| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹42.3 LAdmitted-Finance | -12.89% | ₹42.3 L | L1 | Admitted-Finance |
| 2 | L2₹43.1 LAdmitted-Finance | -11.11% | ₹43.1 L | L2 | Admitted-Finance |
| 3 | L3₹46.0 LAdmitted-Finance DELHI ALWAR ROAD SADDIQ NAGAR DISTRICT NUH 122107 | NUH | HARYANA | 122107 | -5.11% | ₹46.0 L | L3 | Admitted-Finance |
Updated dates
Tender Value
₹48.5 L
EMD Value
₹97,000
Closing Date
23 Apr 2026, 6:00 pmClosed
COMMISSIONER
MUNICIPAL COUNCIL SIKAR
Sewer Line Work In Remaining Area Of Housing Board Sector 3 Near Roadways Bus Dipot Sikar
2026_DLB_549909_28
2026-27ENIB01
Open Tender
Civil Works
90 days
MUNICIPAL COUNCIL SIKAR
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
COMMISSIONER, MD RISL
₹97,000
Yes
30 Apr 2026
4 Apr 2026
24 Apr 2026
4 Apr 2026
23 Apr 2026
4 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1Sewer Line Work In Remaining Area Of Housing Board Sector 3 Near Roadways Bus Dipot Sikar | ||||||
| 1.01 | Earth work for Sewer line and Manhole in excavation in foundation, trenches manholes, road side chambers etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level including allowances for any additional excavation beyond the drawings (measurement for payment to be as per standard drawings), re-handling of material/earth to complete the task.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Depth upto 1.5 m
IC to manhole
manhole | - | p.cum | 299 | - | BI01010001010000000000000515BI0100001113 |
| 2.01 | Earth work for Sewer line and Manhole in excavation in foundation, trenches manholes, road side chambers etc. including dressing of sides and ramming of bottoms, including getting out the excavated material, refilling after laying pipe/ foundation and disposal of surplus excavated material at a lead upto 50m suitable site as per direction of Engineer for following depths, below natural ground / Road top level including allowances for any additional excavation beyond the drawings (measurement for payment to be as per standard drawings), re-handling of material/earth to complete the task.
In all types soils/ saturated soil such as moorum, sand, sandy silt, clay, black cotton soil, kankar, etc.
Add extra for overall depth of excavation above 1.5 m and upto 3.0 m over item no 17.1.1.1 | 157.5 | p.cum | 319.9 | ₹50,384.25 | BI01010001010000000000000515BI0100001114 |
| 3.01 | Dismantling of flexible pavements for sewer line and manholes and disposal of dismantled materials up to a lead of 50 metres as directed by Engineer including allowances for any additional dismantling beyond the drawings (measurement for payment to be as per standard drawings), re-handling of material/earth to complete the task.
Bituminous courses | 21 | p.cum | 534 | ₹11,214 | BI01010001010000000000000515BI0100001115 |
| 4.01 | Dismantling of flexible pavements for sewer line and manholes and disposal of dismantled materials up to a lead of 50 metres as directed by Engineer including allowances for any additional dismantling beyond the drawings (measurement for payment to be as per standard drawings), re-handling of material/earth to complete the task.
Granular courses | - | p.cum | 372 | - | BI01010001010000000000000515BI0100001116 |
| 5.01 | Carriage of Materials by mechanical transport including loading, unloading and stacking :: Stone, boulders, gravelly material(Taken Lead UP to 5kms) | 1,160 | p.cum | 239.78 | ₹2,78,144.8 | BI01010001010000000000000515BI0100001117 |
| 6.01 | Providing Barricading for Trenches using 80 - 100 mm dia Wooden Ballies as vertical post, atleast 1.5m above ground level and atleast 30-45 cm below ground level at a spacing of 3 m. Two rows of PVC Tape (preferably red in colour) strip barricading horizontal strip securely tied by the vertical members. Vertical members shall be painted in red and white colour. Rate is inclusive removal and cleaning of site complete in all respect. | 1,000 | p.mtr. | 113.5 | ₹1,13,500 | BI01010001010000000000000515BI0100001118 |
| 7.01 | Providing at site, lowering & laying in trenches, aligning & jointing of PVC-U pipes (SN 8) as per IS 15328 (amended up to date) and as per specifications with rubber rings with socket and spigot joint, (EPDM/SBR) for all depths for pipe length as per drawing and specification including hydraulic field testing (including the cost and conveyance of water to site for testing) and commissioning etc complete as directed by Engineer. Note : E/w to be measured and paid separately. Length of pipe shall be measured in between the outer wall of two manholes / Inspection chambers. Pipe in the manhole/inspection chamber’s wall shall deemed to be included in the item of manhole/inspection chamber shall not be payable.
110 mm Nominal Dia | 400 | p.mtr. | 263.5 | ₹1,05,400 | BI01010001010000000000000515BI0100001119 |
| 8.01 | Providing, lowering, laying, aligning, fixing in position and jointing at all level/ depths full round HDPE DWC (double wall corrugated) pipes of SN8 grade as per IS 16098 (Part 2) amended upto date in trenches in complete including all material, labour, sectional hydro testing (including the cost and conveyance of water to site for testing) and commissioning as per Technical Specifications, drawings and as per direction of Engineer. Note : E/w to be measured and paid separately. Length of pipe shall be measured in between the outer wall of two manholes / Inspection chambers. Pipe in the manhole/inspection chamber’s wall shall deemed to be included in the item of manhole/inspection chamber shall not be payable.
200 mm ID | 1,100 | p.mtr. | 618 | ₹6,79,800 | BI01010001010000000000000515BI0100001120 |
| 9.01 | Providing granular bedding having width = outer dia of pipe (Bc) + 500mm, thickness below pipe = 0.25Bc or 100mm (whichever is higher) and haunching = 0.5Bc, with graded hard crusher broken stone of 100% passing through 20mm sieve, 20 to 50 % passing through 10mm sieve and 100 % retain on 6.3mm sieve, laying in layers of thickness 10/15cm including ramming, consolidation etc complete for all type of pipes of following sizes as per drawing and or as directed by Engineer.
200 mm internal diameter | 600 | p.mtr. | 167 | ₹1,00,200 | BI01010001010000000000000515BI0100001121 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.36 MB
UBN.pdf
Tender Documents • 0.49 MB
Tbid.pdf
Tender Documents • 1.60 MB
Userguide.pdf
Tender Documents • 3.59 MB
BOQ_980468.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid