| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC 1006 MANAK CHOUK MHOW DIST INDORE MADHYA PRADESH453441 | INDORE | INDORE | MADHYA PRADESH | 453441 | ₹1.2 Cr Quoted ₹1.3 Cr | L1 | Accepted-AOC 1st Lowest and reasonable |
| 2 | L2₹1.3 Cr+₹1.7 L (1.39%)Rejected-Finance OFFICE 4 9 SWARG ASHRAM NANAK RAM COLONY PARMANAND CHOWK DELHI 110009 | DELHI | DELHI | DELHI | 110009 | ₹1.3 Cr+₹1.7 L (1.39%) | L2 | Rejected-Finance 2nd Lowest |
| 3 | L3₹1.3 Cr+₹4.3 L (3.41%)Rejected-Finance STREET NO 11 SECTOR NO 04 TILAK NAGAR SAGAR ROAD BIKANER RAJASTHAN 334001 | BIKANER | RAJASTHAN | 334001 | ₹1.3 Cr+₹4.3 L (3.41%) | L3 | Rejected-Finance 3rd Lowest |
| 4 | L4₹1.4 Cr+₹10.2 L (8.10%)Rejected-Finance STREET NO 11 SECTOR NO 04 TILAK NAGAR SAGAR ROAD BIKANER RAJASTHAN 334001 | BIKANER | RAJASTHAN | 334001 | ₹1.4 Cr+₹10.2 L (8.10%) | L4 | Rejected-Finance 4th Lowest |
| 5 | L5₹1.4 Cr+₹12.3 L (9.75%)Rejected-Finance 640 MAIN ROAD BABINA CANTT JHANSI UP 284401 | JHANSI | JHANSI | UP | 284401 | ₹1.4 Cr+₹12.3 L (9.75%) | L5 | Rejected-Finance 5th Lowest |
| Sl No | Description | Qty | Unit | M/s Ravi Traders L5 | M/s Himgiri construction L2 | S R BUILDERS AND SUPPLIERS L6 | Narayandas Phoolchand Mishra Infrastructures Pvt. Ltd. L1 | M/S Umashanker Mishra L7 | SUNAR CONTRACTOR L4 | r.s.jain & sons L3 |
|---|---|---|---|---|---|---|---|---|---|---|
| 1.00 | Dismantling of floor hearth or wall tilling including cement mortar bedding (but not backing) and rubbish of the premisses complete all as specified and directed. | 562 | Sqm | 10 ₹5,620 Lowest | 20 ₹11,240 | 10 ₹5,620 Lowest | 30 ₹16,860 | 10 ₹5,620 Lowest | 22 ₹12,364 | 25 ₹14,050 |
| 2.00 | Dismantling of stone slabs and tiles of any description or thickness in floors, aprons etc laid, bedded and pointed in any mortar complete all as specified and directed | 12 | Xsqm | 100 ₹1,200 Lowest | 100 ₹1,200 Lowest | 100 ₹1,200 Lowest | 100 ₹1,200 Lowest | 100 ₹1,200 Lowest | 188 ₹2,256 | 250 ₹3,000 |
| 3.00 | Demolition of cement concrete (un reinforced) in ground floor and paving n. exc. 15cm thickness (below or above ground level complete all as specified and directed. | 109 | Cum | 100 ₹10,900 Lowest | 175 ₹19,075 | 200 ₹21,800 | 350 ₹38,150 | 190 ₹20,710 | 190 ₹20,710 | 200 ₹21,800 |
| 4.00 | M & L 25mm thick cement concrete type B-1, 1:2:4 (using 20 mm graded aggregate) for levelling course in floors complete all as specified and directed. | 1,246 | Sqm | 90 ₹1,12,140 | 110 ₹1,37,060 | 125 ₹1,55,750 | 50 ₹62,300 Lowest | 125 ₹1,55,750 | 90 ₹1,12,140 | 100 ₹1,24,600 |
| 5.00 | M & L for 75mm thick cement concrete 1:3:6 type C1, with using 20mm graded stone aggregate as in floor/ plinth protection finish the surface even and smooth with using extra cement including filling the expansion joints with bitumen filler / filler boards and necessary form work etc complete all as specified and as directed. | 240 | Sqm | 250 ₹60,000 | 280 ₹67,200 | 300 ₹72,000 | 250 ₹60,000 | 285 ₹68,400 | 200 ₹48,000 Lowest | 250 ₹60,000 |
| 6.00 | M & L for Treating the soil under plinth protection at the rate of 5 litre of emulsion per squre metre of surface area complete all as directed and specified. | 240 | Sqm | 60 ₹14,400 | 120 ₹28,800 | 50 ₹12,000 Lowest | 50 ₹12,000 Lowest | 200 ₹48,000 | 150 ₹36,000 | 75 ₹18,000 |
| 7.00 | M&L for Treatment of soil under existing floors using emulsion @ one ltr per hole 300mm apart including drilling and plugging 12mm dia holes to match the existing floors with cement mortar 1:2 (1 cement : 2 coarse sand) to match the existing floors complete all as specified and directed. | 450 | Sqm | 80 ₹36,000 | 80 ₹36,000 | 100 ₹45,000 | 60 ₹27,000 Lowest | 100 ₹45,000 | 155 ₹69,750 | 75 ₹33,750 |
| 8.00 | Taking down chowkhats or frames not exc 1.5 sqm each without taking off shutter from the frame complete all as specified and directed. | 108 | Each | 10 ₹1,080 Lowest | 65 ₹7,020 | 100 ₹10,800 | 100 ₹10,800 | 100 ₹10,800 | 55 ₹5,940 | 50 ₹5,400 |
| 9.00 | Taking down chowkhats or frame exc 1.5 sqm but not exc 4 sqm with shutter (without taking off shutter frome the frame ) complete all as specified and directed. | 180 | Each | 10 ₹1,800 Lowest | 75 ₹13,500 | 100 ₹18,000 | 150 ₹27,000 | 120 ₹21,600 | 55 ₹9,900 | 50 ₹9,000 |
| 10.00 | S & F 125 x 60 mm size Pressed steel frames for doors with one or more rebates including necessary fixing lugs, hinges, lock strike plate,hold fast includ etc,complete all as specified and directed. | 125 | RM | 800 ₹1,00,000 | 680 ₹85,000 | 580 ₹72,500 | 650 ₹81,250 | 700 ₹87,500 | 600 ₹75,000 | 475 ₹59,375 Lowest |
Tender Value
₹1.4 Cr
EMD Value
₹2.2 L
Closing Date
16 May 2026, 6:00 pmClosed
CWE MHOW
HQ CWE MHOW, MHOW CANTT, MHOW -453441
SPECIAL REPAIR TO BLDG NO SM 88 SM 89 AND SM 201 UNDER GE MIS MHOW
2026_MES_762224_1
CWE/MHOW/02(T) OF 2026-27
Open Tender
Civil Works
Item Rate
180 days
HQ CWE MHOW
Please refer Tender docs
8 documents required · 8 mandatory
₹1,000
GE (M) Inf School Mhow
₹2.2 L
15 Sept 2026
25 Apr 2026
18 May 2026
25 Apr 2026
16 May 2026
9 May 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling of floor hearth or wall tilling including cement mortar bedding (but not backing) and rubbish of the premisses complete all as specified and directed. | 562 | Sqm | - | - |
| 2 | Dismantling of stone slabs and tiles of any description or thickness in floors, aprons etc laid, bedded and pointed in any mortar complete all as specified and directed | 12 | Xsqm | - | - |
| 3 | Demolition of cement concrete (un reinforced) in ground floor and paving n. exc. 15cm thickness (below or above ground level complete all as specified and directed. | 109 | Cum | - | - |
| 4 | M & L 25mm thick cement concrete type B-1, 1:2:4 (using 20 mm graded aggregate) for levelling course in floors complete all as specified and directed. | 1,246 | Sqm | - | - |
| 5 | M & L for 75mm thick cement concrete 1:3:6 type C1, with using 20mm graded stone aggregate as in floor/ plinth protection finish the surface even and smooth with using extra cement including filling the expansion joints with bitumen filler / filler boards and necessary form work etc complete all as specified and as directed. | 240 | Sqm | - | - |
| 6 | M & L for Treating the soil under plinth protection at the rate of 5 litre of emulsion per squre metre of surface area complete all as directed and specified. | 240 | Sqm | - | - |
| 7 | M&L for Treatment of soil under existing floors using emulsion @ one ltr per hole 300mm apart including drilling and plugging 12mm dia holes to match the existing floors with cement mortar 1:2 (1 cement : 2 coarse sand) to match the existing floors complete all as specified and directed. | 450 | Sqm | - | - |
| 8 | Taking down chowkhats or frames not exc 1.5 sqm each without taking off shutter from the frame complete all as specified and directed. | 108 | Each | - | - |
| 9 | Taking down chowkhats or frame exc 1.5 sqm but not exc 4 sqm with shutter (without taking off shutter frome the frame ) complete all as specified and directed. | 180 | Each | - | - |
| 10 | S & F 125 x 60 mm size Pressed steel frames for doors with one or more rebates including necessary fixing lugs, hinges, lock strike plate,hold fast includ etc,complete all as specified and directed. | 125 | RM | - | - |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.41 MB
BOQ_853782.xls
BOQ • 2.09 MB
GenralPagesAndConditions02T.pdf
Tender Documents • 0.64 MB
Credit02T.pdf
Tender Documents • 0.17 MB
PS02T.pdf
Tender Documents • 0.77 MB
SpecialCondition02T.pdf
Tender Documents • 0.22 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .