EXECUTIVE ENGINEER (W/S) , GRWW
OFFICE OF THE EXECUTIVE ENGINEER (WATER SUPPLY) GARDEN REACH WATER WORKS, BIDHANGARH, KOL-66
FABRICATION AND ERECTION OF MS STRUCTURAL WORK WITH MS COVER PLATE OPPOSITE SEB COMPLEX ON TARATALA ROAD WITH OTHER ALLIED WORKS.
2026_KMC_1026959_1
EEWS/KMC/GRWW/26-27/26
Open Tender
MECHANICAL
7 days
OPPOSITE SEB COMPLEX ON TARATALA ROAD.
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹9,900
8 Jun 2026
8 Jun 2026
25 Jun 2026
8 Jun 2026
23 Jun 2026
8 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | I.S.M.C AS PER IS: 2062-2011/LATEST REVISION, MAKE:SAIL/TATA/JINDAL
UPTO 200 X 75 | 1 | KILOGRAM | 60.38 | ₹60.32 | item1 |
| 2 | 5. I.S.M.B AS PER IS: 2062-2011/LATEST REVISION, MAKE:SAIL/TATA/JINDAL
A) UPTO 200 X 100 | 84 | KILOGRAM | 51.73 | ₹4,345.32 | item2 |
| 3 | M.S. PLATE AS PER IS: 2062-2011/LATEST REVISION, MAKE:SAIL/TATA/JINDAL
B) ABOVE 10 MM TO 20 MM THICKNESS | 0.2 | KILOGRAM | 68.6 | ₹13.65 | item3 |
| 4 | M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816-1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814-2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg./m. or 15% of weight for finished structal members weighing less than 22.5 Kg./m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m./2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. I) For structural members of specified sections weighing less than 22.5 Kg/m | 0.44 | MATRIC TON | 59,119 | ₹26,012.36 | item4 |
| 5 | Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc (This item is applicable to new work or old work when the original surface has been exposed by removal of old paint.) | - | SQUARE METER | 29 | - | item4 |
| 6 | Coating of 'Epoxy Resin of thickness not less than 160 micron with a lowviscosity,crystallization-resistant epoxy resin base with a reactive diluents combined with high build epoxy amine adducts as per BS 5493 standard and a polyamide or amido polyamine or any other suitable hardener. It shall react with epoxy resin at normal ambient temperature, suitable for solvent-free coatings as per recommended proportion for use on metal, concrete and wood surface to protect from corrosion as well as damagefrom chemical reaction after making the surface free from dust, oil and moisture etc. all complete as per instruction and to the satisfaction of EIC. [This item will be operated on prior permission from the concerned SE/Dy Chief Engineer] | - | SQUARE METER | 449 | - | item6 |
| 7 | Welding in M.S.structural work with gas or electric: (a) Tack weld | 180 | POINT | 9 | ₹1,620 | item9 |
| 8 | Sub Total | - | - | - | - | - |
| 9 | GST 9% | 1 | Nos | - | - | BI01010001010000000000000515BI0100001170 |
| 10 | GST 9% | 1 | Nos | - | - | BI01010001010000000000000515BI0100001170 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.32 MB
tbid.pdf
Tender Documents • 0.55 MB
OIDDETAILS.pdf
Additional Documents • 0.62 MB
BOQ_2522731.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid