Tender Value
₹6.5 L
EMD Value
₹13,001
Closing Date
12 Oct 2026, 3:00 pmClosed
Commissioner
Infantry Road, Vellore Corporation, Vellore-632001
Construction and Shifting of old Bus Shelter Building From Gudiyatham Junction to Gudiyatham Main Road in Ward No . 5 Zone - I, Vellore City Municipal Corporation
2026_MAWS_708152_1
931/2026/E1/G.F-2026-27/P1
Open Tender
Civil Works
Works
180 days
Vellore
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹13,001
25 Sept 2026
25 Sept 2026
12 Oct 2026
25 Sept 2026
12 Oct 2026
25 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand,silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering, ,and baling out water and cleaning and levelling the site etc.,complete 10 m3 | 11.67 | m3 | - | - |
| 2 | Supplying and filling in foundation and basement with Crushed Stone Sand (M- Sand) in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard
specification | 1.46 | m3 | - | - |
| 3 | Plain Cement Concrete 1:4:8 (One cement four sand and eight aggregates) using 40mm gauge hard broken granite jelly for foundation including consolidation and dewatering for foundation whenever necessary etc. complete. | 7.41 | m3 | - | - |
| 4 | Supplying and filling the basement with Well Gravel filling in layers of not more than 15cm thick well rammed watered and compacted - etc., complete complying with standard specification. | 34.65 | m3 | - | - |
| 5 | Suppling and erecting shuttering with necessay supports for Plinth Beam with all cross bracings etc., complete ( Side Only) the payment for centering shall be given offer the concrete is laid vertical portion using steel plate. | 21.17 | m2 | - | - |
| 6 | Supplying, erecting with necessary supports for plain surface such as RCC Boxing side slab and silmilar RCC slab with all cross bracing etc., complete in all floors of any height ( the retrived materials ) should be taken back by the contractor the payment for cenetering shall be given after the concrete is laid ( vertical portion ) 10m2 etc., complete | 19.44 | m2 | - | - |
| 7 | Reinforced Cement concrete 1:1 1/2:3 (One cement one and half sand and three aggregates) using 20 mm gauge band broken granite chips for foundation including consolidation and dewatering for foundation wherever necessary etc.complete. (GF) | 5.94 | m3 | - | - |
| 8 | Suppling and fabricating and placingin position MS (or) R.T.S.bar for reinforcement toal lRCC works as per the design given including cost of steel and binding wire also in all floors. | 534.69 | kg | - | - |
| 9 | Brick work in CM 1:5 (one cement & five sand) using II class ground moulded bricks of size 9"X43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification - 100CFT, For Ground floor. | 18.88 | m3 | - | - |
| 10 | Plastering with cement mortar (1:5),12 mm ,thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications (S.I.306) | 59.42 | m2 | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.79 MB
BOQ_851030.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .