Tender Value
₹87.8 L
EMD Value
₹1.8 L
Closing Date
19 Mar 2026, 2:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Revenue
Above/Below/Par
OA/3
16 conditions · 4 needing a document upload
Financial Eligibility Criteria: Advance Correction Slip No. 1) Ref: 2022/ce- i/ct/gcc-2022/policy dated- 14.07.2022) A. Para 10.2., Part I of GCC shall be read as under: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover under: Financial Eligibility Criteria: Advance Correction Slip No. 1) Ref: 2022/ce-i/ct/gcc-2022/policy dated- 14.07.2022) A. Para 10.2., Part I of GCC shall be read as under: The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover under: The tenderers shall submit requisite information as per Annexure-XIV (as per tender document & NIT), along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Similar nature of work :Any Civil engineering work comprising of operation and treatment of any type of sewerage treatment plant/effluent treatment plant/Water treatment plant
16 conditions · 4 needing a document upload
A . Documents to be uploaded only in the website by the Tenderer Following Annexures duly filled and signed are to be uploaded online only prior to Closing of Tender. Original copy of all the documents to be submitted to office within 7 days whenever demanded by the Railway. Annexures are available at Upload/View Document menu in Home Page of IREPS portal for works tender. 1. The details of the works completed by the tenderer during the last Seven years to be filled in Annexure-I. 2. The details of Plants and Machinery with the tenderer to be filled in Annexure- II. 3. Details of Personnel and Organization of the Tenderer to be filled in Annexure-III. 4. Details of Works presently on hand of the Tenderer to be filled in Annexure- IV. 5. The details regarding Association of Railway Officer s with the tenderer to be filled in Annexure- V. 6. List of the Arbitration cases of the Tenderer during last Five years to be filled in Annexure-VI. 7. List of the Court cases of the Tenderer during last Five years to be filled in Annexure- VII. 8. NEFT MANDATE FORM. All Payments to the agency including the refund of the Earnest Money of the unsuccessful bidder preferably will be remitted through NEFT. The Tenderer is required to submit Bank details and A/C No. etc. in Annexure-VIII. 9.Format for Certificate to be uploaded by Tenderer Along with the tender documents Annexure-IX and IX-A (As per GCC-2022 Annexure-V and V-A). 10. GST COMPLAINT INVOICE Annexure-X 11. LETTER OF CREDIT Annexure-XI, 12. Bid Capacity Declaration Annexure-XII.13. Bid Security declaration Annexure-XIII and 14. Annual Contractual Turnover Data Declaration Annexure-XIV (As per GCC-2022 Annexure-VI-B).
B . T h e tender offer complete in a l l respect and with all documents is t o b e submitted online by e-tendering process through the website www.ireps.gov.in before the closing time/date of this tender as mentioned in the NIT (Notice Inviting Tender). Tenderer can revise the bids any number of times till the closing time/date of the tender. No manual offers shall be accepted.
Demand for the Financial Criteria, Association of Railway Officers, List of Arbitration cases, Court cases and Mandate for NEFT are to be uploaded with a scanned copy duly filled in and signed as per annexure no. IV, V, VI, VII, VIII respectively. These Annexures are available in View Document menu at Home page and is downloadable. The details of the uploaded documents should be produced whenever demanded for verification on written request at any point of time of the tender and contract within 7 days.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Operation and maintenance of 3.2 MLD Water Treatment Plant for 03 years at Azimganj station under ADEN/AZ
283_2025-26
283_2025-26
Open
Works - General
36 Months
Howrah, West Bengal
₹0
₹1.8 L
19 Mar 2026
25 Feb 2026
5 Mar 2026
31 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| — | — | — | 87,77,028.08 | ||
| — | 1096.00 | — | — | ||
| Operation and maintenance of pump at intake point | — | — | — | 12,97,006.4 | |
| — | 1096.00 | — | — | ||
| Operation, maintenance and repairing of valve at Reservoir | — | — | — | 12,97,006.4 | |
| — | 1096.00 | — | — | ||
| Operation, maintenance and repairing of Filter Plant | — | — | — | 12,97,006.4 | |
| — | 1096.00 | — | — | ||
| Repairing of Filter Plant, Clarifier, Floculator etc | — | — | — | 12,97,006.4 | |
| — | 1096.00 | — | — | ||
| Operation and maintenance of valve including filling of overhead tank and supply of water at Coaching watering Line, East Quarter colony/AZ, West Quarter colony/AZ, AZ station all 1 to 6 platform, Running Room/AZ, All service building at AZ Station and various offices at AZ i.e. SSE(TRD)/AZ office, RPF barrack/AZ, GRP office/AZ, SSE/Signal/AZ office, SSE(Telecom )/AZ office, ADEN/AZ office etc. | — | — | — | 9,16,694.4 | |
| — | 10000.00 | — | — | ||
| Supply of lime to the site of work for operation and maintenance of water treatment plant. The rates includes transportation, loading,unloading with all labour, taxes, inspection cost of materials if required & other incidental charges etc | — | — | — | 51,000 | |
| — | 10000.00 | — | — | ||
| "Supply of ferric allum to the site of work for opeartion and maintance of water treatment plant. The rates includes transportation, loading, unloading with all labour, taxes, inspection cost of materials if required & other incidental charges etc. " | — | — | — | 77,200 | |
| — | 231000.00 | — | — | ||
| Supply of sodium Hypochlorite solution (NaOCL) to the site of work for operation& maintenance of water treatment plant. Theincludes transportation, loading, rates unloading with all labour, taxes, inspection of materials if required& other incidental. | — | — | — | 18,82,650 | |
| — | 36.00 | — | — | ||
| Supply of consumable item like gear oil, wheel bearing grease, mobile, wash cotton, bleaching powder, phenyl, waste cotton, emerypaper, bamboo basket etc | — | — | — | 1,46,966.76 | |
| — | 10000.00 | — | — | ||
| Labour and hire charges of machineries for underground & OH tank cleaning operation by submiersible water pump to drainout excess water, removal of slugee by suction process by using machine, cleaning of walls, ceiling and floor by high jet machine rubbing allwalls by rotary jet machineand cleaning the corners by plain jet machine, removal of deposited sludge by vacum suction machine after doingsame, done by degradable, anti- bacterial, non toxic agent lime H202 of volume 8.48% finally treatment of UV radiator to all walls and floor forat least 5 minutes. The work shall be complete in all respects. The rate shall be included of all tackles, tools & plants, labour and consumbalematerials including transportation charges and removal of all of job (Cleaning to be done every six months apart) | — | — | — | 800 | |
| — | 6.00 | — | — | ||
| The testing of Raw water sample from the Govt. engineering college/university to findout the dosages of Alum, lime and liquiedchlorine to remove the turbidity maintain PH value disinfection and respectively. The testing will be done on the basis of raw water sample takentwice throughout the year(in dry season season). Note: Here set means per set test | — | — | — | 1,10,020.8 | |
| — | 4.00 | — | — | ||
| Repairing and supplying, fitting fixing spare parts/ equipment for automatic dosing and lime dosing pumps and setting rightcondition with contractors materials, skilled & unskilled labour etc. complete as per direction of Engineer- In-Charge | — | — | — | 86,167.88 | |
| — | 6.00 | — | — | ||
| For overhauling and re- commissioning the filter bed, unloading of whole filter media i.e. gravel, sand and mud from the shell ofPressure filter, inside cleaning up of the wall and painting with anticorrosive bituminous paint. Supply of new full charge of various grade media,repairing of headers lateral pipe line, loading of charged media inside of the shell and commissioning of the plant, within the schedule tine limitas per the direction of Engineer In charge at site. | — | — | — | 2,64,868.62 | |
| — | 1.00 | — | — | ||
| Overhauling and re- commissioning of compressor including supplying fitting fixing piston ring and other new parts which isrequired during overhauling functioning position | — | — | — | 5,093.62 | |
| — | 20.00 | — | — | ||
| Repairing of existing all sizes sluice valves and non-return valves including changing of brass spindle and brass gutka at fillterhouse and belur Intake pump house as per instruction of Engineer In-charge | — | — | — | 47,540.4 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
2ndcorrectionslip.pdf
ATTACHMENT
GCCACS14.07.2022-compressed.pdf
ATTACHMENT
CheckList_3.pdf
ATTACHMENT
JPOSTCables_1.pdf
ATTACHMENT
Annexure-X2.pdf
ATTACHMENT
NewAnnexure-IX-merged.pdf
ATTACHMENT
Annexure-XII_.pdf
ATTACHMENT
ColouredFinal_GCC_April-22_pdf_27.04.22_1.pdf
ATTACHMENT
LetterregardingrecommendedlistofBrands_makeofmaterialsdated03.09.2025.pdf
ATTACHMENT
Updatedtenderdocument_151.pdf
ATTACHMENT
Annexure-XI_11_2.pdf
ATTACHMENT
Annexure-XIV_1.pdf
ATTACHMENT
Annexure-IIIIII_3.pdf
ATTACHMENT
Annexure-IVVVIVIIVIII_2.pdf
ATTACHMENT
Annexure-XIII_1.pdf
ATTACHMENT
specialconditionwater_1.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .