Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹6.6 LAccepted-Finance | ₹6.6 L | 1 | Accepted-Finance Accept |
| 2 | 2₹7.7 L+₹1.1 L (16.9%)Accepted-Finance | ₹7.7 L+₹1.1 L (16.9%) | 2 | Accepted-Finance Accept |
| 3 | 3₹7.9 L+₹1.3 L (19.5%)Accepted-Finance | ₹7.9 L+₹1.3 L (19.5%) | 3 | Accepted-Finance Accept |
| 4 | 3₹7.9 L+₹1.3 L (19.5%)Accepted-Finance | ₹7.9 L+₹1.3 L (19.5%) | 3 | Accepted-Finance Accept |
| 5 | 4₹8.3 L+₹1.7 L (26.1%)Accepted-Finance MAIN ROAD OBEDULLAHGUNJ RAISEN M P 464993 | OBEDULLAHGUNJ | RAISEN | MADHYA PRADESH | 464993 | ₹8.3 L+₹1.7 L (26.1%) | 4 | Accepted-Finance Accept |
Tender Value
₹12.3 L
EMD Value
₹24,632
Closing Date
30 Jul 2026, 3:00 pmClosed
EE PHED Div Churu
EE PHED Div Churu
Work for Regular operation and maintenance of Asloo and Ghantel Pump House and various size of valves of distribution at RWSS under Disst sub division Churu
2026_PHCJA_576225_1
04/2026-27 EE PHED DIV CHURU
Open Tender
Miscellaneous Works
Percentage
365 days
Churu
TD, Bid Ernest money, TD Fee, RISL Charges, Experience Certificate, Registration and non Historical Stamp all other PQ docs as per TD
2 documents required · 2 mandatory
₹500
EE PHED Div Churu
₹24,632
Yes
3 Aug 2026
21 Jul 2026
31 Jul 2026
21 Jul 2026
30 Jul 2026
21 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Maintenance of pipelines irrespective of size & material which
includes Repairing of Bursts & leakages pollution control, survey & removal of choking, disconnection of illegal connections, Collection & recording minimum 10 nos. residual chlorine samples during daily supply timings, interconnections and all works related to pipeline network in existing distribution /rising main pipe lines of all sizes by digging out suitable size of pit in soft and loose soil/ hard soil including cutting of Black top, WBM & CC top of road of any size at work site. This will also include cutting of pipe ends, fixing of pipe piece with jointing material to make repair leak proof and then refilling of excavated tench / pit /road shall be done properly i.e after a layer of 20 cm with proper watering and ramming in layers. For entire job contractor will use their own T & P. Contractor with his own resources shall arrange de-watering,JCB & Tractor compressor if any and restore
any amenity at his own cost damaged while performing the work in this item. The work includes daily patrolling and repair the leakages within stipulated time and complete maintenance of pipe line network of rising and distribution pipeline network within the scope of work for per km pipe line per month. Minimum labour for a following kms pipelines to be deployed. | - | - | - | - |
| 2 | 1 km to 50 km - one fitter-II & one beldar | 96 | Per KM Per Month | 610 | ₹58,560 |
| 3 | Running expenditure of pump house which includes complete operation of pump motor, maintenance of log-books as directed by Engineer-in-Charge, general up keeping of premises, security arrangements, regular chemical dosing in CWR, cleaning and de silting of SR/CWR/SUMP once every six months, daily valve operation under the campus of pump house and all other works as mentioned in scope of work in TD for per pump house per month.(power supply minimum 16 hrs)(excluding repairing of pumping machinery etc.) | 24 | Each | 36,600 | ₹8,78,400 |
| 4 | Maintenance of centrifugal pump sets and motor/ Monoblock including cost of
rewinding of motor, material components & accessories required to repair pumpsets, starters etc.
of electric panels, deinstallation and re installation of pumpsets complete in all respect for per
Centrifugal pump set with pannel per month. maintenance of histroy sheet as directed by
Engineer-in-charge for centrifugal pump set per month.
Operated load of Centrifugal Pump sets (HP) | - | - | - | - |
| 5 | 6.0 HP to 12.5 HP | 48 | Each | 2,105 | ₹1,01,040 |
| 6 | Maintenance of centrifugal pump sets and motor/ Monoblock including cost of
rewinding of motor, material components & accessories required to repair pumpsets, starters etc.
of electric panels, deinstallation and re installation of pumpsets complete in all respect for per
Centrifugal pump set with pannel per month. maintenance of histroy sheet as directed by
Engineer-in-charge for centrifugal pump set per month.
Operated load of Centrifugal Pump sets (HP) | - | - | - | - |
| 7 | 13.0 HP to 20.0 HP | 36 | Each | 3,307 | ₹1,19,052 |
| 8 | 21 HP to 30.0 HP | 12 | Each | 3,815 | ₹45,780 |
| 9 | Daily/ periodical operations of valves at supply times for specified department per sluice valve per months ( valve key and cap to be arranged by contractor ownself )
80 mm to 300 mm | 24 | per month | 1,200 | ₹28,800 |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.71 MB
Nit04TD.pdf
Tender Documents • 4.59 MB
BOQ_1024521.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .