| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹7.8 CrAccepted-AOC | ₹7.8 Cr Quoted ₹7.9 Cr | 1 | Accepted-AOC Being qualified in all respect |
| 2 | 2₹9.0 Cr+₹1.1 Cr (13.5%)Rejected-Finance HOUSE NO 953 SECTOR 23 HUDA BHIWANI TEHSIL AND DISTRICT BHIWANI | BHIWANI | BHIWANI | HARYANA | ₹9.0 Cr+₹1.1 Cr (13.5%) | 2 | Rejected-Finance L-2 |
| 3 | 3₹10.0 Cr+₹2.1 Cr (26.8%)Rejected-Finance KARNAL ROAD KAITHAL | ₹10.0 Cr+₹2.1 Cr (26.8%) | 3 | Rejected-Finance L-3 |
Tender Value
₹6.1 Cr
EMD Value
₹12.2 L
Closing Date
12 Nov 2019, 5:00 pmClosed
Director students welfare cum Estate officer LUVAS
2nd floor, Giri Center, CCSHAU campus, LUVAS Hisar
Providing and Laying of Sewerage line Construction of manhole chamber Construction of 1.00 MLD Sewerage Treatment Plant
2019_HRY_106370_1
DSW/RE4/STP/NOV/19
Open Tender
Construction Works
Works
547 days
Hisar
As per DNIT
3 documents required · 3 mandatory
₹20,000
LUVAS
₹12.2 L
29 Mar 2022
29 Oct 2019
13 Nov 2019
29 Oct 2019
12 Nov 2019
29 Oct 2019
Amount
N.S. Item
Design, construction, erection, testing and Commissioning of MPS and following Components:-(i) Panel room of 30 sq. mtr. Covered area and PLC room including toilet block of 20 sq. mtr. covered area with RCC framed structure of brick work vitrified glazed tiles flooring, powder coated aluminum frame of size 100mm x 45mm of 10 gauge for chowkhat, 75mm x 45mm of 10 gauge for door frame, 45mm x 45mm of 10 gauge for window frame with 5mm thick glass AIS/Saint Gobain/ Modi Float. The toilet block shall be with one half staff urinal & one European W/C, one wash hand basin as per approved drawings.ii) RCC inlet chamber, screen chamber, rectangular collecting tank suitable for 1.00 MLD average flow with peak factor of 2.25, landscaping of the campus, providing and installing 3 No. of 48.00m3 / hour, pump at 16 mtr. head each with suitable LT Panel equipped with all safety devices, automatic capacitor bank and submersible cable from LT Panel to pump sets complete in all respects(iii)K-9 D.I. Pipe of suitable dia at MPS including welding and screwing of Flanges. ISI Marked D.I. fittings, Sluice Valves, Non return valves as per requirement even for bye pass arrangement complete in all respects. Pipe from MPS to inlet channel of STP and for bye pass and from chlorination tank to nearby arrangement will be arranged by contractor at his own cost.(iv) 3 Nos. CI Gear Operated Sluice Gate withSS spindle (SS 410) and seats (SS 304) (2 Nos)for Screens and 1 no. for partition of collecting tank) as per design. (v) Supply and installation of 2 Nos. mechanical coarse screens of minimum length 6 meters for 1.00 MLD average flow with peak factor of 2.25. Note: 1. The connecting sewer of same diameter and material of construction, laid at adequate depth between sewers to newly constructed structures is included in scope of work. 2. All the infrastructure except construction of staff quarter, and path ways/ roads required to be executed at site to make the MPS functional is included in the scope of work of lump sum job. 3. All the Pumping Machinery, Panel Board, Level Sensor etc shall be controlled by PLC & SCADA and shall be synchronized with the PLC panels at MPS & STP site through broadband internet facility. 1. The size and quantities of all the above components will be as per approved Structural/ Hydraulic/ Mechanical/ Electrical Design to be approved by Department before actual execution of work.
SEWAGE TREATMENT PLANT “Design, construction, erection, testing & commissioning of 1.00 MLD capacity Sewage Treatment Plant based on Sequential Batch Reactor (SBR) Technology complete in all respect including disposal of treated effluent through DI Pipe Rising main by Pumping, mechanical fine screen. Landscaping, MCC Panel Room & all other contingent Electrical, Mechanical, Piping & Instrumentation work. With PLC & SCADA Arrangement for STP & MPS along with Synchronizing it with each other including furniture & laboratory equipments as per detail given in the bid document:- (i) 2 No. High Mast of 9 mtr GI Octagonal pole of 4 mm thickness (T=100 mm, B=200mm, Base Plate = 320 x 320 x 20 mm), Window at 500 mm from Base Plate with 4 No. LED energy efficient lamps on each pole. (ii) Supply and installation 2 Nos. fine Screens of minimum length of 6 meters for 1.00 MLD average flow with peak factor of 2.25 than 500 kg) at STP site. (iii) Providing and installing 2 No. centrifuges (1Working + 1 Stand bye) including centrifuge feed pump, all fittings, instrumentations, electric panel board etc. as per design complete in all respect including packing dry sludge in 20 Kg. bag and supplying the same to market Kisan Sewa Kendra or as directed by Engineer-in-charge within the lead as pointed at clause 4.4.5 of the NIT.
CCTV CAMERAS Providing and Installing 5 CCTV Cameras 3 Cameras for STP and 2 Cameras for MPS) complete as per satisfaction of the Engineer– in- Charge, within 96 hours of signing the Agreement along with 90 days recording (DVR), 32 inch LED Screen, 16 Channel DVR at STP Site and 8 Channel DVR at MPS Site with connectors, cables, poles and power supply with online real-time output facility. The cameras at both the sites i.e. MPS and STP shall be synchronized at STP site. Cameras: i) At STP & MPS Site- 1 No. PTZ speed dome 360 degree 50X zoom camera, 3 No. 12mm lens size, 1 Nos. 3.6mm lens size. Make: - Sony/ Canon/Panasonic/ Samsung. CCTV Cameras should be installed and commissioned before starting execution of work.
TRANSFORMER, D.G. SET & FENCED ENCLOSURES Design, Supply & Erection of 1No. copper wound Transformer of 100 KVA on load tap changer or suitable capacity on higher side (at STP) of standard make outdoor type, VCB Panel, G.O. Switch, H.T. Metering Panels, APFC Panels along with for each Transformer, 11KV Substation, entire cable network from G.O. Switch to H.T. Metering equipment and from H.T. Metering to Transformer Main to L.T. Panel, Earthing, safety equipment and any other contingent thereto complete in all respect as per DNIT and getting it passed from Chief Electrical Officer.
Design, Supply & Erection of 1 Nos. DG Set of 135 KVA or suitable capacity on higher side (at STP) capacity each with Acoustic Canopy, AMF Panel and Copper Earthling of suitable rate with change over switch & synchronizing panel complete as per DNIT.
Construction of HT / LT Panel room, PLC room, Centrifuge house, blower room and Lab cum office building including doors, windows & fittings with toilet block including all Sanitary fittings etc. as per drawings attached in DNIT at MPS & STP site covered area with RCC framed structure of brick work vitrified glazed tiles flooring, powder coated aluminium frame of size 100mm x 45mm of 10 gauge for chowkhat, 75mm x 45mm of 10 gauge for door frame, 45mm x 45mm of 10 gauge for window frame with 5mm thick glass AIS/Saint Gobain/ Modi Float Covered Area (600 sqm).
Providing, lowering, laying, cutting & jointing of DWC pipe as described in IS code including the cost of jointing material as well as carriage, loading, unloading, stacking, handling, rehandling etc. complete in all respects to the satisfaction to the EIC, with hydraulic testing of sewer line including cost of water and equipment required for testing as per specification, drawing and direction of Engineer-in-Charge.200 mm dia
250 mm dia
300 mm dia
Providing laying, jointing, cutting & testing of HDPE pipe 400 mm i/d, PE 100, PN 6 & all other works as per IS: Code 14333 : 1996 as amended upto date and as required at site complete in all respect 400 mm i/d
Operation and maintenance of Structures, Pumping machinery and rising main, Sewerage line & Sewerage Treatment Plant. For operation and maintenance Structures, Pumping machinery, rising main, Sewerage line & Sewerage Treatment Plant as illustrated in the scope of work for 6 year including 1 year defect liability period after 3 month trial run period.Operation & Maintenance for 12 months during defect liability period after trail run of 3 months and Five years thereafterOperation and Maintenance of during the 2nd year Mtc. of 1st year
Operation and Maintenance of during the 3rd year Mtc. of 2nd year
Operation and Maintenance of during the 4th year Mtc. of 3rd year
Operation and Maintenance of during the 5th year Mtc. of 4th year
Operation and Maintenance of during the 6th year Mtc. of 5th year
Vinod Kumar Singal Contractor
MAHA LAXMI CONSTRUCTION COMPANY
MAHA LAXMI CONSTRUCTION COMPANY
GOYAT TRADING COMPANY
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .