Loading…
Loading…
Tender Value
₹25.0 L
EMD Value
₹49,962
Closing Date
9 Sept 2026, 5:00 pm
EXECUTIVE ENGINEER, M.I. DIVISION, HAZARIBAG
EXECUTIVE ENGINEER, M.I. DIVISION, HAZARIBAG
Construction of two Extra classroom works in Middle School Barwadih, Block- Vishnugarh, District- Hazaribag
2026_WRD_117725_1
DMFT/MID/HAZARIBAG/F2 - 17/2026-27
Open Tender
Civil Works
Percentage
120 days
VISHNUGARH, HAZARIBAG
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
₹49,962
21 Aug 2026
21 Aug 2026
11 Sept 2026
21 Aug 2026
9 Sept 2026
21 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation in foundation trenches in ordinary soil (vide classification of soil item - A) and disposal of excavated earth to a distance up to 50m. Including all lifts with levelling ramming the foundation trenches removing roots of trees shurbs all complete as per approved design & building specification and direction of E / I .(5.1.1. BCD ) | 74.46 | M3 | 151.82 | ₹11,304.52 |
| 2 | Extra for earth work in hard soil as per specification and direction of E/I (vide classification of soil item) - ( 5.1.2 BCD) | 44.68 | M3 | 15.51 | ₹692.99 |
| 3 | Providing coarse clean sand filling in foundation trenches and plinth including ramming and watering in layers not exceeding 150mm thick with all leads & lifts including the cost of all materials, labour, royality, & taxes all complete as per building specification and direction of E/I (5.1.10 BCD) | 40.51 | M3 | 589.51 | ₹23,881.05 |
| 4 | Providing designation 75B one brick flat soling joints filled with local sand including the cost of watering taxes royality all complete as per building specification and direction of E/I..(5.6.3 BCD) | 176.63 | M2 | 330.34 | ₹58,347.95 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering -All work up to plinth level:1:2:4(1Cement :2 coarse sand (zone-III):graded stone aggregate 20 mm nominal size). (5.3.1.2 BCD) | 15.16 | M3 | 4,598.23 | ₹69,709.17 |
| 6 | Providing designation 75 B brick work in C.M. (1:6) in foundation and plinth with approved quality of clean coarse sand of F.M. 2 to 2.5 including providing 10mm thick mortar joints, cost of screening materials, raking out joints to 15mm depth, curing, taxes and royalty all complete as per building specification and direction of E/l. (5.2.6.BCD | 8.15 | M3 | 5,110.26 | ₹41,648.62 |
| 7 | Providing R.C.C. M-200 with nominal mix (1:1.5:3) in foundation with approved quality of stane chips 20mm to 6 mm size graded and clean coarse sand of F.M. 2.5 to 3 Excluding screeing, shuttering, mixing cement concrete in mixer and placing in position, vibrating, striking, curing, taxes and royalty all complete as per building specification and direction of E/I. ( 5.3.9.1 BCD) | 10.41 | M3 | 5,218 | ₹54,319.38 |
| 8 | Centering and shuttering including strutting, propping etc and removal of form for Columns(5.3.17.1 BCD) | 29.4 | M2 | 194.5 | ₹5,718.3 |
| 9 | Centering and shuttering including strutting, propping etc and removal of form for Foundations, footings, bases of caloumns etc., for mass concrete.(5.3.17.6 BCD) | 55.54 | M2 | 465.38 | ₹25,847.21 |
| 10 | Providing and laying in position specified grade of reinforced cement concrete in columns ,excluding the cost of centering ,shuttering , finishing and reinforcement -All work above plinth level up to floor five level)1:1.5:3(1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20mm nominal size). (5.3.10 BCD) | 3.51 | M3 | 6,082.45 | ₹21,349.4 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.23 MB
TENDER_DOCUMENTS_17.pdf
Tender Documents • 15.02 MB
BOQ_159140.xls
BOQ • 0.43 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].