV Disc Insulator with fitting.
11 KV Pin Insulator with pin.
11 KV V-type Cross Arm with clamp.
F-Bracket
Fixing of Stone Pad as per RESPO norms.
Fixing of Danger Plate as per RESPO norms.
Fixing of T-OFF Channel as per RESPO norms.
Fixing of Top Channel as per RESPO norms.
Fixing of Dropper Channel as per RESPO norms.
Fabrication of T/F Base Channel/Angle as per RESPO Norms.
Fixing of Holding Clamp as per RESPO norms.
Providing/Fixing of missing Nut bolts and washer
Providing/Fixing of clamps.
Straightening of tilted PCC/ST poles at various places as per direction of JE.
Guarding of 11 KV line by laying two nos. GI wire parallel and fixing of lacings (tilli) at a distance at 2-3 Mtr. as per RESPO manual and also including the cost of arragement of labour, T & P etc. required for proper completion of work.
Safe carriage of Old line material viz. Conductor, G.I. Earth wire, ABC conductor, Cross Arm, Angle, Channel, Insulators, Clamps & other line material from any other place or from site of work to store centre/ J.E. Store of its loading & unloading at the respective ends including the cost of labour, T&P and carrier etc. required for proper completion of work.
SANJAY ELECTRICALS
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .