Tender Value
₹55.0 L
EMD Value
₹54,960
Closing Date
27 Jul 2026, 6:00 pmDue tomorrow
E.E., R.W. Division-I, Ganjam, Berhampur
O/o the S.E., R.W. Division No.-I, In-front of De-paul School, Engineering School Road, Ganjam, Berhampur, 760010
RD Road To Pallabha With Extension To Bhitirikhola And Phalsa Forest
2026_CERWI_135774_1
OT-12/SERWDG-I/2026-27
National Competitive Bid
Civil Works - Roads
Percentage
60 days
Berhampur
2 documents required · 2 mandatory
₹10,000
₹54,960
Yes
27 Jul 2026
15 Jul 2026
28 Jul 2026
15 Jul 2026
27 Jul 2026
15 Jul 2026
15 Jul 2026 - 20 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing road land in area of light jungle including uprooting rank vagetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of tress cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned upto a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness including watering and cost of labour, cess & all materials etc. complete as per direction of Engineer-In-Charge. | 12,262.5 | sqm | 8.63 | ₹1,05,825.38 |
| 2 | Providing & laying laterite moorum of approved quality from approved quarry & spreading on road surface to required slope & camber including watering & compacting with H.R.R to the required density to required thickness including cost, conveyance taxes, royality, additional charges, DMF 10% & EMF 5% over royalty cess complete as per direction of the Engineer in charge. | 307.58 | cum | 1,396.18 | ₹4,29,437.04 |
| 3 | Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, moorum & sand to fill-up the interstices of coarse aggregate, watering and compacting to the required density including Royalty, Cost of coneyance, DMF (10% over royalty), EMF (5% over royalty) & Addl. Charges as admissible etc complete as per Technical Specification Clause 405 of MoRD by Mechanical means and as per direction of Engineer-In-Charge. (Grading No.-III) | 91.97 | cum | 3,130.23 | ₹2,87,887.25 |
| 4 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.40 kg per sqm on the prepared not primed surfaces & cleaned with Hydraulic broom as per Technical Specification Clause 503 of MoRD. and as per direction of Engineer-In-Charge. (By Mechanical Mean) | 1,226.27 | sqm | 34.37 | ₹42,146.9 |
| 5 | Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.20 kg per sqm on the prepared primed surface & cleaned with Hydraulic broom as per Technical Specification Clause 503 of MoRD. and as per direction of Engineer-In-Charge. (By Mechanical Mean) | 11,092.48 | sqm | 22.87 | ₹2,53,685.02 |
| 6 | Providing and laying semi dense bituminous concrete with batch type hot mix plant using crushed aggregates of speficied grading premixed with bituminous binder of 60/70 penetration grade of bitumen , transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheelede, vibratory and tandem rollers to achieve the desired compaction as per clause 508 of MoSRT&H specification for Road & Bridge works and all other T&P articles including cost, conveyance, royality, additional charges, DMF 10% & EMF 5% over royalty Cess, taxes of chips and bitumen & other required materials etc. complete as per specification and direction of the Engineer in charge. | 307.97 | cum | 13,694.19 | ₹42,17,399.69 |
| 7 | Earth work in excavation of foundation in hard soil with all leads & lifts including dressing the sides & leveling the bed of the foundation to the required width & required depth including shoring shuttering, propping bullah, pilling, dewatering from foundation supplying & working of pumps including hire & running charges of pumps & all machineries required for the work & providing coffer dam if required & stacking the excavated materials away from the working areas with Cess complete as per specification & direction of the Engineer-in-charge. | 21.6 | cum | 282.88 | ₹6,110.21 |
| 8 | Providing & filling good clean river sand of approved quality including watering to complete saturation & ramming complete including cost conveyance, royalty, additional charges, DMF 10% & EMF 5% over royalty Cess & taxes of all materials & cost of all labour & T&P required for the work etc complete as per specification & direction of Engineer-in Charge. | 3.6 | cum | 968.48 | ₹3,486.53 |
| 9 | Providing Plain Cement concrete M-15 in foundation upto a required depth below ground level and upto a required height above ground level/bed level using 40mm down graded hard granite aggregates of approved quality from approved quarry including hoisting, lowering, laying compacting in position in layers to proper slope & level including watering, curing and cost, conveyance, Cess, royality, additional charges, DMF 10% & EMF 5% over royalty taxes of all materials etc. with all labour and T&P required for the work including dewatering, shuttering if necessary complete as per direction of Engineer-in-charge.
In Foundation | 3.6 | cum | 5,288.27 | ₹19,037.77 |
| 9.01 | In substructure | 24 | cum | 5,428.9 | ₹1,30,293.6 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_2.pdf
PDF • 23.41 MB
Tendernotice_1.pdf
PDF • 3.44 MB
BOQ_601471.xls
BOQ • 0.29 MB
COR1.pdf
PDF • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].