| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹27.9 LAccepted-AOC 17 125 CHOPAN ROAD OBRA OBRA OBRA SONEBHADRA SONBHADRA UTTAR PRADESH 231219 | SONBHADRA | UTTAR PRADESH | 231219 | ₹27.9 L | L1 | Accepted-AOC Lowest rate |
| 2 | L2₹28.3 LRejected-Finance 345 PANDAV NAGAR GAZIABAD | ₹28.3 L | L2 | Rejected-Finance Higher to L1 |
| 3 | L3₹28.4 LRejected-Finance 1 28 SHOP NO 116 1 28 U G F TILAK NAGAR TILAK NAGAR WEST DELHI DELHI 110018 | WEST DELHI | DELHI | 110018 | ₹28.4 L | L3 | Rejected-Finance Higher to L1 |
| 4 | L4₹28.6 LRejected-Finance B 1 146 SECTOR B ALIGANJ LUCKNOW | LUCKNOW | UTTAR PRADESH | 226001 | ₹28.6 L | L4 | Rejected-Finance Higher to L1 |
| Sl No | Description | Qty | Unit | swastik traders L3 | UDAY ENGINEERS L4 | S K ENGINEERING WORKS L1 | NIRMAL ENGINEERS L2 |
|---|---|---|---|---|---|---|---|
| 1.00Mechanical work | |||||||
| 1.01 | Erection of 2nd stage of Embedment parts of Cross Regulator at km 18.270 of Ken Main Canal, Banda. All material will be provided by Deptt. All T&P, labour and other equipments required to complete the work will be provided by Contractor.GST extra as per Applicable | 5 | JOB | 1,98,000 ₹9.9 L | 1,96,000 ₹9.8 L | 1,94,000 ₹9.7 L | 1,95,000 ₹9.8 L |
| 1.02 | Erection of Shutter Assembly of Cross Regulator at km 18.270 of Ken Main Canal, Banda. All material will be provided by Deptt. All T&P, labour and other equipments required to coGST extra as per Applicablemplete the work will be provided by Contractor. | 5 | JOB | 1,48,000 ₹7.4 L | 1,50,000 ₹7.5 L | 1,46,000 ₹7.3 L | 1,51,000 ₹7.5 L |
| 1.03 | Erection of Stanchion leg of Cross Regulator at km 18.270 of Ken Main Canal, Banda . All material will be provided by Deptt. All T&P, labour and other equipments required to complete the work will be provided by Contractor.GST extra as per Applicable | 6 | JOB | 1,85,000 ₹11.1 L | 1,88,000 ₹11.3 L | 1,82,000 ₹10.9 L | 1,84,000 ₹11.0 L |
Tender Value
Refer Docs
EMD Value
₹58,000
Closing Date
2 Apr 2026, 3:00 pmClosed
Works Manager
Irrigation Wokshop Division Jhansi
Erection of 2nd stage of Embedment parts , Shutter Assembly , Stanchion leg of Cross Regulator at km 18.270 of Ken Main Canal, Banda
2026_UPIDM_1128881_1
10/WM/2025-2026
Open Tender
Miscellaneous Works
90 days
banda
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
₹58,000
20 Apr 2026
23 Mar 2026
2 Apr 2026
23 Mar 2026
2 Apr 2026
23 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1Mechanical work | ||||||
| 1.01 | Erection of 2nd stage of Embedment parts of Cross Regulator at km 18.270 of Ken Main Canal, Banda. All material will be provided by Deptt. All T&P, labour and other equipments required to complete the work will be provided by Contractor.GST extra as per Applicable | - | JOB | - | - | BI01010001010000000000000515BI0100001113 |
| 1.02 | Erection of Shutter Assembly of Cross Regulator at km 18.270 of Ken Main Canal, Banda. All material will be provided by Deptt. All T&P, labour and other equipments required to coGST extra as per Applicablemplete the work will be provided by Contractor. | - | JOB | - | - | BI01010001010000000000000515BI0100001114 |
| 1.03 | Erection of Stanchion leg of Cross Regulator at km 18.270 of Ken Main Canal, Banda . All material will be provided by Deptt. All T&P, labour and other equipments required to complete the work will be provided by Contractor.GST extra as per Applicable | - | JOB | - | - | BI01010001010000000000000515BI0100001115 |
stage.html
html • 0.05 MB
techsummary_2105578.pdf
finance_2105578.pdf
BOQ Comparative Chart
xlsx
finsummary_2105578.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.