Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹7.8 LAdmitted-Finance | +0.00% | ₹7.8 L | L1 | Admitted-Finance |
| 2 | L1₹7.8 LAdmitted-Finance | +0.00% | ₹7.8 L | L1 | Admitted-Finance |
| 3 | L2₹7.8 L+₹3,889.90 (0.50%)Admitted-Finance 115 SUBHAH PURI DAURALA MEERUT UTTAR PRADESH 250221 | MEERUT | UTTAR PRADESH | 250221 | +0.50% | ₹7.8 L+₹3,889.90 (0.50%) | L2 | Admitted-Finance |
Tender Value
₹9.2 L
EMD Value
₹45,901
Closing Date
3 Jun 2026, 12:00 pmClosed
OFFICE NP HARRA
OFFICE NP HARRA
Construction of RCC drain from Babu of house to Budhu Carpenter of house in Ward-09.
2026_DOLBU_1148560_1
075/NPH/2026-27 Date 13/05/2026
Open Tender
Civil Works
Fixed-rate
45 days
OFFICE NP HARRA
3 documents required · 3 mandatory
₹1,083
OFFICE NP HARRA
₹45,901
16 Jun 2026
14 May 2026
3 Jun 2026
14 May 2026
3 Jun 2026
14 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation in soil mixed with kankar,silt& licquid mud with including back filling watering and ramming of excavated earth.including supply of all material,labour and T&P etc.required for proper completion of work,(Chpt-4/252) | 85.22 | Cum | 95 | ₹8,095.9 |
| 2 | Concrete in 1:6:12 with brick ballast of 4cm guage including supply of all material,labour and T&P etc.required for proper completion of work.(Chpt-5/273) | 12.78 | Cum | 2,930 | ₹37,445.4 |
| 3 | Concrete in 1:2:4 with stone ballast of 4cm guage including supply of all material,labour and T&P etc.required for proper completion of work.(Chpt-5/279a) | 8.52 | Cum | 5,650 | ₹48,138 |
| 4 | R.C.C work in 1:1.5:3 with cement,coarse sand and stone gritt of 4cm guage in Raft foundation i/c supply of all material,labour and T&P etc.including all complete of work,(Chpt-5/287a) | 12.78 | Cum | 6,230 | ₹79,619.4 |
| 5 | R.C.C work in 1:1.5:3 with cement,coarse sand and stone gritt of 2cm guage in Rcc wall i/c supply of all material,labour and T&P etc.including all complete of work,(Chpt-5/289) | 30.22 | Cum | 7,670 | ₹2,31,787.4 |
| 6 | R.C.C work in 1:1.5:3 with cement,coarse sand and stone gritt of 2cm guage in RCC Slab i/c supply of all material,labour and T&P etc.including all complete of work,(Chpt-5/284a) | 5.64 | Cum | 7,300 | ₹41,172 |
| 7 | Mild steel or Iron work suc as reinforced including supply of all material,labour and T&P etc.required for proper completion of work,(asper Analysis) | 36.05 | qtl | 7,088 | ₹2,55,522.4 |
| 8 | Dewatering of water by diesel Pumping set | 360 | hrs | 200 | ₹72,000 |
| 9 | Add Sign board | 1 | job | 4,200 | ₹4,200 |
stage.html
html • 0.03 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.35 MB
Tendernotice_2.pdf
PDF • 1.80 MB
BOQ_2149921.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .