| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹8.0 LAdmitted-Finance | -18.44% | ₹8.0 L | L1 | Admitted-Finance |
| 2 | L2₹8.0 L+₹6,541.46 (0.82%)Admitted-Finance | -17.77% | ₹8.0 L+₹6,541.46 (0.82%) | L2 | Admitted-Finance |
| 3 | L3₹8.1 L+₹12,008.94 (1.51%)Admitted-Finance | -17.21% | ₹8.1 L+₹12,008.94 (1.51%) | L3 | Admitted-Finance |
| 4 | L4₹8.5 L+₹51,355.32 (6.45%)Admitted-Finance | -13.18% | ₹8.5 L+₹51,355.32 (6.45%) | L4 | Admitted-Finance |
| 5 | L5₹8.5 L+₹53,112.73 (6.67%)Admitted-Finance | -13.00% | ₹8.5 L+₹53,112.73 (6.67%) | L5 | Admitted-Finance |
Tender Value
₹9.8 L
EMD Value
₹19,527
Closing Date
7 Aug 2026, 4:00 pmClosed
EE(BM-PK)
Room no-1615 16th floor Palika Kendra New Delhi
A/R and M/O building in BM-PK Division during 2026-27 SH Repair of damaged platforms for PVC water storage tanks, parapet walls, and other miscellaneous works on the roof of Palika Kunj Housing Complex under Aliganj S/c
2026_NDMC_295931_1
NITNO.39/EE(BM-PK)/2026-27
Open Tender
Civil Works - Buildings
Works
60 days
NDMC area
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹19,527
11 Aug 2026
30 Jul 2026
7 Aug 2026
30 Jul 2026
7 Aug 2026
30 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing: 1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | 0.2 | Cubic Metre | 10,016.04 | ₹2,003.21 |
| 2 | Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in superstructure above plinth level up to floor V level in all shapes and sizes in : Cement mortar 1:4 (1 cement : 4 coarse sand) | 18 | Cubic Metre | 9,458.46 | ₹1,70,252.28 |
| 3 | Structural steel work in single section, fixed with or without connecting plate, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 160 | Kilogram | 118.78 | ₹19,004.8 |
| 4 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.
Hot finished welded type tubes | 429 | Kilogram | 196.77 | ₹84,414.33 |
| 5 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete.
Hot finished welded type tubes | 293 | Kilogram | 174.71 | ₹51,190.03 |
| 6 | Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-Charge) of total coated thickness 0.50 mm (base metal of minimum 0.45 mm thickness with total coating thickness of 0.05mm) with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. | 51 | square meter | 747.67 | ₹38,131.17 |
| 7 | 12 mm cement plaster of mix : 1:4 (1 cement: 4 coarse sand) | 246 | square meter | 361.71 | ₹88,980.66 |
| 8 | Finishing walls with Acrylic Smooth exterior paint of required shade :
New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) | 231 | square meter | 162.56 | ₹37,551.36 |
| 9 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :
Two or more coats on new work | 80 | square meter | 157.8 | ₹12,624 |
| 10 | Washed stone grit plaster on exterior walls height upto 10 metre above ground level, in two layers, under layer 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ), furrowing the under layer with scratching tool, applying cement slurry on the under layer @ 2 Kg of cement per square metre, top layer 15 mm cement plaster 1:1/ 2:2 (1 cement: 1/2 coarse sand : 2 stone chipping 10 mm nominal size), in panels with groove all around as per approved pattern, including scrubbing and washing the top layer with brushes and water to expose the stone chippings ,complete as per
specification and direction of Engineer-in-charge (payment for providing grooves shall be made separately). | 45 | square meter | 1,176.44 | ₹52,939.8 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.99 MB
BOQ_393828.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .