Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹31.3 CrAccepted-Finance | ₹31.3 Cr | L1 | Accepted-Finance Qualified |
| 2 | L2₹33.6 Cr+₹2.3 Cr (7.46%)Rejected-Finance RATE ACCEPTED BY DEPTT | ₹33.6 Cr+₹2.3 Cr (7.46%) | L2 | Rejected-Finance Disqualified |
| 3 | L3₹35.5 Cr+₹4.2 Cr (13.5%)Rejected-Finance | ₹35.5 Cr+₹4.2 Cr (13.5%) | L3 | Rejected-Finance Disqualified |
Tender Value
₹34.8 Cr
EMD Value
₹17.4 L
Closing Date
27 Jun 2026, 5:30 pmClosed
COMMISSIONER OF UJJAIN MUNICIPAL CORPORATION
CHHATRAPATI SHIVAJI BHAWAN, AGAR ROAD UJJAIN
Construction of EWS residential unit on the land located at Panwasa for displacement of the families residing there for acquisition of Gond Basti residential unit
2026_UAD_496211_2
30/Simhasth Cell/2026
Open Tender
Civil Works - Buildings
Percentage
548 days
the land located at Panwasa
YES PLEASE REFER TENDER DOCUMENT
4 documents required · 4 mandatory
₹50,000
₹17.4 L
Ujjain
17 Jul 2026
13 Jun 2026
29 Jun 2026
13 Jun 2026
27 Jun 2026
22 Jun 2026
18 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation for foundation, trenches for pipes / cables or drains etc. by mechanical means / manual means (exceeding 30cm in depth.) including ramming of bottom, dressing of sides, disposal of excavated earth including of all lift and lead upto 50m.Disposed earth
to be levelled and neatly dressed. | 16,878.63 | - | 151 | ₹25,48,672.38 |
| 2 | Supplying and filling in plinth under floors including, watering, ramming consolidating and dressing complete.
(A) Moorum / Hard Copra | 421.35 | - | 478 | ₹2,01,405.3 |
| 3 | Filling in trenches with available excavated earth in layer not exceeding 20cm in depth consolidating each deposited layer by ramming & watering. | 14,071 | - | 89 | ₹12,52,319 |
| 4 | Supplying and filling in plinth under floors including, watering, ramming consolidating and dressing complete.
(A) Crusher Stone Dust | 421.35 | - | 687 | ₹2,89,467.45 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering All work up to plinth level. Cement concrete grade M-10 (Nominal Mix)with 20 mm maximum size of stone aggregate.
Footing and plinth Beam. | 501 | - | 4,219 | ₹21,13,719 |
| 6 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering All work up to plinth level. Cement concrete grade M-15( Nominal Mix)with 20 mm maximum size of stone aggregate.
Grade slab | 283 | - | 4,755 | ₹13,45,665 |
| 7 | Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding up to floor level including cost of binding wire, wastage and over laps upto 12 mm horizontal / inclined position of reinforcement bars in slab and beams, plinth, chajjas, lintels, upto 4.5m vertical leng th of reinfor cement in wall columns (over laps shall be provided as per requirement of IS: 13920 ; IS456 &SP: 34) etc. complete.Thermo-Mechanically Treated bars. (Fe 500 D or more)
Ground Floor | 2,87,181 | - | 58 | ₹1,66,56,498 |
| 8 | Providing and laying in position machine batched and machine mixed and machine vibrated design mix cement concrete of M-25 grade mixed in aconcrete mixer of not less than 0.2 cum capacity and approporiate weigh batcher using approved mix design, for reinforced cement concrete work inluding pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement. including Admixtures in recommended proportions as per IS 9103 to accelerate, retards etting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge.( A ) Upto Plinth level | 2,676.2 | - | 5,547 | ₹1,48,44,881.4 |
| 9 | Centering and shuttering including strutting, propping stretching etc. complete for and removal of formwork by sheet plate or plywood shuttering for : Foundations, footings, bases of columns, etc. For mass concrete. | 1,998.42 | - | 160 | ₹3,19,747.2 |
| 10 | Lintels, beams, plinth beams, girders, bressumers and cantilevers. | 1,991.4 | - | 270 | ₹5,37,678 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.32 MB
tenderdocument.pdf
Tender Documents • 1.73 MB
NIT.pdf
Other Document • 0.26 MB
BOQ_620948.xls
BOQ • 0.53 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .