| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹25.0 LAccepted-AOC | 1 | Accepted-AOC L1 BIDDER | |
| 2 | 2₹25.1 L+₹6,200 (0.25%)Rejected-AOC | 2 | Rejected-AOC L2 BIDDER | |
| 3 | 3₹25.2 L+₹20,200 (0.81%)Rejected-AOC C O BICHITRA NATH NIKASHI PO NIKASHI PS MUSHALPUR BAKSA ASSAM PIN 781372 | NIKASHI | BAKSA | ASSAM | 781372 | 3 | Rejected-AOC L3 BIDDER |
| Sl No | Description | Qty | Unit | CHANAKYA NATH L3 | KHANIN DAS L2 | BINOD DAS L1 |
|---|---|---|---|---|---|---|
| 1.01 | 11.1 Excavation for Structure Earthwork in excavation for structures as per drawing and technical specifications clause 305.1 including setting out costruction of shoring and barcing removal of stups and other deleterious material and disposal upto a lead of 50 m dressing of sides and bottom and backfilling in trenchs with exzavated Ordinary soil | 1 | Nos | 9,500 ₹9,500 Lowest | 9,500 ₹9,500 Lowest | 9,500 ₹9,500 Lowest |
| 1.02 | Brick work in C.M 1:5 mix including all labour charges etc complete | 5 | Nos | 1,775 ₹8,875 Lowest | 1,775 ₹8,875 Lowest | 1,775 ₹8,875 Lowest |
| 1.03 | Brick work in C.M 1:5 mix including all labour 111charges etc complete Brick work in C.M 1:5 mix including all labour 1charges etc complete | 10 | mm | 20,500 ₹2,05,000 Lowest | 20,500 ₹2,05,000 Lowest | 20,500 ₹2,05,000 Lowest |
| 1.04 | Plastering in C.M 1:5-12 mm thick with including cost and conveyance of all materials and including all labour charges etc complete | 85 | km | 7,559 ₹6,42,515 Lowest | 7,559 ₹6,42,515 Lowest | 7,559 ₹6,42,515 Lowest |
| 1.05 | Plastering in C.M 1:5-12 mm thick with including cost and conveyance of all materials and in | 95 | KK | 7,850.09 ₹7,45,758.55 Lowest | 7,850.09 ₹7,45,758.55 Lowest | 7,850.09 ₹7,45,758.55 Lowest |
| 1.06 | Brick work in C.M 1:5 mix including all labour 1charges etc complete Brick work in C.M 1:5 mix including all labour 1charges etc complete | 100 | Nos | 8,076.2 ₹8,07,620 Lowest | 8,076.2 ₹8,07,620 Lowest | 8,076.2 ₹8,07,620 Lowest |
| 2.00Laying and Jointing PVC Pipe. Heading | ||||||
| 2.01 | Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using | 5 | Nos | 2,980.15 ₹14,900.75 Lowest | 2,980.15 ₹14,900.75 Lowest | 2,980.15 ₹14,900.75 Lowest |
| 2.02 | Brick work in C.M 1:5 mix using 2nd class ground moulded chamber burnt bricks with including cost | 33 | Nos | 1,500.9 ₹49,529.7 Lowest | 1,500.9 ₹49,529.7 Lowest | 1,500.9 ₹49,529.7 Lowest |
| 3.00 | Construction of chamber for 100mm sluices valve | 2 | Nos | 12,000 ₹24,000 | 5,000 ₹10,000 | 1,900 ₹3,800 Lowest |
Tender Value
₹25 L
EMD Value
₹50,000
Closing Date
1 Sept 2026, 2:30 pmClosed
BDO,Jalah Development Block
BDO JALAH DEVELOPMENT BLOCK,JALAH
Const.of RCC Box Culvert on the road from Andres Basumatary to Binod Brahma house near Dane Basumatary house at Koklabari (Active Code-128494698 under)15th FC (Untied Grant) for the year 2025-26 during 2026-27
2026_BoTC_53411_1
JDB/15FC/E/13/PtIII/26-27/8702
Open Tender
Civil Works
Item Rate
180 days
JALAH BAKSA
Refer to Bid Document
4 documents required · 4 mandatory
₹500
₹50,000
Yes
19 Sept 2026
11 Aug 2026
2 Sept 2026
11 Aug 2026
1 Sept 2026
11 Aug 2026
11 Aug 2026 - 1 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | 11.1 Excavation for Structure Earthwork in excavation for structures as per drawing and technical specifications clause 305.1 including setting out costruction of shoring and barcing removal of stups and other deleterious material and disposal upto a lead of 50 m dressing of sides and bottom and backfilling in trenchs with exzavated Ordinary soil | - | Nos | 1.25 | - |
| 1.02 | Brick work in C.M 1:5 mix including all labour charges etc complete | - | Nos | - | - |
| 1.03 | Brick work in C.M 1:5 mix including all labour 111charges etc complete Brick work in C.M 1:5 mix including all labour 1charges etc complete | - | mm | 100 | - |
| 1.04 | Plastering in C.M 1:5-12 mm thick with including cost and conveyance of all materials and including all labour charges etc complete | - | km | 53 | - |
| 1.05 | Plastering in C.M 1:5-12 mm thick with including cost and conveyance of all materials and in | - | KK | 10 | - |
| 1.06 | Brick work in C.M 1:5 mix including all labour 1charges etc complete Brick work in C.M 1:5 mix including all labour 1charges etc complete | - | Nos | 11 | - |
| 2Laying and Jointing PVC Pipe. Heading | |||||
| 2.01 | Plain Cement Concrete 1:4:8 (one cement four fine aggregates and eight coarse aggregates) using | - | Nos | 10 | - |
| 2.02 | Brick work in C.M 1:5 mix using 2nd class ground moulded chamber burnt bricks with including cost | - | Nos | 22 | - |
| 3Construction of chamber for 100mm sluices valve | |||||
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.07 MB
SBD.pdf
Tender Documents • 3.18 MB
FOB.pdf
Additional Documents • 0.45 MB
BOQ_84092.xls
BOQ • 0.34 MB
CORRIGENDUM.pdf
PDF • 0.01 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .