Loading…
Loading…
Tender Value
₹1.8 Cr
EMD Value
₹2.4 L
Closing Date
2 Feb 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
GSU/PRYJ
15 conditions · 3 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
Balance sheet for the 4th previous year (i.e. FY 2021-22 or as applicable for the instance tender) as per para 10.2 of GCC-2022 and para 4.15.2 of the tender document shall be considered in evaluation of financial eligibility criteria only when it is clearly certified in Annex-VI B or a self declared certificate duly signed by chartered accountant stating that the balance sheet of last financial year (i.e. FY 2024-25 or as applicable for the instance tender) has not been audited/yet to be prepared.
67 conditions · 22 needing a document upload
Please submit bank details of the firm / individual/ JV / partnership etc. i.e.Name of the Bank along with Bank Branch Code, Account Number, IFSC Code, PAN Number and other necessary & relevant documents.
Please furnish list of Works on hand indicating Description of Work, Contract Value, Approximate value of balance work yet to be done and Date of award.
Please furnish documents in support of your claim to fulfill the eligibility criteria as mentioned in the tender documents. Each page of the copy of documents / certificates in support of credentials, submitted by the you, shall be self-attested / digitally signed by the you or authorized representative of the your firm. Only those documents which are declared explicitly by you as "documents supporting the claim of qualifying the laid down eligibility criteria", will be considered for evaluating the offer or otherwise available in the offer.
Please furnish statement of deviations from tender conditions, if any.
Requisite documents proving technical eligibility criteria and financial eligibility criteria has been uploaded along with those required as per explanation given in clause 10 of IRGCC-2022 (Works Matter).
Tenderers who is/are not borne on the approved list of the contractors of North Central Railway shall submit along with his/their tender as per clause 11 of IRGCC-2022 (Works Matter), as applicable.
All requisite valid documents regarding constitution of business of the bidding firm should be submitted along with the tender as per clause 14 of IRGCC-2022 (Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, specifically authorizing him/them to sign the tender, submit the tender and further to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such specific person is authorized for above purposes through a provision made in the partnership deed / Memorandum of Understanding / Article of Association /Board resolution, failing which tender shall be summarily rejected. A separate power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, shall be submitted after award of work, specifically authorizing him/them to deal with all other contractual activities subsequent to signing of agreement, if required. Note: A Power of Attorney executed and issued overseas, the document will also have to be legalized by the Indian Embassy and notarized in the jurisdiction where the Power of Attorney is being issued. However, the Power of Attorney provided by Bidders from countries that have signed the Hague Legislation Convention 1961 are not required to be legalized by the Indian Embassy if it carries a conforming Appostille certificate. Reference: para 15 of IRGCC-2022 (Works matter),otherwise their offer will be considered incomplete and shall not be considered.
Joint Venture firms, if applicable in the instant tender, should submit all valid requisite documents and fulfil the stipulations as per clause 17 of IRGCC-2022 (Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
Partnership firms, if bidding for the instant tender, should submit all valid requisite documents and fulfil the stipulations as per clause 18 of IRGCC-2022 (Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
Please submit bank details of the firm / individual/ JV / partnership etc. i.e.Name of the Bank along with Bank Branch Code, Account Number, IFSC Code, PAN Number and other necessary & relevant documents.
Please furnish list of Works on hand indicating Description of Work, Contract Value, Approximate value of balance work yet to be done and Date of award.
Please furnish documents in support of your claim to fulfill the eligibility criteria as mentioned in the tender documents. Each page of the copy of documents / certificates in support of credentials, submitted by the you, shall be self-attested / digitally signed by the you or authorized representative of the your firm. Only those documents which are declared explicitly by you as "documents supporting the claim of qualifying the laid down eligibility criteria", will be considered for evaluating the offer or otherwise available in the offer.
Please furnish statement of deviations from tender conditions, if any.
Requisite documents proving technical eligibility criteria and financial eligibility criteria has been uploaded along with those required as per explanation given in clause 10 of IRGCC-2022 (Works Matter).
Tenderers who is/are not borne on the approved list of the contractors of North Central Railway shall submit along with his/their tender as per clause 11 of IRGCC-2022 (Works Matter), as applicable.
All requisite valid documents regarding constitution of business of the bidding firm should be submitted along with the tender as per clause 14 of IRGCC-2022 (Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
The tenderer whether sole proprietor / a company or a partnership firm / joint venture (JV) / registered society / registered trust / HUF / LLP etc if they want to act through agent or individual partner(s), should submit along with the tender, a copy of power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, specifically authorizing him/them to sign the tender, submit the tender and further to deal with the Tender/ Contract up to the stage of signing the agreement except in case where such specific person is authorized for above purposes through a provision made in the partnership deed / Memorandum of Understanding / Article of Association /Board resolution, failing which tender shall be summarily rejected. A separate power of attorney duly stamped and authenticated by a Notary Public or by Magistrate in favour of the specific person whether he/they be partner(s) of the firm or any other person, shall be submitted after award of work, specifically authorizing him/them to deal with all other contractual activities subsequent to signing of agreement, if required. Note: A Power of Attorney executed and issued overseas, the document will also have to be legalized by the Indian Embassy and notarized in the jurisdiction where the Power of Attorney is being issued. However, the Power of Attorney provided by Bidders from countries that have signed the Hague Legislation Convention 1961 are not required to be legalized by the Indian Embassy if it carries a conforming Appostille certificate. Reference: para 15 of IRGCC-2022 (Works matter),otherwise their offer will be considered incomplete and shall not be considered.
Joint Venture firms, if applicable in the instant tender, should submit all valid requisite documents and fulfil the stipulations as per clause 17 of IRGCC-2022 (Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
Partnership firms, if bidding for the instant tender, should submit all valid requisite documents and fulfil the stipulations as per clause 18 of IRGCC-2022 (Works Matter),otherwise their offer will be considered incomplete and shall not be considered.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Rates are inclusive of all taxes/octroi, license fee, royalty charges etc. legally leviable by State, Central Govt. and/or any other local authority. If any Tax/Royalty/Octori is quoted extra, the same will neither be considered for evaluation of the tender nor will be paid. However any changes in rate of taxes or any new tax /cess on Works Contract will be dealt according to clause 37 of IRGCC-2022 (Works Matter).
Tenderers are advised to visit the site of work to ascertain all aspects of the site conditions viz accessibility, availability of approach road, nature of the soil, availability of material, availability of labour etc. that may be encountered in course of execution of work.
Tenderer should see the website for the corrigendum/addendum to the NIT/tender document, if any that may be uploaded prior to tender opening (inclusive) as there will not be any separate communication for that.
The tenderer for carrying any construction work in Uttar Pradesh must get themselves registered from the registering Officer under Section - 7 of the Building and Other Construction Workers Act, 1996 and rules made there-to by the Uttar Pradesh Govt. and submit certificate of Registration (Labour Department). For enactment of this Act, the tenderer shall be required to pay cess @ 1% of cost of construction work to be deducted from each bill.
The contractor(s) shall observe all the formalities, perform all the acts and abide by all the provisions contained in the Contract Labour Act-1970 and Contract Labour Central Rules, 1971 which in addition to other stipulations provides that the contractor(s) shall obtain license(s) from appropriate licensing officer of the area before commencement of the work and shall produce a copy thereof along with the original to the Railway office, which will be returned to the contractor after verification.
If any complaint is received against the contractor regarding violation of contract laws, (exposing Principal Employer to the risk of legal proceedings under labour laws), the guilty contractor will be black listed and their contract shall be terminated following the due procedure, apart from initiating criminal proceedings against him with the help of Labour department officials. (Authority: RB letter no.2008/E (LI)/AT/CNR/3, dated 24.01.2018).
It is the responsibility of the tenderer to see corrigendum, if any, to tender notice up to the date of tender opening. IRGCC-2022 (works matter) is for reference only. Any correction issued by competent authority up to date of opening will be applicable. Tenderer should quote accordingly.
Though no minimum eligibility criteria is specified for tenders below Rs. 50.00 Lakhs, tenderers are advised to upload documents so that their financial capacity, capability & past performance to undertake the tendered work can be adjudged during evaluation of their offer. Documents testifying tenderer previous experience for the type of job for which tender is invited with list of works carried out in the past and financial status should be produced along with the tender.
The provision of Construction and Demolition Waste Management Rule 2016 issued by Ministry of Environment Forest and Climate Change dated 29.03.2016 and published in the Gazette of India, Part - II, Section -3, Sub-section (ii) are binding upon the Contractor. Contractor shall implement these provisions at worksites, for which no extra payment will be payable.
The tenderers shall submit a copy of certificate stating that all their statements/documents submitted along with bid are true and factual. Standard format of certificate to be submitted by the bidder is enclosed as Annexure-A. Non submission of above certificate by the bidder shall result in summarily rejection of his/their bid.
It is to be noted that tenderer digital signature on the E-Tender form will be considered as confirmation that tenderer have read and accepted all the conditions laid down in the documents as well as related specification of items,schedule & quantity of items in the tender, consisting of techno-commercial offer form (including special conditions attached to E-Tender) and Financial offer form, unless specific deviation is quoted in the techno- commercial offer form.
The quantities shown in the attached Schedule are given as a guide and are approximate only and are as a guide to give the tenderer(s) an idea of quantum of work involved. Quantities are subject to variation according to the needs of the Railway. The Railway does not guarantee work under each item of the Schedule. The Railway reserves the right to increase/ decrease and/or delete or include any of the quantities given above and no extra rate will be allowed on this account.
In case of any information submitted by tenderer is found to be false forged or incorrect at any time during process for evaluation of tenders, it shall lead to forfeiture of the tender Earnest Money Deposit besides banning of business for a period of upto five years. In case of any information submitted by tenderer is found to be false forged or incorrect after the award of contract, the contract shall be terminated. Earnest Money Deposit (EMD), Performance Guarantee and Security Deposit available with the railway shall be forfeited. In addition, other dues of the contractor, if any, under this contract shall be forfeited and agency shall be banned for doing business for a period of upto five years.
The tenderer has to submit necessary documents in compliance of clause 10 to 18 (Part-I) of IRGCC 2022 (Works matter) mandatorily, otherwise offer will be considered as Incomplete Offer and accordingly shall not be considered.
Rates are inclusive of all taxes/octroi, license fee, royalty charges etc. legally leviable by State, Central Govt. and/or any other local authority. If any Tax/Royalty/Octori is quoted extra, the same will neither be considered for evaluation of the tender nor will be paid. However any changes in rate of taxes or any new tax /cess on Works Contract will be dealt according to clause 37 of IRGCC-2022 (Works Matter).
Tenderers are advised to visit the site of work to ascertain all aspects of the site conditions viz accessibility, availability of approach road, nature of the soil, availability of material, availability of labour etc. that may be encountered in course of execution of work.
Tenderer should see the website for the corrigendum/addendum to the NIT/tender document, if any that may be uploaded prior to tender opening (inclusive) as there will not be any separate communication for that.
The tenderer for carrying any construction work in Uttar Pradesh must get themselves registered from the registering Officer under Section - 7 of the Building and Other Construction Workers Act, 1996 and rules made there-to by the Uttar Pradesh Govt. and submit certificate of Registration (Labour Department). For enactment of this Act, the tenderer shall be required to pay cess @ 1% of cost of construction work to be deducted from each bill.
The contractor(s) shall observe all the formalities, perform all the acts and abide by all the provisions contained in the Contract Labour Act-1970 and Contract Labour Central Rules, 1971 which in addition to other stipulations provides that the contractor(s) shall obtain license(s) from appropriate licensing officer of the area before commencement of the work and shall produce a copy thereof along with the original to the Railway office, which will be returned to the contractor after verification.
If any complaint is received against the contractor regarding violation of contract laws, (exposing Principal Employer to the risk of legal proceedings under labour laws), the guilty contractor will be black listed and their contract shall be terminated following the due procedure, apart from initiating criminal proceedings against him with the help of Labour department officials. (Authority: RB letter no.2008/E (LI)/AT/CNR/3, dated 24.01.2018).
It is the responsibility of the tenderer to see corrigendum, if any, to tender notice up to the date of tender opening. IRGCC-2022 (works matter) is for reference only. Any correction issued by competent authority up to date of opening will be applicable. Tenderer should quote accordingly.
Though no minimum eligibility criteria is specified for tenders below Rs. 50.00 Lakhs, tenderers are advised to upload documents so that their financial capacity, capability & past performance to undertake the tendered work can be adjudged during evaluation of their offer. Documents testifying tenderer previous experience for the type of job for which tender is invited with list of works carried out in the past and financial status should be produced along with the tender.
The provision of Construction and Demolition Waste Management Rule 2016 issued by Ministry of Environment Forest and Climate Change dated 29.03.2016 and published in the Gazette of India, Part - II, Section -3, Sub-section (ii) are binding upon the Contractor. Contractor shall implement these provisions at worksites, for which no extra payment will be payable.
The tenderers shall submit a copy of certificate stating that all their statements/documents submitted along with bid are true and factual. Standard format of certificate to be submitted by the bidder is enclosed as Annexure-A. Non submission of above certificate by the bidder shall result in summarily rejection of his/their bid.
It is to be noted that tenderer digital signature on the E-Tender form will be considered as confirmation that tenderer have read and accepted all the conditions laid down in the documents as well as related specification of items,schedule & quantity of items in the tender, consisting of techno-commercial offer form (including special conditions attached to E-Tender) and Financial offer form, unless specific deviation is quoted in the techno- commercial offer form.
The quantities shown in the attached Schedule are given as a guide and are approximate only and are as a guide to give the tenderer(s) an idea of quantum of work involved. Quantities are subject to variation according to the needs of the Railway. The Railway does not guarantee work under each item of the Schedule. The Railway reserves the right to increase/ decrease and/or delete or include any of the quantities given above and no extra rate will be allowed on this account.
In case of any information submitted by tenderer is found to be false forged or incorrect at any time during process for evaluation of tenders, it shall lead to forfeiture of the tender Earnest Money Deposit besides banning of business for a period of upto five years. In case of any information submitted by tenderer is found to be false forged or incorrect after the award of contract, the contract shall be terminated. Earnest Money Deposit (EMD), Performance Guarantee and Security Deposit available with the railway shall be forfeited. In addition, other dues of the contractor, if any, under this contract shall be forfeited and agency shall be banned for doing business for a period of upto five years.
The tenderer has to submit necessary documents in compliance of clause 10 to 18 (Part-I) of IRGCC 2022 (Works matter) mandatorily, otherwise offer will be considered as Incomplete Offer and accordingly shall not be considered.
P-Way work in connection with development of GMC as satellite Station under Dy. CPM/GSU/PRYJ.
GSU-09~NCR
GSU-09
Open
Works - General
12 Months
Prayagraj, Uttar Pradesh
₹0
₹2.4 L
2 Feb 2026
9 Jan 2026
19 Jan 2026
64 items across 1 schedule · ₹1,60,51,169.85 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Joining with strong nylon rope in one cross and one horizontal pattern of minimum 5mm dia. | RM | 4600.00 | 98.53 | 4,53,238 |
| 2 | Fish plates of 6 bolts. | Joint | 150.00 | 248.72 | 37,308 |
| 3 | Dismantling & removing existing SEJ (Switch Expansion Joint) assembly during line block and its replacement with plain track as of adjoining section with all fittings including rail cutting and drilling of holes and renewal of special sleepers with PSC Sleepers as directed and aligning rails, providing fishplates and bolts/ temporary connection with adequate welding gap with adjoining rail and ensuring proper track geometry for 30 kmph speed. The release material shall be stacked as directed by Engineer in charge. | Set | 22.00 | 8,346.7 | 1,83,627.4 |
| 4 | 1 in 12 Turnout (Under Traffic Block) | Set | 15.00 | 32,788.7 | 4,91,830.5 |
| 5 | 1 in 12 Turnouts | Set | 3.00 | 46,855.85 | 1,40,567.55 |
| 6 | For average lead up to 50m and lift up to 5m | cum | 1830.00 | 95.52 | 1,74,801.6 |
| 7 | Lifting and packing for regrading the existing PSC sleeper track to required height / level in stages not exceeding 75mm or part thereof at a time, providing permissible ramp for the track, insertion of moorum / sand / stone ballast uniformly under the existing track and placing the same to safe approved gradient, gauge, cushion including levelling and one round of through packing to allow train movement at restricted speed of 30 kmph for a specified length with all leads & lifts and fixing, marking, painting rail level pegs at every 30m interval. Note: Lifting of track shall be done in stages as per procedure prescribed in latest edition of IRPWM to get the proposed final level as per approved working profile, as directed by Engineer in-charge. | TRM | 920.00 | 165.69 | 1,52,434.8 |
| 8 | Boxing and profiling of ballast as per procedure prescribed in latest edition of IRPWM including cess dressing on both sides of track. The work will include removing excess ballast from track and putting the same in crib and shoulder by leading to a maximum of 50m including crossing of track, deweeding on ballast section etc and as directed by Engineer-In charge. | TRM | 920.00 | 24.39 | 22,438.8 |
| 9 | For 60Kg 90 UTS Rails | Each | 300.00 | 2,384.44 | 7,15,332 |
| 10 | For 60 Kg - 90 UTS Rail | Each | 277.00 | 3,414.62 | 9,45,849.74 |
| 11 | For 60 Kg/60EI - R260 grade Rail | Each | 280.00 | 3,357.61 | 9,40,130.8 |
| 12 | Dismantling of existing LWR/SWR track of any structure, removing rails, sleepers, fish plates, cutting of rails, segregation and stacking of released Rails, Sleepers and fitting at nominated location in countable manner within a free lead of 500m, levelling of ballast to correct profile for laying new track over it, all as per direction of Engineer-in-Charge. | TRM | 4600.00 | 165.16 | 7,59,736 |
| 13 | For sleeper density of 1660 sleepers per km | TRM | 2830.00 | 258.59 | 7,31,809.7 |
| 14 | For one shift ( 12 Hrs) | Each | 6.00 | 1,144.61 | 6,867.66 |
| 15 | Completion drawing of yard at junction station | Each | 3.00 | 8,387.2 | 25,161.6 |
| 16 | For PSC Sleeper Track with Sleeper Density of 1660 | TRM | 1910.00 | 127.76 | 2,44,021.6 |
| 17 | For PSC Sleeper Track with Sleeper Density of 1660 | TRM | 1910.00 | 98.28 | 1,87,714.8 |
| 18 | 1 in 12 PSC layout | Set | 3.00 | 13,828.92 | 41,486.76 |
| 19 | With 2 bolts | Set | 76.00 | 102.55 | 7,793.8 |
| 20 | For 60 Kg Rails | RM | 1910.00 | 53.3 | 1,01,803 |
| 21 | For 60 Kg Rails | TRM | 1910.00 | 73.34 | 1,40,079.4 |
| 22 | 1 in 12 Turnout | Set | 6.00 | 1,126.44 | 6,758.64 |
| 23 | Carrying out ancillary works required for UTV working under line block i.e., turning of rails/ Sleepers and keeping in position for fixing of UTV clamps to rail, keeping rails/PSC Sleepers in position while loading into BFR, removal of clamps on BFR for releasing loaded rail/Sleepers, adjusting of rails/Sleepers on BFR etc. by providing minimum of three men in a shift of 8 hours, with all contractor's tools, all lead, lift, crossing of tracks etc., complete and as directed by the engineer - in - charge. Note: In case, contractor provides less no. of Labour, payment will be deducted for each such person @ 2/3 rd of the accepted item rate. | Shift | 45.00 | 2,120.76 | 95,434.2 |
| 24 | 60 Kg - 110/90 UTS - On Running Line | Each | 1070.00 | 329.59 | 3,52,661.3 |
| 25 | On Running Line | Each | 2140.00 | 62.36 | 1,33,450.4 |
| 26 | In Wagon where mechanical handling is possible a n d traffic block is not required or in Truck/trailer. | MT | 900.00 | 116.79 | 1,05,111 |
| 27 | In Wagon where mechanical handling is possible a n d traffic block is not required or in Truck/trailer. | MT | 265.00 | 115.27 | 30,546.55 |
| 28 | For lead up to 500 metre. | MT | 900.00 | 356.93 | 3,21,237 |
| 29 | For lead beyond 500 metre and up to 1 Km. | MT | 900.00 | 459.92 | 4,13,928 |
| 30 | For lead up to 500m | MT | 900.00 | 401.38 | 3,61,242 |
| 31 | For lead beyond 500 metre and up to 1 Km | MT | 1710.00 | 583.84 | 9,98,366.4 |
| 32 | Extra to Items no. 171042 for lead beyond 1 Km for every subsequent Km or part thereof and up to 10 Km | MT | 9000.00 | 72.86 | 6,55,740 |
| 33 | From wagons not involving traffic block or on lines, not opened to traffic but handling by mechanical means is not possible | MT | 750.00 | 113.76 | 85,320 |
| 34 | From Wagon where mechanical handling is possible a n d traffic block is not required or in Truck / trailer. | MT | 1560.00 | 86.39 | 1,34,768.4 |
| 35 | In Wagon where mechanical handling is possible a n d traffic block is not required or in Truck / trailer | MT | 800.00 | 90.7 | 72,560 |
| 36 | I n Wagon/Truck / trailer where mechanical handling is possible a n d traffic block is not required. | MT | 300.00 | 114.83 | 34,449 |
| 37 | For lead up to 500 metres | MT | 700.00 | 277.85 | 1,94,495 |
| 38 | For lead beyond 500 metre and up to 1 Km | MT | 700.00 | 411.36 | 2,87,952 |
| 39 | Extra to Items no. 172032 for lead beyond 1 Km for every subsequent Km or part thereof and up to 10 Km | MT | 7000.00 | 42.66 | 2,98,620 |
| 40 | Lead up to 5 Km | MT | 700.00 | 159.36 | 1,11,552 |
| 41 | Lead beyond 5 Km and up to 10 km | MT | 700.00 | 200.54 | 1,40,378 |
| 42 | Lead beyond 10 Km and up to 20 km | MT | 700.00 | 256.56 | 1,79,592 |
| 43 | Lead beyond 20 Km and up to 30 km | MT | 700.00 | 324.75 | 2,27,325 |
| 44 | Lead beyond 30 Km and up to 50 km | MT | 650.00 | 419.4 | 2,72,610 |
| 45 | Lead beyond 50 Km and up to 100 Km | MT | 650.00 | 625.38 | 4,06,497 |
| 46 | Lead up to 5 Km | MT | 700.00 | 52.99 | 37,093 |
| 47 | Lead beyond 5 Km and up to 10 km | MT | 700.00 | 94.18 | 65,926 |
| 48 | Lead beyond 10 Km and up to 20 km | MT | 700.00 | 150.2 | 1,05,140 |
| 49 | Lead beyond 20 Km and up to 30 km | MT | 700.00 | 218.39 | 1,52,873 |
| 50 | Lead beyond 30 Km and up to 50 km | MT | 650.00 | 313.03 | 2,03,469.5 |
| 51 | Lead beyond 50 Km and up to 100 Km | MT | 650.00 | 519.02 | 3,37,363 |
| 52 | From Truck / Trailer | MT | 700.00 | 84.43 | 59,101 |
| 53 | From Truck / Trailer | MT | 300.00 | 88.06 | 26,418 |
| 54 | From Truck / Trailer | MT | 400.00 | 117.93 | 47,172 |
| 55 | Rails, switches, crossings, SEJ, Glued Joints, Check Rails etc. | MT | 1075.00 | 351.11 | 3,77,443.25 |
| 56 | All type of PSC sleepers | MT | 3150.00 | 383.69 | 12,08,623.5 |
| 57 | P.Way fittings of all types and other similar loose items | MT | 100.00 | 358.83 | 35,883 |
| 58 | Caution Indicator Board of size 1400mmx400mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each | 9.00 | 6,066.05 | 54,594.45 |
| 59 | Stop Indicator Board of size 1400mmx400mm with back support frame fixed to vertical post of MS angle of size 50mmx50mmx6mm of 3650 mm long | Each | 6.00 | 6,066.05 | 36,396.3 |
| 60 | JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity | Hour | 150.00 | 794.59 | 1,19,188.5 |
| 61 | Hydra or similar tyre mounted Pick-n-Carry crane of 12T capacity for misc. works of handling of material | Hour | 150.00 | 942.83 | 1,41,424.5 |
| 62 | Tractor with Trolley for local transportation or other misc. works. | Hour | 1530.00 | 200.69 | 3,07,055.7 |
| 63 | Arranging labour as and when required by the Engineer in charge, for various works under SSE/P.Way, with contractor's T&P, equipments, hand signal flags, etc. as per specifications, special conditions and detailed scope of work as furnished in the tender and as directed by the Engineer in charge. Note: Item shall be operated with prior approval of concerned Sr. DEN / DEN in charge. | Day | 460.00 | 651.58 | 2,99,726.8 |
| 64 | Supplying and filling 50 kg size empty cement polythene bags with Rly. Ballast/moorum/earth/Sand/quarry dust etc. placing the filled bags on the high banks /bridge approaches/nominated place etc. dumping and spreading at the nominated locations to profile under block period with all contractor's labour, tools, plants, loading, unloading, filling, spreading including all lead/lift etc. complete and as directed by the Engineer in charge at site including crossing of track where necessary. | Each | 765.00 | 15.23 | 11,650.95 |
| Schedule total | ₹1,60,51,169.85 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
acs2.pdf
ATTACHMENT
GCC_April-2022_2022_CE-I_CT_GCC-2022_POLICY_27_04_22.pdf
ATTACHMENT
ACS1.pdf
ATTACHMENT
ACS4.pdf
ATTACHMENT
ACS6.pdf
ATTACHMENT
ACS5.pdf
ATTACHMENT
ACS3.pdf
ATTACHMENT
ACS-07.pdf
ATTACHMENT
ACS-08.pdf
ATTACHMENT
ACS-9.pdf
ATTACHMENT
ACS-10.pdf
ATTACHMENT
TenderDocumentsOfGMC_1.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .