| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.9 LAccepted-AOC | L1 | Accepted-AOC Bbeing L1 | |
| 2 | L2₹3.2 L+₹26,925.24 (9.31%)Rejected-Finance | L2 | Rejected-Finance Being L-2 | |
| 3 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical Others-Offline bid documents not submitted as per bid requirements |
Tender Value
Refer Docs
Closing Date
29 Jul 2021, 6:00 pmClosed
Senior Manager Contract and Procurement
Sr Manager (Civil) P and C Division Salal Power Station Jyotipuram, Reasi (J and K) PIN 182312
Construction of balance Boundary wall at Gadal Reasi
2021_NHPC_637471_1
NH/SPS/CD/NIT-10/21-22/214-21
Open Tender
Civil Works
Item Rate
60 days
Salal PS Jyotipuram
7 documents required · 7 mandatory
₹0
Exempted
18 Sept 2021
7 Jul 2021
2 Aug 2021
7 Jul 2021
29 Jul 2021
7 Jul 2021
Amount
Earth work in excavation by mechanical means (hydraulic excavator) in trenches for foundations, drains, pipes, cables etc. (not exceeding 1.5 m in width) and for shafts, wells, cesspits and the like not exceeding 10 sqm on plan, including dressing of sides and ramming of bottoms lift upto 1.5 m, including getting out excavated earth and disposal of surplus excavated earth as directed, within a lead of 50 metres: All Kind of Soil
Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with:1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size)
Random Rubble masonry with hard stone in foundation and plinth including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with: Cement mortar 1:6 (1 Cement : 6 coarse sand)(b) Nallah
Centring and shuttermg including strutting, propping etc. and removal of form for: Foundations, footings, bases of column etc for mass concrete
Providing and laying in position cement concrete of specified grade excluding the cost of centring and shuttering- All work upto plinth level. 1:2:4 (1 cement: 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
karnail singh
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .