| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.5 LAdmitted-Fee/PreQual/Technical/Finance PALLA STREET VENGANTHUR VILUPPURAM | ₹3.5 L | L1 | Admitted-Fee/PreQual/Technical/Finance |
| 2 | L2₹3.6 L+₹6,901.73 (1.97%)Admitted-Fee/PreQual/Technical/Finance | ₹3.6 L+₹6,901.73 (1.97%) | L2 | Admitted-Fee/PreQual/Technical/Finance |
| Sl No | Description | Qty | Unit | MAHA BUILDERS L2 | NAVEEN CONSTRUCTIONS L1 |
|---|---|---|---|---|---|
| 1.00 | Clearing light jungle including all charges etc., complete as per the directed by the departmental officers. | 3,000 | m2 | 6.33 ₹18,990 Lowest | 7 ₹21,000 |
| 2.00 | Painting with first quality emulsion paint two coats over a priming coat including through cleaning, scrapping, removal of dust and including necessary plaster of paris putty works wherever required etc., complete. | 740 | m3 | 145 ₹1,07,299.87 | 120 ₹88,799.89 Lowest |
| 3.00 | Earth work excavation and refilling in all kinds of soil including sand, silt, wet sand under water, black cotton, stiff black cotton, clay, hard stiff clay, hard red earth, murram, stoney earth, gravel and shales etc. excepting all kinds of rock and boulders exceeding 0.014 cum. in volume including rough dressing and dumping the excavated materials away from work site manually within 10m initial lead and 2m initial lift as per the direction of Engineer-in-charge . | 30 | m3 | 186 ₹5,580 Lowest | 200 ₹6,000 |
| 4.00 | Cement concrete 1:4:8 (one cement, four sand and Eight aggregate) using 40mm gauge hand broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted, etc., complete complying with standard specification. | 15 | m3 | 5,295 ₹79,425 | 5,000 ₹75,000 Lowest |
| 5.00 | Plain Cement Concrete 1:2:4 (one cement, two fine aggregates and four coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification | 15 | m3 | 6,266 ₹93,990 Lowest | 6,900 ₹1,03,500 |
| 6.00 | Painting with first quality emulsion paint Two coats over a base coat over a priming coat including through cleaning, scrapping, removal of dust and including necessary plaster of paris putty works wherever required etc., complete. | 167.96 | m3 | 259 ₹43,501.69 Lowest | 280 ₹47,028.86 |
| 7.00 | Painting new iron work for doors, windows, grills, weld mesh sceens etc., two coats over one coat of primer including through cleaning, scrapping, removal of dust and including necessary plaster of paris putty works wherever required etc., complete. | 58 | m3 | 130 ₹7,540.52 Lowest | 150 ₹8,700.6 |
| 8.00 | Supply and fixing of WT Bulk head fitting with guard ( Philips / Bajaj / Crompton / K.lite ) suitable for 11W CFL lamp with CFl(SD83) | 2 | m3 | 821 ₹1,642 | 519 ₹1,038 Lowest |
| 9.00Add GST 18% | |||||
Tender Value
₹5 L
EMD Value
₹5,000
Closing Date
12 Aug 2026, 3:00 pmClosed
The Assistant Commissioner,
North Zone, Coimbatore Corporation, Balasundaram Road,Oppsite Womens Polytechnic
Maintenance and Repair to the Subramaniyampalayam Corporation Middle School in Ward No 15, North Zone
2026_MAWS_690592_35
E2/NorthZone/2026-27
Open Tender
Civil Works
Works
90 days
North Zone, Coimbatore Corporation
As per the tender condition attached
5 documents required · 5 mandatory
₹0
₹5,000
14 Aug 2026
5 Aug 2026
13 Aug 2026
5 Aug 2026
12 Aug 2026
5 Aug 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Clearing light jungle including all charges etc., complete as per the directed by the departmental officers. | 3,000 | m2 | - | - |
| 2 | Painting with first quality emulsion paint two coats over a priming coat including through cleaning, scrapping, removal of dust and including necessary plaster of paris putty works wherever required etc., complete. | 740 | m3 | - | - |
| 3 | Earth work excavation and refilling in all kinds of soil including sand, silt, wet sand under water, black cotton, stiff black cotton, clay, hard stiff clay, hard red earth, murram, stoney earth, gravel and shales etc. excepting all kinds of rock and boulders exceeding 0.014 cum. in volume including rough dressing and dumping the excavated materials away from work site manually within 10m initial lead and 2m initial lift as per the direction of Engineer-in-charge . | 30 | m3 | - | - |
| 4 | Cement concrete 1:4:8 (one cement, four sand and Eight aggregate) using 40mm gauge hand broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted, etc., complete complying with standard specification. | 15 | m3 | - | - |
| 5 | Plain Cement Concrete 1:2:4 (one cement, two fine aggregates and four coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification | 15 | m3 | - | - |
| 6 | Painting with first quality emulsion paint Two coats over a base coat over a priming coat including through cleaning, scrapping, removal of dust and including necessary plaster of paris putty works wherever required etc., complete. | 167.96 | m3 | - | - |
| 7 | Painting new iron work for doors, windows, grills, weld mesh sceens etc., two coats over one coat of primer including through cleaning, scrapping, removal of dust and including necessary plaster of paris putty works wherever required etc., complete. | 58 | m3 | - | - |
| 8 | Supply and fixing of WT Bulk head fitting with guard ( Philips / Bajaj / Crompton / K.lite ) suitable for 11W CFL lamp with CFl(SD83) | 2 | m3 | - | - |
| 9 | Add GST 18% | - | - | - | - |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.39 MB
NITE2-Buildings.pdf
Tender Documents • 0.38 MB
BOQ_830878.xls
BOQ • 0.28 MB
ITBE2.pdf
Additional Documents • 0.05 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .