| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹16.4 CrAccepted-AOC | ₹16.4 Cr | L1 | Accepted-AOC AS PER UPLOADED |
| 2 | L2₹17.9 CrRejected-Finance | ₹17.9 Cr | L2 | Rejected-Finance AS PER FINANCIAL EVALUATION |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
Refer Docs
EMD Value
₹40 L
Closing Date
16 Jan 2025, 1:00 pmClosed
SUPERINTENDING ENGINEER
SUPERINTENDING ENGINEER GANDAK IRRIGATION WORK CIRCLE-1, GORAKHPUR
Rehabilitation work of lining of the damaged part of the inner slope of left and right bank of the main western Gandak canal from km 18.900 to km 19.710, km 21.710 to km 22.360, km 23.800 to km 24.500 In district- Maharajganj
2025_UPIDC_989176_2
10/SE/2024-25
Open Tender
Civil Works
635 days
NICHLAUL
Please refer Tender documents.
2 documents required · 2 mandatory
₹7,354
₹40 L
Yes
11 Mar 2025
2 Jan 2025
16 Jan 2025
2 Jan 2025
16 Jan 2025
2 Jan 2025
Amount
Dismantling of existing Brick Lining and its proper disposal within an initial lead of 60m and lift 1.5m with cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
Earth work in filling to recupe the canal section all lead and lift manual compaction and dressing to profile as directed by Engineer-in-Charge as per I.D. specification..................per cum
Earth work excavation in foundation for toe wall/top wall and sleepers including digging and refilling the trenches with its proper disposal within 30 meter lead & all lift with cost of all material labour and T&P etc., for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
Plain Cement Concrete in 1:4:8 in base of toe wall with Coarse Sand F.M. Not less than 2.0, old dismantled brick ballast of nominal size of 25 mm to 40 mm, placed in position and properly compacted including cost of all materials, labour and T&P with all leads and lift/down for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
Cement Concrete in 1:2:4 in Toe Wall, Sleepers and Top/Cut-off Wall with Coarse Sand having F.M. Not less than 2.0, Crushed Stone grit of nominal size of 12.5 mm to 20 mm, Mechanically mixed, placed in proper position and properly compacted including cost of all materials, labour and T&P etc. for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification......per cum.
Supplying and laying of Water stopper at transverse sleepers including cost of all materials, labour and T&P etc proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
Cement Concrete in M-20 (1:1.5:3 ) in Lining with Coarse Sand having F.M. Not less than 2.0, Crushed Stone grit of nominal size of 12.5 mm to 20 mm, Mechanically mixed, placed in proper position by paver machine and properly compacted including cost of all materials, labour and T&P etc. for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification......per Sqm.
Supplying and laying Coarse Sand (FM not less then 2.00) in filter including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
Supplying and laying crushed Stone Grit (12.5-20)mm in filter material including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
Supply & Laying LDPE film 200 micron thick first grade on slope below lining including cost of all materials, labour, T&P etc required for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
Centering and shuttering for CC work including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
Supplying and fixing Pressure Relief Valve including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
Running of 5 H.P. generator set pump for dewatering including arrangement of Pump suction and delivery pipes and other accessories at site including cost of all materials, labour and T&P etc.for complete work as directed by Engineer-in-Charge as per I.D.specification.
Providing and fixing sealing compound in between panel joints including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by engineer -in-charge as per drawing and I.D. Specification
Supplying and laying 25 mm dia CPVC Pipe in Sleepers including cost of all material, labour & T&P etc., complete work directed by Engineer-in-charge.
Brick on edge soling with old dismantled lining brick/tile including preparation of sub-grade to prescribed camber, filling joint with Local sand/earth including cost of all material, labour and T&P etc., for proper completion of work as directed by Engineer-in-Charge and as per I.D. specification.
S S Infrazone Pvt Ltd (BID ID -4856266)
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf