| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.6 LAccepted-AOC | L1 | Accepted-AOC Lower Rate | |
| 2 | L2₹6.0 L+₹20,980 (3.60%)Rejected-AOC | L2 | Rejected-AOC Higher Rate | |
| 3 | L3₹6.2 L+₹41,050 (7.04%)Rejected-AOC | L3 | Rejected-AOC Higher Rate |
Tender Value
Refer Docs
EMD Value
₹6,900
Closing Date
30 Oct 2021, 12:00 pmClosed
Superintending Engineer
Electricity Construction Circle, RPH, Kesco, Kanpur
Laying of 33 kV XLPE Cable at 132 kV Krishna Nagar Transmission S/S for energizing 33 kV PAC and 33 kV Sujaatganj under E.U.D.D. Daheli Sujaanpur from Independent Bays
2021_KESCO_627456_1
18/Const./2021-22
Open Tender
Construction Works
Item Wise
180 days
EUDD-Daheli Sujanpur, Kesco, Kanpur
Please refer to tender document
2 documents required · 2 mandatory
₹1,180
Yes
Kesco
₹6,900
3 Jan 2022
5 Oct 2021
30 Oct 2021
5 Oct 2021
30 Oct 2021
5 Oct 2021
Taking out of 33/11 kV XLPE 3x300 Sq.mm cable from drum/complete drum of cable at site of work or store using JCB including carriage
Digging of Trench for laying of cable in different situations in size of 30 cm. wide and 1 to 1.5 meter deep.
In Normal soil
In Kharanja Soil
In Metallic Road
Laying of 33 KV XLPE cable in above digged trench covering with bricks and back filling and proper ramming.
Laying of MS Pipe in digged trench
Laying of Cable in MS Pipe
Making 33/11 kV straight through joint including digging of pit upto 1.1 metre depth and making a proper chamber for straight through joints using bricks, cement, etc.
Making outdoor joints of 11/33 KV XLPE Cable where the cable is being laid.
Mounting of cable box on double pole/cable support structure without Pipe
Mounting of cable box on double pole/cable support structure With Pipe
Chopping of tree branches lying in the route of existing line touching the tree branches to the phase line conductor making fault to the feeder, for 3” to 18” dia or as per requirement of site.
Opening of H.T. Jumpers from the existing 3 Phase 3 Wire H.T. O.H. line for erection work.
Making of H.T. Jumpers from the existing 3 Phase 3 Wire H.T. O.H. line for erection work.
L/C for mounting of Pin Insulator
Taking out already laid cables by exacavation safely without damaging the cables
Digging of new trench for excavated cables
Laying of excavated cable in new trench
Fabrication of following structure with M.S. Channel, M.S. Angle, M.S. Flat etc. in required size and length including cutting, drilling holes, welding and assembling as per drawing.
Cable Support Structure.
Erection and grouting of following structures with 1:4:8 CC 25 mm brick ballast in required size in proper alignment and making plinth of all structure in 1:2:4 CC mix with 20 mm stone grit, 15 Cm ground level to smooth finish and its proper curing including cost of cement.
Cable Support Structure.
Painting of following structure/equipment after rubbing and cleaning with Emery paper, coating with one coat of Red Oxide and two coat of grey enamel ISI marked paint with smooth finish including cost of paint and labour.
Cable Support Structure.
Making of H.T. Section Point
Carriage of all concerning stock material except mentioned above from Kesco. Store to site or vice-versa.
Connecting of newly erected network with Kesco mains including testing, commissioning and energization of the same completely.
Kamadgeri Traders
Goodluck Electricals
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .