Tender Value
₹1.6 Cr
EMD Value
₹3.1 L
Closing Date
12 Jan 2023, 5:00 pmClosed
As Per NIT
As Per NIT
Dismantling Loading on Trucks shifting to designated area unloading and stacking of Electro Mechanical Equipment of Khandong 2x25 MW Power Station
2022_NEEPC_138265_1
NEEPCO KHPS NIT 477 date 14.12.2022
Open Tender
Electrical Works
Works
60 days
As Per NIT
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,360
Yes
As Per NIT
₹3.1 L
Yes
4 Feb 2023
14 Dec 2022
14 Jan 2023
15 Dec 2022
12 Jan 2023
16 Dec 2022
Amount
Dismantling of all the oil and water cooling pipe lines of turbine guide bearing assembly including Top Cover Pressure equiliser pipes etc.
Dismantling of TGB coolers, RTD’s, DTT’s, Guide bearings, retaining sleeve etc.
Dismantling of Shaft sealing arrangement including pipe lines.
Dismantling of adjusting ring, lower/upper cone.
Dismantling of runner cone and runner.
Dismantling of turbine shaft.
Disconnecting of guide vane servomotor from the regulating ring and connected pipelines and removal of the same.
Dismantling of guide vane link mechanism components like lever, link etc. all guide vane bush housings etc.
Removal of guide vanes.
Dismantling of top cover assembly and Pivot ring.
Dismantling of regulating ring.
Disconnecting of MIV from Servomotor, Penstock, Spiral Casing and removal of MIV, Servomotor including control panels and pipe lines.
Dismantling of by pass valve , Air Valve and leakage unit including pipe lines.
Dismantling of EHG.
Dismantling of HMC including pipe lines etc.
Dismantling of OPU system including all and Pressure receiver.
Dismantling of DT dewatering, Drainage system including pipes ,control panels etc.
Dismantling of CO2 system including Cylinders, pipe lines, panels etc.
Any other items required for complete dismantling and removal of all the machineries inside the Power House premises
Shifting of all the dismantled items to designated area (within 500 mtr.) including transportation, loading , unloading and necessary arrangement for the same.
Dismantling of Generator dome, Slip ring, collector casing and top shaft.
Dismantling of all vapour seals & piping etc.
Removal of RTD’s, DTT’s, Thermostats and guide pads of LGB, UGB etc.
Removal of all oil retaining sleeves including pipe lines.
Dismantling CW pipe lines and oil lines of LGB and UGB.
Removal of Generator Air coolers and removal of oil coolers of LGB, UGB etc.
Dismantling/Removal of Rotor.
Dismantling of brake drums & jack system including control panel.
Removal of bottom bracket.
Decoupling of Generator and Turbine shaft and removal of Generator shaft.
Dismantling of Thrust pad, Spring Mattress, Stool including H.P. lub systems.
Dismantling of Stator in 3 segments after removing requisite stator coils & terminals.
Dismantling of Bus duct including Excitation Transformer, UAT, CT, PT, LAVT etc.
Dismantling of neutral terminal and removal of NGT, CT, Resistor isolator etc.
Dismantling / Removal of all Power and Control cables insite the P.H. building.
Any other items required for complete dismantling and removal of all the machineries inside the Power House premises
Shifting of all the dismantled items to the deisgnated area (within 500 mtr.) including transportation, loading , unloading and necessary arrangement for the same.
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .