| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.3 LAccepted-AOC VERMA COTTAGE BELOW B C S NEW SHIMLA H P | ₹7.3 L | L1 | Accepted-AOC L1 |
| 2 | L2₹8.1 L+₹83,651.76 (11.5%)Rejected-Finance UPPER KANGNA DHAR VERMA COTTAGE BELOW BCS SHIMLA 9 | ₹8.1 L+₹83,651.76 (11.5%) | L2 | Rejected-Finance L2 |
| 3 | L3₹9.0 L+₹1.7 L (24.1%)Rejected-Finance R O VILL CHEOG TEH THEOG DISTT SHIMLA | ₹9.0 L+₹1.7 L (24.1%) | L3 | Rejected-Finance L3 |
| 4 | L4₹9.3 L+₹2.0 L (27.5%)Rejected-Finance | ₹9.3 L+₹2.0 L (27.5%) | L4 | Rejected-Finance L4 |
| 5 | Rejected-Technical | - | - | Rejected-Technical documents not uploaded |
| Sl No | Description | Qty | Unit | ashok kumar verma L2 | SUNEEL CHAUHAN L3 | VINOD VERMA L1 | Devender L4 |
|---|---|---|---|---|---|---|---|
| 1.00 | Excavation in foundation, trenches etc., in earth work in all type of soil such as pick work, jumper work, blasting work Kankar, moorum shingles including decomposed soft and hard rock etc., up to all heights stacking the excavated earth not more 3 meters clear from the edge of excavation and then returning the stacked soil in 15cm. layers, when required into plinth and sides of foundation etc., consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated earth up to including all leads and lifts complete in all respect and as per the direction of Engineer-in-charge. | 108 | cum | 10 ₹1,080 Lowest | 10 ₹1,080 Lowest | 10 ₹1,080 Lowest | 150 ₹16,200 |
| 2.00 | Providing form work with steel plates 3.15mm thick welded with angle iron frame 30x30x5mm so as to give finish including centering, shuttering, strutting and propping etc., with wooden ballies and battens height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal of the same for insitu reinforced concrete and plain concrete work in:- Foundation, footing, basis of columns etc. and mass concrete. Including all leads and lifts complete in all respects and as per direction of Engineer in Charge. | 104.49 | sqm | 74 ₹7,732.26 | 10 ₹1,044.9 Lowest | 150 ₹15,673.5 | 100 ₹10,449 |
| 3.00 | Providing and laying cement concrete 1:5:10 ( 1 cement: 5 sand: 10 graded stone aggregate 40mm nominal size) with 15% plum and curing complete excluding cost form work in retaining walls/Breast walls, the size of plums shall usually be 150mm to 300mm as per H.P.PWD specification.complete. | 146.97 | cum | 5,200 ₹7,64,244 | 6,000 ₹8,81,820 | 4,800 ₹7,05,456 Lowest | 6,000 ₹8,81,820 |
| 4.00 | Stone filling behind R/wall/B/wall | 54 | cum | 600 ₹32,400 | 100 ₹5,400 | 10 ₹540 Lowest | 50 ₹2,700 |
| 5.00 | Providing weep hole of 100 mm dia @1 Sqm Each complete as direction of Engineer-in-charge. | 63 | meter | 65 ₹4,095 | 180 ₹11,340 | 50 ₹3,150 Lowest | 230 ₹14,490 |
Tender Value
₹13.6 L
EMD Value
₹27,200
Closing Date
18 Jun 2026, 11:00 amClosed
AGM office sewerage division US Club Shimla
AGM office sewerage division US Club Shimla
Restoration of Rain Damages Construction of retaining wall below inlet at STP North Disposal
2026_SJPNL_135612_1
SJPNL/sewerage/NIT/583-586
Open Tender
Civil Works
Item Rate
30 days
Shimla
Please refer Tender documents.
8 documents required · 8 mandatory
₹350
₹27,200
30 Jun 2026
3 Jun 2026
18 Jun 2026
3 Jun 2026
18 Jun 2026
3 Jun 2026
3 Jun 2026 - 18 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation, trenches etc., in earth work in all type of soil such as pick work, jumper work, blasting work Kankar, moorum shingles including decomposed soft and hard rock etc., up to all heights stacking the excavated earth not more 3 meters clear from the edge of excavation and then returning the stacked soil in 15cm. layers, when required into plinth and sides of foundation etc., consolidating each deposited layer by ramming and watering and then disposing of all surplus excavated earth up to including all leads and lifts complete in all respect and as per the direction of Engineer-in-charge. | 108 | cum | 506.87 | ₹54,741.96 |
| 2 | Providing form work with steel plates 3.15mm thick welded with angle iron frame 30x30x5mm so as to give finish including centering, shuttering, strutting and propping etc., with wooden ballies and battens height of propping and centring below supporting floor to ceiling not exceeding 4 metres and removal of the same for insitu reinforced concrete and plain concrete work in:- Foundation, footing, basis of columns etc. and mass concrete. Including all leads and lifts complete in all respects and as per direction of Engineer in Charge. | 104.49 | sqm | 506.87 | ₹52,962.85 |
| 3 | Providing and laying cement concrete 1:5:10 ( 1 cement: 5 sand: 10 graded stone aggregate 40mm nominal size) with 15% plum and curing complete excluding cost form work in retaining walls/Breast walls, the size of plums shall usually be 150mm to 300mm as per H.P.PWD specification.complete. | 146.97 | cum | 506.87 | ₹74,494.68 |
| 4 | Stone filling behind R/wall/B/wall | 54 | cum | 506.87 | ₹27,370.98 |
| 5 | Providing weep hole of 100 mm dia @1 Sqm Each complete as direction of Engineer-in-charge. | 63 | meter | 506.87 | ₹31,932.81 |
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.40 MB
Form6.pdf
Tender Documents • 0.60 MB
Form8.pdf
Tender Documents • 1.94 MB
BOQ_200811.xls
BOQ • 0.28 MB
conditions.pdf
Tender Documents • 0.15 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .