Loading…
Loading…
Tender Value
₹1.4 Cr
EMD Value
₹2.7 L
Closing Date
1 Jun 2026, 3:30 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
SR DEE/G
16 conditions · 5 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or V whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual tumover shall be calculated as an average of 'total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual bontractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet
Valid Electrical contractor license as per IE rules 1956, Clause 45.
Valid Electrical Supervisor's License.
The tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or (iii) One similar work costing not less than the amount equal to 60% of advertised value of the tender. Substantially Completed Work means an ongoing work in which payment equal to or more than 90% of the present contract value (excluding the payment made for adjustment of Price variation (PVC), if any) has been made to the contractor in that ongoing contract and no proceedings of termination of contract on Contractor's default has been initiated. The credential certificate in this regard should have been issued not prior to 60 days of date of invitation of present tender.
SIMILAR NATURE OF WORK : (As per CESE/KKK's note no. EL/112/0 dated 16.9.2025): "Execution of any HT or LT electrical Work"
27 conditions · 2 needing a document upload
Following Annexures duly filled and signed are to be uploaded online prior to Closing of Tender. Original copy of all the documents to be submitted to office within 7 days whenever demanded by the Railway. Annexures are available at Upload/View Document menu in Home Page of IREPS portal for works tender. 1. The details of the works completed by the tenderer during the last three years to be filled in Annexure-I. 2. The details of Plants and Machinery with the tenderer to be filled in Annexure- II. 3. Details of Personnel and Organization of the Tenderer to be filled in Annexure- III. 4. Details of Works presently on hand of the Tenderer to be filled in Annexure- IV. 5. The details regarding Association of Railway Officer(s) with the tenderer to be filled in Annexure-V. 6. List of the Arbitration cases of the Tenderer during last Five years to be filled in Annexure-VI. 7. List of the Court cases of the Tenderer during last Five years to be filled in Annexure- VII. 8. NEFT MANDATE FORM. All Payments to the agency (including the refund of the Earnest Money of the unsuccessful bidder preferably) will be remitted through NEFT. The Tenderer is required to submit Bank details and A/C No. etc. in Annexure-VIII. 9. Documents related to Credentials as per eligibility criteria: (For tender value above Rs. 50 Lakh). 10. Format (Declaration of tenderer) to be uploaded by tenderer as per "Document Verification Certificate", available in home page, view document. 11. Tenderer shall exercise an Option in writing in favour of taking payment due against the tender through 'Letter of Credit' arrangement. 12. All necessary papers in support of eligibility criteria. 13. Special condition mandatory updation of Labour data "Annexure-C". 14. Contractor should upload Electrical contractor license as per IE rules 1956, clause 45. 15.Contractor should upload Electric supervisor license or Electric supervisor's certificate of competency along with tender offer.
Demand for the Financial Criteria, Association of Railway Officers, List of Arbitration cases, Court cases and Mandate for NEFT are to be uploaded with a scanned copy duly filled in and signed as per annexure no. IV, V, VI, VII, VIII respectively. These Annexures are available in View Document menu at Home page and is downloadable. The details of the uploaded documents should be produced whenever demanded for verification on written request at any point of time of the tender and contract within 7 days
This tender complies with public procurement policy (Make in India) order 2017, dated 15.6.2017 issued by department of industrial promotion & policy , Ministry of commerce, circulated vide Rly. Board's L/no. 2015/RS(G)/779/5 dated 03.8.2017 and 27/12/2017. The definition & calculation of content in accordance with the make in India policy as approved by PCEE is 50% of minimum local content(MLC).
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
i) Electrical work in c/w "Construction of additional rooms at Running Room Malda." ii) Electrical work in c/w " Construction of new crew lobby building and Renovation/augmentation of existing running room of MLDT."
EL-MLDT-E-TENDER-429
EL-MLDT-E-TENDER-429
Open
Works - General
6 Months
Maldah, West Bengal
₹0
₹2.7 L
1 Jun 2026
8 May 2026
18 May 2026
130 items across 1 schedule
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Supply, installation, testing & commissioning of 500 KVA Outdoor type transformer as per - IS 1180 (Part 1): 2014 or latest Conductor (Winding) material -copper Minimum BEE Star Rating/Energy efficiency level-3 | Set | 1.00 | 10,23,317.75 | 10,23,317.75 |
| 2 | Provision of Heavy flooring of size 16 feet x 16 feet x 2 feet with boundary wall for transformer placement ( Size as per site, total volumn of work remain same) | Numbers | 1.00 | 2,13,913.33 | 2,13,913.33 |
| 3 | Supply, installation & termination of Heat Shrinkable 11 Kv outdoor type cable end termination kit suitable for 3 core XLPE HT cable up to 95 sq. mm 11 Kv grade | Set | 2.00 | 8,900.8 | 17,801.6 |
| 4 | "Erection of the Rail pole 2no for 'H' pole structureof suitable length(Apprx. 9 Mtrs. long) complete with foundation of size 6 ft x 2.5 ft x 2.5 ft depth including transportation of rail pole from different location to proposed site as per IS 1239(Part-1):1990 including supply, fixing, testing and commissionig of follwing items as follows. 1) 11 Kv ,400 A., 50 Hz 3-phase vertically mounted Gang Operated Switch complete with down rod, isolator & other accessory with proper earthing as per site requirements-01 set 2) Supply, fixing, testing and commissioning of lighting arrester ( 9KV-5KV) ( A set of 3 pcs) with all other accessories suitable for 11 KV HT feeder-1set ( Rail pole to be supplied by Rly.)" | Set | 1.00 | 18,833.62 | 18,833.62 |
| 5 | Scraping, Cleaning & painting of Rail/tubular pole along with cross arm bracket by anti- corrosive red oxide & double coat of alluminium paint & finally black paints up to 1.5 Mtr. above ground level. | Numbers | 2.00 | 150.83 | 301.66 |
| 6 | Supply, fixing & testing of Guy rod assembly of size 5/8 inch X 6' ft. long complete with anchor plate and guy rod of suitable length of size 7/10 SWG stranded GI wire straining insulator etc. including foundation of anchor plate as per IE standard. | Each | 4.00 | 625.61 | 2,502.44 |
| 7 | Supply & fixing of cross arm bracket made of M.S. angle of size 65 mm x 65 mm x 6 mm of length 6.5 ft long with 3 Nos. of 11 Kv pin insulator including supply of all necessary clamps, nuts & bolts etc. & painting. | Each | 6.00 | 1,960.17 | 11,761.02 |
| 8 | Supply & fixing of ISI branded M.S. channel of size 75 mm x 40 mm x 6 mm of length 3.5 Mtrs. Long including fabrication and binding for Double pole structure & allied accessories as per site requirement. | Each | 6.00 | 1,800.83 | 10,804.98 |
| 9 | Supply & fixing of ISI branded M.S. angle of size 65 mm x 65 mm x 6 mm of length 3.5 Mtrs. Long including fabrication and binding for Double pole structure & allied accessories as per site requirement. | Set | 6.00 | 1,376.53 | 8,259.18 |
| 10 | Supply, fixing, testing and commissioning of 11 KV Disc insulator completer with hardware materials. | Set | 6.00 | 380.73 | 2,284.38 |
| 11 | supply, fixing of 1.1KV LT E - PVC/XLPE/HS.KITS-STRAIGHT THROUGH JOINT kit 16-120 sq mm | Set | 4.00 | 1,268.7 | 5,074.8 |
| 12 | supply and fixing of 1.1KV LT E - PVC/XLPE/HS.KITS-STRAIGHT THROUGH JOINT kit 150-240 sq mm | Set | 4.00 | 1,546.28 | 6,185.12 |
| 13 | Laying of LT cable through the HDPE pipe 50- 63 mm Diameter (PE 100, PN-6) as per IS 4984 or Latest for Platform surface cable laying of min 1 feet depth for cable laying including supply of HDPE pipe and LT XLPE 4C x 25 sq mm cable (C2-FR-LSH) | Metre | 400.00 | 436.48 | 1,74,592 |
| 14 | Laying of LT cable through the HDPE pipe 50- 63 mm Diameter (PE-100,PN-6) as per IS 4984 or Latest for underground cable laying of min 1 meter depth including supply of HDPE piper LT XLPE 4C x 25 sq mm cable (C2-FR-LSH) for 25 sq mm cable | Metre | 200.00 | 375.88 | 75,176 |
| 15 | Cable trenching, laying through underground as per IS-1255, 1983 or latest.including supply of LT XLPE 4C x 25 sq mm cable (C2- FR-LSH) | Metre | 300.00 | 413.94 | 1,24,182 |
| 16 | Cable trenching, laying through underground as per IS-1255, 1983 or latest.including supply of LT XLPE 4C x 25 sq mm cable (C2- FR-LSH) | Metre | 200.00 | 216.11 | 43,222 |
| 17 | Supply of floor mounted LT distribution Feeder pillar 4-way size 36''x30''x20'' made by 50mmx50mmx6mm angle covered with inside & outside anticorrosive painted with MS sheet of 14 SWG(2mm thick) on RCC basement. (300A) | Set | 2.00 | 6,667.52 | 13,335.04 |
| 18 | Laying of minimum 75 mm dia HDPEpipe (PE- 100, PN-6) or as per site byMicro - tunneling method under theroad, footpath, rail track etc. As perrequired depth to laying and inserting LT4 core cable 70 sq mm cable throughHDPE pipes including supply of HDPEpipe.(cable will be supplied by Railway). | Metre | 200.00 | 758.88 | 1,51,776 |
| 19 | Butt welded joint for micro tunneling work with laying of 75 mm dia HDPE pipes (one joint for every 6 mtrs length) | Metre | 32.00 | 224.09 | 7,170.88 |
| 20 | Laying of LT cable through the HDPE pipe 90 mm Diameter PE 100, PN-6) as per IS 4984 or Latest for underground cable laying of min 1 meter depth including supply of HDPE pipe (Cable will be supplied by Railway) For cable 70-120 sq mm cable | Metre | 400.00 | 241.73 | 96,692 |
| 21 | Cable trenching, laying as per IS-1255, 1983 or latest. | Metre | 500.00 | 252.94 | 1,26,470 |
| 22 | Cable laying through pole/wall/floor as per site requirement as per IS-1255, 1983 or latest. | Metre | 100.00 | 39.4 | 3,940 |
| 23 | Design,Supply, Lifting, ,Erection, Installation,Testing and Commissioningof Outdoor Units of VRF system with Air- conditioner suitable for operation at ambient temp.upto 56C-(Cap- Split to minimum4 units, each unit having minimum capacity 8HP or as p e r per requirement mentioned by site incharge) (Detailed sepecification-A) Unit- "Per Unit" should be read as "per/HP" | Per Unit | 84.00 | 23,989.58 | 20,15,124.72 |
| 24 | Supply, Installation, Testing & Commissioning of wall mounted High wall units,230v / 1ph / 50 Hz,complete with all acessoriess minimum 1.5 TR capacity | Set | 24.00 | 28,224 | 6,77,376 |
| 25 | Supply & erection ofRefrigerant (R410a / R- 32)charge to the outdoor unitand connected pipesbetween outdoor unit andAHU as per siterequirement. | Kg | 140.00 | 960 | 1,34,400 |
| 26 | Supply installation of Interconnecting refrigerant pipe copper piping work with thickness of (19mm/13 mm thick)closed cell elastomeric class-O nitrile rubber tubular insulation between each set of indoor & outdoor units &specifications, all piping inside the room shall be properly supported with MS hanger / angle etc. as required size 25.4 mm with 19 mm thick insulation. [RM =Running Meter] | RM | 20.00 | 1,492.7 | 29,854 |
| 27 | Supply installation of Interconnecting refrigerant pipe copper piping work with thickness of (19mm/13 mm thick)closed cell elastomeric class-O nitrile rubber tubular insulation between each set of indoor & outdoor units &specifications, all piping inside the room shall be properly supported with MS hanger / angle etc. as required size 19.1 mm with 19 mm thick insulation. [RM =Running Meter] | RM | 150.00 | 576.96 | 86,544 |
| 28 | Supply installation of Interconnecting refrigerant pipe copper piping work with thickness of (19mm/13 mm thick)closed cell elastomeric class-O nitrile rubber tubular insulation between each set of indoor & outdoor units &specifications, all piping inside the room shall be properly supported with MS hanger / angle etc. as required size 15.9 mm with 13 mm thick insulation. [RM =Running Meter] | RM | 70.00 | 526.08 | 36,825.6 |
| 29 | Supply installation of Interconnecting refrigerant pipe copper piping work with thickness of (19mm/13 mm thick)closed cell elastomeric class-O nitrile rubber tubular insulation between each set of indoor & outdoor units &specifications, all piping inside the room shall be properly supported with MS hanger / angle etc. as required size 12.7 mm with 13 mm thick insulation. [RM =Running Meter] | RM | 100.00 | 379.2 | 37,920 |
| 30 | Supply installation of Interconnecting refrigerant pipe copper piping work with thickness of (19mm/13 mm thick)closed cell elastomeric class-O nitrile rubber tubular insulation between each set of indoor & outdoor units &specifications, all piping inside the room shall be properly supported with MS hanger / angle etc. as required size 9.5 mm with 13 mm thick insulation. [RM =Running Meter] | RM | 100.00 | 286.06 | 28,606 |
| 31 | Supply and erection of Y-Joints/T-Joints/Ref- net separation refrigeration pipe joints and header shall be in the appropriate orientation to enable correct distribution of refrigerant for IDU as per requirement at site. | Numbers | 24.00 | 4,777.12 | 1,14,650.88 |
| 32 | Cable tray: Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray(Galvanisation thicknessnot less than 50 microns)with perforation not morethan 17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I.suspenders including G.I.bolts & nuts, etc. as required. (300 mm width X50 mm depth X thick 1.6 mm). | RM | 150.00 | 969.6 | 1,45,440 |
| 33 | Cable tray: Supplying and installing following size of perforated Hot Dipped Galvanised Iron cable tray(Galvanisation thicknessnot less than 50 microns)with perforation not morethan 17.5%, in convenient sections, joined with connectors, suspended from the ceiling with G.I.suspenders including G.I.bolts & nuts, etc. as required. (150 mm width X50 mm depth X thick 1.6 mm). | RM | 150.00 | 969.6 | 1,45,440 |
| 34 | Supply, erection and commisioning of GI sheet thickness 18 SWG for covering of top of cable tray including supply of scrow, clamp etc as per site. | Square Foot | 820.00 | 306.8 | 2,51,576 |
| 35 | Drain Piping: i) Supply and fixing of heavy duty rigid 25mm dia PVC piping complete with fittings,supports as per AC unit manufacture'r STD. & specifications and duly insulated with 6mm thickclosed cell nitrile rubber insulation as required a tsite & as relevant IS | RM | 120.00 | 242.63 | 29,115.6 |
| 36 | Drain Piping: ii) Supply andfixing of heavy duty rigid 32mm dia PVC piping complete with fittings,supports as per AC unit manufacture'r STD. & specifications and duly insulated with 6mm thickclosed cell nitrile rubber insulation as required at site & as relevant IS. | RM | 140.00 | 376 | 52,640 |
| 37 | Supply, laying , wiring and commissioning of 2 Core 1.5 sq mm PVC insulated Shielded Screened and multi-stranded Copper Cable suitable sizeof PVC conduit pipe with 1sq. mm for control cum transmission along with looping between indoor & outdoor VRF system as per direction by site engineerin-charge. | RM | 160.00 | 180.69 | 28,910.4 |
| 38 | "MS FRAME FOR OUTDOOR UNITS Supply, Fabrication and Installation of MS frame using channels/angle iron sections as required for mounting of air cooled remote condensers and air cooled condensing units for VRF outdoor units. " | Kg | 300.00 | 88.85 | 26,655 |
| 39 | Supply, Installation, testing & commissioning of copper/ aluminium base PCB of multi-layer construction, and house microcontrollers, relays, sensors for compressor/fan control,managing power (IPM for inverter), and communicating across the system of Indoor and outdoor for Hitachi make VRF unit. (Above 20 HP) | Set | 4.00 | 1,35,700 | 5,42,800 |
| 40 | Supply, Installation, testing & commissioning of copper/ aluminium base PCB of multi-layer construction, and house microcontrollers, relays, sensors for compressor/fan control,managing power (IPM for inverter), and communicating across the system of Indoor and outdoor for Hitachi make VRF unit. (up to 20HP) | Set | 4.00 | 90,804 | 3,63,216 |
| 41 | SITC of liquid line solinoide valve along with all accessories in the connection with refrigerant line for Outdoor isolation | Set | 10.00 | 17,464 | 1,74,640 |
| 42 | SITC of manually operated on-line valve in refrigerant line along with all accessories | Set | 10.00 | 4,602 | 46,020 |
| 43 | "Supply, fixing and connection of Timer unit for AC outdoor unit Consisting of below materials with CRCA enclosure & complete wiring- 1) MCB 63A 4P -02 set 2) Contactor 63A 4P -2NO 3) Digital Time Switch-01 set 4)2Way Center Off Change over Switch 25A- 01set" | Set | 5.00 | 22,158 | 1,10,790 |
| 44 | "Supply, installation, testing and commissioning of outdoor type TTA Panel , floor mounted, per IEC 61439-1 &2 or as per following specification 1)Copper Busbar rating 500Amps - 4 Nos (RYB-N)-1set 2.) 400A, 4P, 50KA Microprocessor type type MCCB (Ics=100%Icu) with LSIG protection 02 nos with spare (Incoming) a) 125A, 4P, 50KA Microprocessor type type MCCB (Ics=100%Icu) with LSIG protection 02 nos (Out going with spare) b) 100A, 4P, 50KA Microprocessor type type MCCB (Ics=100%Icu) with LSIG protection 02 nos (Out going) b) 63A, 4P, 50KA Microprocessor type type MCCB (Ics=100%Icu) with LSIG protection 04 nos (Out going) C) Digital Timerfor with 63A, AC3 duty power contactor- 2 set b) LCD Display, panel mounted multi- function Energy meter (for V, I, Frequency, Power Factor, Power & energy RS485 compatible)- 1 set f) LED Indication Lamp (RYB), ON/Off Indication, Push Button in each feeder -1 set g) Earthing Terminal-02 set (spreader terminals to be provided in each MCCB)" | Set | 1.00 | 6,63,295.11 | 6,63,295.11 |
| 45 | Wiring of sub-main line 2.5 sq mm Phase & neutral (2 Nos copper wire) with ECC of 1no. 1.5 sq.mm , PVC insulated single core, M/Strand copper wire as per General specification of IE rule | Metre | 385.00 | 119.97 | 46,188.45 |
| 46 | Wiring of sub-main line 4 sq mm Phase & neutral (2 Nos copper wire) with ECC of 1no. 2.5 sq.mm. , PVC insulated single core, M/Strand copper wire as per General specification of IE rule | Metre | 600.00 | 152.21 | 91,326 |
| 47 | Wiring of sub-main line 6 sq mm Phase & neutral (2 nos copper wire) with ECC of 1no. 2.9 sq.mm (minimum) , PVC insulated single core, M/Strand copper wire as per General specification of IE rule | Metre | 400.00 | 160.11 | 64,044 |
| 48 | Wiring of Main line 3 Phase & neutral (4 wire) copper conductor of size 10 mm sq with ECC as per General specification of IE rule | Metre | 100.00 | 561.34 | 56,134 |
| 49 | Extra cost for concealed of Main/sub main line1.5/4/ 6 sq mm | Metre | 1485.00 | 43.97 | 65,295.45 |
| 50 | Wiring of light /fan/exhaust/wall fan point (modular) | Numbers | 360.00 | 501.99 | 1,80,716.4 |
| 51 | Wiring of 2 way light /fan point | Numbers | 24.00 | 403.76 | 9,690.24 |
| 52 | Extra cost for concealed wiring for light /fan/exhaust/wall fan point | Numbers | 384.00 | 80.85 | 31,046.4 |
| 53 | Supply , fixing and connection of 6A plug socket-01 nos Switch -6A -01 nos with board and wire connection.(modular) | Numbers | 40.00 | 332.67 | 13,306.8 |
| 54 | Supply , fixing and connection of 6/16A plug socket-01 nos Switch -20A -01 nos with board with wire connection.(modular) | Numbers | 20.00 | 545.22 | 10,904.4 |
| 55 | Extra cost for concealed of 6A/6-16A plug point | Numbers | 60.00 | 41.86 | 2,511.6 |
| 56 | supply and fixing of Door Bell- Battery Operated Wired Door Bell including supply of battery | Set | 2.00 | 441.16 | 882.32 |
| 57 | Supply , fixing & connection of LED 9W lamp with suitable angular batten holder with metal ring . | Numbers | 20.00 | 134.3 | 2,686 |
| 58 | Supply & fixing of LED tube light fitting complete set 20W (Aluminum housing)Lumen 120Lm/watt | Numbers | 160.00 | 352.02 | 56,323.2 |
| 59 | Supply, replacement/new provision and fixing of BLDC energy efficient (5 star rated) ceiling fan 1200 mm sweep wattage-max 35W with air delivery:-min 230 cu mtr/min (with remote) | Numbers | 50.00 | 3,078.93 | 1,53,946.5 |
| 60 | Supply, fixing and connection of Exhaust Fan of 300 mm. | Numbers | 10.00 | 1,869.23 | 18,692.3 |
| 61 | "Supply and fixing of wall light fittings for reading LED of 3W | Numbers | 50.00 | 1,863.43 | 93,171.5 |
| 62 | Supply , concealed fixing & connection of of LED Skirting light (Foot light) 3 module (including concealed through GI Box 3M) | Numbers | 72.00 | 717.55 | 51,663.6 |
| 63 | "Supply, fixing and connection of 8W Landscape Luminaire -Bollard with PCC foundation ( L-1 ft x B-1 ft x H-10 inch) " | Numbers | 12.00 | 3,790.9 | 45,490.8 |
| 64 | Supply, fixing and connection of Cable Junction Boxes IP 66 with terminals and integrated membranes / metric knockouts for cable entry size (L X B X H) mm -104 x 104 x 70 as per hensel cat no-DK 0404 G or similar including supply of all materials. | Numbers | 12.00 | 869.68 | 10,436.16 |
| 65 | Laying of LT cable/wire through the HDPE pipe 40 mm Diameter (PE 63, PN-6) as per IS 4984 or Latest for underground cable laying of min 1 feet depth including supply of HDPE pipe and cable/wire 3 core 4 sq mm copper cable including all necessary connection with copper lug. | Metre | 300.00 | 359.44 | 1,07,832 |
| 66 | Supply and fixing of G.I. Pipe heavy gauge size 1/1.25 inch dia 2.5 ft. long bended as per site requirement including 2 sets of M.S clamps, nuts & bolts, wiring with flexible PVC Cu. cable through G.I. Pipe. | Set | 10.00 | 165.63 | 1,656.3 |
| 67 | Supply and fixing and connection of LED Street light 70W. System efficasy min- 140Lm/w | Set | 10.00 | 3,714.32 | 37,143.2 |
| 68 | Design, manufacture, display ofwall /hanging / floor mounting typeLED illuminated sign / directionboard as per specification. | Square Foot | 84.00 | 2,223.45 | 1,86,769.8 |
| 69 | Erection and installation of wall /hanging / floor mounting type LEDilluminated sign / direction boardsincluding wiring and all. | Square Foot | 84.00 | 222.32 | 18,674.88 |
| 70 | Supply, fixing and connection of 12W LED recess mounting( downlight).(3000-5600K) | Numbers | 120.00 | 842.91 | 1,01,149.2 |
| 71 | Supply design, fixing and connection of LED Name board | Square Foot | 60.00 | 1,673.78 | 1,00,426.8 |
| 72 | Supply and fixing and testing of occupancy sensor for lighting circuit of chambers etc. | Set | 20.00 | 2,563.99 | 51,279.8 |
| 73 | Supply, fixing, connection of Busbar Chember 4 way of Cap-63A wall mounted including connection of LT cable with proper lugs and and cable gland etc | Set | 4.00 | 5,493.62 | 21,974.48 |
| 74 | Supply, fixing & connection three phase distribution board provision for incomer 8 pole and single phase outgoings 4 way (8+12) modules including followings items 1) FP MCB (63A)-01 nos 2) DP MCB (16A)-6 nos with necessary connection including earth." | Set | 3.00 | 6,360.99 | 19,082.97 |
| 75 | "Supply, Fixing & connection of SPN 6 way (No of module 6+2) MCB sheet steel Distribution Board with metal door i) Inclding supply of 4 nos SP MCB (6-32A) ii) 01 no RCCB 32/40A (100mA)" | Numbers | 12.00 | 4,813.59 | 57,763.08 |
| 76 | Supply, fixing and connection of modular mobile charging board consisting of following. 1) Modular board cover with base plate -8M- 01 nos. 2) Modular Switch 1way 10A-03 nos. 3) 6/10A multi socket -02 nos. 4) Twin USB Charger up to- 2.1A-1M-01 nos. 5)8 Module GL metal board-01 nos | Set | 32.00 | 1,456 | 46,592 |
| 77 | Extra cost for concealed DB/mobile charging board | Numbers | 48.00 | 64.03 | 3,073.44 |
| 78 | Supply, installation , commissioning & testing of earthing as per IS:3043 or latest amendment. | Set | 20.00 | 2,655.47 | 53,109.4 |
| 79 | Supply and laying of GI strip 25 mm X 6 mm or 50 mm X 6 mm for laying from earth pipe to transformer/body/panel board/ switch board earth nutral connection with LT & HT body etc | Kg | 78.70 | 81.57 | 6,419.56 |
| 80 | Supply, Installation, test and commissioning of Water Heater Cap-25 Ltrs | Set | 2.00 | 12,178.23 | 24,356.46 |
| 81 | Supply, fixing & commissioning of MCCB of Cap-160A (36 KA) 4 pole 415V ,50 Hz complete with Enclosure. | Numbers | 2.00 | 15,446.16 | 30,892.32 |
| 82 | Installation & commissioning of Water Cooler on suitable cc foundation including supply of all material and water drainage system with fixing of all materials at site location.(water cooler will be supplied by Rly) | Numbers | 4.00 | 1,819.94 | 7,279.76 |
| 83 | Supply & fixing of Perforated Cable Tray box type with cover Size 300 mm x 75 mm- Hot dip Galvanized. | Metre | 100.00 | 1,220.58 | 1,22,058 |
| 84 | Supply and fixing, Installtion testing and commissioning of Solar water Heating System with Heat Exchanger cap 500 LPD. | Set | 4.00 | 60,923.52 | 2,43,694.08 |
| 85 | Supply and fixing of of 1 " CPVC pipe | Foot | 8.00 | 43.08 | 344.64 |
| 86 | Supply and fixing and fixing of 1 " UPVC pipe | Foot | 680.00 | 31.37 | 21,331.6 |
| 87 | Supply & fixing of 0.75 inch CPVC Brash FTA. | Numbers | 12.00 | 268 | 3,216 |
| 88 | Supply & fixing of 0.75 inch to 0.5 inch CPVC Brash L bow. | Numbers | 12.00 | 91.2 | 1,094.4 |
| 89 | Supply & fixing of 1 nch CPVC Ball Valve. | Numbers | 8.00 | 349.6 | 2,796.8 |
| 90 | Supply & fixing of 1inch CPVC Bush. | Numbers | 8.00 | 33.3 | 266.4 |
| 91 | Supply & fixing of 1 inch x 3/4 inch CPVC to UPVC Bush. | Numbers | 8.00 | 28.5 | 228 |
| 92 | Supply & fixing of 1inch UPVC L Bow. | Numbers | 12.00 | 44 | 528 |
| 93 | Supply & fixing of 1 inch UPVC ( T ). | Numbers | 16.00 | 58.5 | 936 |
| 94 | Supply & fixing of 1 inch UPVC socket. | Numbers | 12.00 | 31.5 | 378 |
| 95 | Supply and fixing of 3/4 " CPVC pipe | Foot | 1210.00 | 33.93 | 41,055.3 |
| 96 | Supply and fixing of 1" CPVC union | Numbers | 6.00 | 218.05 | 1,308.3 |
| 97 | Supply and fixing of 1" CPVC (T) | Numbers | 48.00 | 61.33 | 2,943.84 |
| 98 | Supply and fixing of 1" CPVC socket | Numbers | 44.00 | 34.98 | 1,539.12 |
| 99 | Supply and fixing of 1" CPVC L Bow | Numbers | 48.00 | 44.38 | 2,130.24 |
| 100 | Supply and fixing of 3/4" CPVC (T) | Numbers | 44.00 | 43.08 | 1,895.52 |
| 101 | Supply and fixing of 3/4" CPVC SOCKET | Numbers | 100.00 | 27.98 | 2,798 |
| 102 | Supply and fixing of 3/4" CPVC L Bow | Numbers | 104.00 | 30.28 | 3,149.12 |
| 103 | Supply and fixing of 1/2" STEEL TAP | Numbers | 32.00 | 484.42 | 15,501.44 |
| 104 | Sypply of 1" Brash ball valve | Numbers | 12.00 | 831.74 | 9,980.88 |
| 105 | Supply and fixing of UPVC Ball Valve | Numbers | 12.00 | 417.06 | 5,004.72 |
| 106 | Supply and fixing of 1" UPVC FTA (Brash) | Numbers | 12.00 | 390.4 | 4,684.8 |
| 107 | Supply and fixing of 1" UPVC MTA (Brash) | Numbers | 12.00 | 370.16 | 4,441.92 |
| 108 | Supply and fixing of 1" CPVC Brash FTA | Numbers | 12.00 | 413.02 | 4,956.24 |
| 109 | Supply and fixing of 1" CPVC Brash MTA | Numbers | 12.00 | 392.78 | 4,713.36 |
| 110 | Supply and fixing of 1" UPVC UNION | Numbers | 20.00 | 164.25 | 3,285 |
| 111 | Supply and fixing of 3.4/1/2 CPVC BRASH SOCKET | Numbers | 24.00 | 218.05 | 5,233.2 |
| 112 | Supply and fixing of CPVC GUM 100 grm | Numbers | 12.00 | 324.46 | 3,893.52 |
| 113 | Supply and fixing of UPVC GUM 100 gm | Numbers | 8.00 | 218.05 | 1,744.4 |
| 114 | Supply and fixing of TAFLON Tape | Numbers | 8.00 | 304.23 | 2,433.84 |
| 115 | Supply and fixing of Zink Pest | Numbers | 8.00 | 86.17 | 689.36 |
| 116 | Supply and fixing of CPVC China Hook 3/4" | Numbers | 400.00 | 8.1 | 3,240 |
| 117 | Supply and fixing of CPVC China Hook 1/4" | Numbers | 200.00 | 10.33 | 2,066 |
| 118 | Supply and fixing of CPVC China Hook 1.1/4" | Numbers | 120.00 | 13.07 | 1,568.4 |
| 119 | Syupply of Tank Nipple set | Numbers | 8.00 | 347.91 | 2,783.28 |
| 120 | Supply and fixing of White cement | Kg | 8.00 | 41.18 | 329.44 |
| 121 | Supply and fixing of 1" G.I Socket | Numbers | 8.00 | 33.94 | 271.52 |
| 122 | Supply and fixing of 1" G.I Plug | Numbers | 8.00 | 30.06 | 240.48 |
| 123 | Supply and fixing of 1/2" , 2" G.I Nipple | Numbers | 8.00 | 21.97 | 175.76 |
| 124 | Supply and fixing of Steel Cap | Numbers | 16.00 | 17.08 | 273.28 |
| 125 | Providing and placing on terrace (at all floor levels) polyethylene water storage tank, IS : 12701 marked, with cover and suitable locking arrangement and making necessary holes for inlet, outlet and overflow pipes but without fittings and the base support for tank. | Litre | 2000.00 | 7.27 | 14,540 |
| 126 | Civil work including installation of water tank | Set | 2.00 | 5,504.55 | 11,009.1 |
| 127 | Supply & fixing of GI Net for covering of solar heater | Square Foot | 1250.00 | 38 | 47,500 |
| 128 | Supply & fixing of 1.1/2x1/2 GI Nut bolt.etc. | Kg | 8.00 | 142 | 1,136 |
| 129 | Supply fixing & connection of GI angle of sizes 1.5 Inch x 1.5 Inch x 5 mm, 1.25 Inch x 1.25 Inch x 5mm & GI flat of size 1.0 Inch x 5mm, 1.5 Inch x 5mm. Including welding, RCC for channel fixing (with RCC of size 8inch x 8inch x 12inch for each corner limp, 4 nos.) and AL painting at welded point with fixing for covering of solar water heater as protection from monkey | Kg | 710.00 | 130 | 92,300 |
| 130 | Supply , fixing and connection of 32A Double Pole RCCB 100mA woth enclosure | Set | 4.00 | 2,504.75 | 10,019 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Checklist.pdf
ATTACHMENT
Technicalcompliances.pdf
ATTACHMENT
CommercialCompliances.pdf
ATTACHMENT
Othercompliances.pdf
ATTACHMENT
GCC-2022uptoACS11.pdf
ATTACHMENT
BISLevelamendment.pdf
ATTACHMENT
Transformerspecification.pdf
ATTACHMENT
429SpecificationofWorksAnnexureA.pdf
ATTACHMENT
429OtherTenderConditionsAnnexure-F.pdf Other conditions Annexure F
ATTACHMENT
Deployment of Qualified Engineer
ATTACHMENT
TenderDocuments-2022MLDT.pdf
ATTACHMENT
Mandatorydocumentslist.pdf
ATTACHMENT
BGFormatforBidSecurity.pdf
ATTACHMENT
LetterofcreditformatAnnexure-B.pdf
ATTACHMENT
MandatoryupdationLabourdataAnnexC.pdf Labour Data Annexure C
ATTACHMENT
MandatoryupdationLabourdataAnnexC.pdf
ATTACHMENT
429OtherTenderConditionsAnnexure-F.pdf
ATTACHMENT
Deploymentofqualifiedengineer-Annexure-_E_.pdf
ATTACHMENT
429SpecificationofWorksAnnexureACorr-1.pdf
CORRIGENDUM
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .