Tender Value
₹24.2 L
EMD Value
₹48,414
Closing Date
15 Jul 2024, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Commandant 32nd Bn SSB Dobhi Gaya
Office of the Commandant 32nd Bn SSB Dobhi Gaya
construction of SPT Jawan barrack at 32nd Bn SSB Dobhi Gaya Bihar
2024_SSB_810029_1
32nd Bn/SSB/Dobhi/Gaya/LWE/2024/06
Open Tender
Construction Works
Works
120 days
32nd Bn SSB Dobhi Gaya
Please refer tender documents
2 documents required · 2 mandatory
₹0
₹48,414
Dobhi Gaya
16 Jul 2024
5 Jun 2024
16 Jul 2024
6 Jun 2024
15 Jul 2024
11 Jun 2024
7 Jun 2024 - 8 Jun 2024
10 Jun 2024
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.1 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. | 18.99 | cum | 260.3 | ₹4,943.1 |
| 1.2 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lif. | 12.51 | cum | 196 | ₹2,451.96 |
| 1.3 | Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift. | 40.32 | cum | 700.5 | ₹28,244.16 |
| 1.4 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 10.75 | cum | 2,123.75 | ₹22,830.31 |
| 1.5 | Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared. | 210 | sqm | 17.6 | ₹3,696 |
| 1.6 | Providing and laying in position excluding cement concrete of level: specified grade the cost of centering and shuttering - All work up to plinth 1:5:10 (1 cement : 5 coarse sand (zone-Ill) derived from natural sources : 10 graded stone aggregate 40 mm nominal size derived from natural sources) | 13.37 | cum | 6,518.6 | ₹87,145.86 |
| 1.7 | Providing and laying damp-proof course 50 mm thick with cement concrete 1:2:4 (1 cement: 2 coarse sand (zone-Ill) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources). | 16.2 | sqm | 495.75 | ₹8,031.15 |
| 1.8 | Making plinth protection 50 mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zone-Ill) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) over 75 mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth. | 32.71 | sqm | 749.3 | ₹24,509.6 |
| 1.9 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand (zone-Ill) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 3.72 | cum | 8,583.4 | ₹31,930.25 |
| 2 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement: 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 3.03 | cum | 10,852.95 | ₹32,884.44 |
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.17 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.50 MB
Tendernotice_1.pdf
Tender Document • 0.50 MB
NITdocument.pdf
Tender Document • 14.59 MB
corrigendum.pdf
Tender Document • 0.49 MB
BOQ_851291.xls
BOQ • 0.33 MB
NITdocument.pdf
Tender Documents • 14.59 MB
BOQ_851291.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .