Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
30 Jun 2026, 3:00 pm
The Commissioner
23(1), Varthagan Street, Municipal Office, Rameswaram
Construction of Dormentary Building at Bus-Stand Back Side Survey No 393 4 in Rameswaram Municipality
2026_MAWS_680808_1
2164_2025_E1
Open Tender
Civil Works - Buildings
365 days
Rameswaram Municipality
Please See Tender Document
2 documents required · 2 mandatory
₹0
₹1.3 L
Rameswaram Municipality
15 Jun 2026
15 Jun 2026
30 Jun 2026
15 Jun 2026
30 Jun 2026
23 Jun 2026
23 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS 20B and Sand, silt or other loose soil, wet sand, silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed, cleaning and levelling the site etc., complete - Footings - First Depth Upto 2.00M | 383 | 1m3 (one cubic metre) | - | - |
| 2 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel, stoney earth and earth mixed with small size boulders SS 20B and Sand, silt or other loose soil, wet sand, silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed, cleaning and levelling the site etc., complete - Plinth Beam | 23 | 1m3 (one cubic metre) | - | - |
| 3 | Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers -Mixing by mechanical means | 55 | 1m3 (one cubic metre) | - | - |
| 4 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid). | 365 | 1m2 (one square metre) | - | - |
| 5 | Supplying and erecting steel centering including necessary supports For plane surfaces such as rectangular or square RCC columns etc. which require only nominal strutting using mild steel sheets made of 10 gauge thick welded with MS angle size 40mm x 40mm x 5 mm and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick).etc..complete in all floors complying with standard specifcation. Steel Adjustable telescopic props shall be rovided as directed by the departmental Officers. (Payment for centering shall be given after the concrete is laid). | 307 | 1m2 (one square metre) | - | - |
| 6 | Supplying and erecting centering for plane surfaces such as RCC Floor/Roof Beam, Lintels, Cantilever Beams, Bed Blocks etc.. with necessary supports and strutting upto 3.60m height in all floors with all cross bracings using MS Sheets made of 10 gauge thick welded with MS angle of Size 25mm x 25mm x 3mm for boarding laid over Steel adjustable Span of Size 2m x 2m(expandable upto 3.60m) and Silver Oak Joists of Size 10 x 5 cm spaced at 50cm to 60cm c/c and supported by Steel Adjustable Telescopic Props of Size 2m x 2m (expandable upto 3.60m) made with outer steel pipe with dia 50mm (3.60mm thick) and inner steel pipe with dia 40mm (2.90mm thick) Spaced at not more than 50 to 60cm c/c , etc complete complying with standard specifications. Steel adjustable span and Steel Adjustable telescopic props shall be provided as directed by the departmental Officers. (Payment for centering shall be given after the concrete is laid). | 444 | 1m2 (one square metre) | - | - |
| 7 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS standards. (No separate payment will be made by the Department for the excess usage of materials) -
Upto Basement | 79 | 1m3 (one cubic metre) | - | - |
| 8 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS standards. (No separate payment will be made by the Department for the excess usage of materials) - Ground Floor | 55 | 1m3 (one cubic metre) | - | - |
| 9 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of sand, but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - The Coarse and Fine aggregates to be used should comply with the requiremnents of IS standards. (No separate payment will be made by the Department for the excess usage of materials) - First Floor | 5 | 1m3 (one cubic metre) | - | - |
| 10 | Supply and fabrication of steel required for all RCC items of works involved in the schedule, cost of steel at site fabrication, labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as as per design given and specified in the drawings, including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc complete as per standard specification | 16,680 | 1Kg (one kilo gram) | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.64 MB
BID_DOC.pdf
Tender Documents • 0.69 MB
BOQ_818135.xls
BOQ • 0.38 MB