Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Admitted-PreQual/Technical | Admitted-PreQual/Technical |
| 2 | Admitted-PreQual/Technical | Admitted-PreQual/Technical |
| 3 | Admitted-PreQual/Technical 275 PRATAP NAGAR CHORAHA MURLIPURA JAIPUR JAIPUR RAJASTHAN INDIA 302039 | JAIPUR | RAJASTHAN | 302039 | Admitted-PreQual/Technical |
Tender Value
₹4.5 Cr
EMD Value
₹9.0 L
Closing Date
15 May 2026, 4:00 pmClosed
SE(Contracts-I), RVPN, Jaipur
SE(Contracts-I), RVPN, Jaipur
ETC of 132 KV 3 Phase SC Transmission Line at Deedwana Traction Substation to Proposed 132 KV GSS Sanwasa line on labour Contract Basis (Under Railway Deposit work) (Approx. 18Km)
2026_RRVPN_551738_1
CONT-I/2025-26/BN-9018002538
Open Tender
Electrical Works
Percentage
240 days
Deedwana to Sanwasa
Please refer Tender documents.
11 documents required · 11 mandatory
₹5,900
As per bid specification
₹9.0 L
SE(Contracts-I), RVPN, Jaipur
8 May 2026
16 Apr 2026
15 May 2026
16 Apr 2026
15 May 2026
27 Apr 2026
22 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | DETAIL SURVEY AS PER TENTATIVE ROUTE INCLUDES THE FOLLOWING MAJOR ACTIVITIES
Pegging of line route , providing of survey pillar at an interval of 3-4 Km line route with required jungle clearance for survey, profile preparation of approved route on graph sheet and marking of offset on either side of line , marking of side clearance for hills, sand dunes etc., as per specification and tower scheduling. | - | KM | - | - |
| 2 | CHECK SURVEY AS PER APPROVED ROUTE OF LINE WHICH INCLUDES: -
Rechecking of the line route as per approved profile, tower centre marking, pit marking, bisection of angle tower as per required at site. | - | KM | - | - |
| 3 | Excavation:- Excavation excluding back filling, including shoring, shuttering, dewatering, etc. upto the required depth as per foundation specification/drawings. | - | - | - | - |
| 4 | (i) Any soil,soft rock other than hard rock | - | CUM | - | - |
| 5 | (ii) Hard rock (with blasting subject to permission or with out permission ) | - | CUM | - | - |
| 6 | SETTING OF TEMPLATE & STUB/ANCHOR BOLT:-
(A) Setting of template & stub/ anchor bolt & removal after concreting, excluding cost of excavation and concreting but including back filling with excavated/ borrowed earth (with lead & lift) in layers with ramming andwatering as per specification. | - | - | - | - |
| 7 | (i) Towers including extension upto 9 Meters | - | MT | - | - |
| 8 | Concreting:-
Providing and laying cement concrete for all types of foundation as per latest ISS:456 including cement, sand, stone aggregate 20mm nominal size, water etc., preparing surfaces, shuttering, mixing, placing, ramming, curing, finishing as per specification and drawings. | - | - | - | - |
| 9 | (i) 1:4:8 | - | CUM | - | - |
| 10 | (ii) 1:3:6 Mix | - | CUM | - | - |
stage.html
html • 0.02 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.76 MB
BOQ_983376.xls
BOQ • 0.27 MB
Commercial_bid_doc_Sanwasa_Deedwana_TSSline_under_BN_9018002538.pdf
Tender Documents • 4.93 MB
Corrigendum1_date_extension_sanwasaline_BN9018002538.pdf
PDF • 0.37 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .