Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2149 CrAccepted-AOC | ₹2149 Cr Quoted ₹2252.6 Cr | L1 | Accepted-AOC BASED ON
FINANCIAL
EVALUATION |
| 2 | L2₹2310.9 CrRejected-AOC | ₹2310.9 Cr | L2 | Rejected-AOC BASED ON
FINANCIAL
EVALUATION |
| 3 | L3₹2734.3 CrRejected-AOC | ₹2734.3 Cr | L3 | Rejected-AOC BASED ON
FINANCIAL
EVALUATION |
Tender Value
Refer Docs
EMD Value
₹4.9 Cr
Closing Date
13 Aug 2019, 11:00 amClosed
RAJESH SANGIA
TOYO ENGINEERING INDIA PVT LTD, Toyo Technology Centre, 71, Kanjur Village Road, Kanjurmarg (East), Mumbai 400 042.
EPCC-1A PACKAGE FOR NEW ATMOSPHERIC and VACCUM DISTILLATION UNIT (AVU) AND ALLIED FACILITIES FOR BARAUNI REFINERY CAPACITY EXPANSION (TO 9.00 MMTPA) PROJECT OF INDIAN OIL CORPORATION LIMITED.
2019_REFHQ_96960_1
IBCE-6373-C00-PJM-TEN-EPCC-01A
Global Tenders
Lump Sum TurnKey
962 days
BARAUNI REFINERY
REFER TENDER DOCUMENT
4 documents required · 4 mandatory
₹4.9 Cr
Yes
NEW DELHI
10 Apr 2020
9 May 2019
14 Aug 2019
9 May 2019
13 Aug 2019
8 Aug 2019
9 May 2019 - 30 May 2019
6 Jun 2019
Amount
Project Management, Residual Process Design, Detailed Engineering (including HAZOP/ SIL study), procurement, fabrication, inspection, transportation of all the equipment’s/ materials to work site, storage, assembly, erection, installation, construction and testing of all above mentioned facilities, including statutory approvals, and to achieve mechanical completion, pre-commissioning, commissioning, performance guarantee test run (PGTR) and handing over of all the facilities to Client including supply of mandatory/ recommended spares based on FEED Package provided by Toyo Engineering India Pvt .Ltd. (TOYO) of Atmospheric Distillation & Vacuum Distillation Unit (AVU) + Naphtha Splitter Unit (NSU) for the “BARAUNI REFINERY CAPACITY EXPANSION to 9.0 MMTPA PROJECT”
FOREIGN CURRENCY PART
INDIAN CURRENCY PART
Description of Work / Item(s)
Amount
Lump-sum Price for Supply Portion for completion of Scope of Work as per Bidding Document
IN FOREIGN CURRENCY
IN INDIAN CURRENCY
Description of Work / Item(s)
Amount
ENGINEERING PRICE (RESIDUAL PROCESS DESIGN AND DETAILED ENGINEERING OF EPCC-1A : AVU UNIT AS PER REQUIREMENTS DETAILED OUT IN VARIOUS SECTIONS OF BIDDING DOCUMENT)
IN FOREIGN CURRENCY
IN INDIAN CURRENCY
LUMPSUM PRICE FOR CONSTRUCTION PORTION AS PER REQUIREMENTS DETAILED OUT IN VARIOUS SECTIONS OF BIDDING DOCUMENT
IN FOREIGN CURRENCY
IN INDIAN CURRENCY
TOTAL OF ENGINEERING AND CONSTRUCTION PRICE [1 +2]
IN FOREIGN CURRENCY
IN INDIAN CURRENCY
Description of Work / Item(s)
Amount
AMOUNT OF FOREIGN COMPONENT
AMOUNT OF INDIAN COMPONENT
Description of Work / Item(s)
Amount
Annual charges for Post Warranty maintenance for ANALYSERS (including GCs) as per Technical Part of Bidding Document for the following periods:
First year after expiry of defect liability
Second year after expiry of defect liability
Third year after expiry of defect liability
Fourth year after expiry of defect liability
Fifth year after expiry of defect liability
Annual charges for Post Warranty maintenance for PLC (Supplied by Contractor) as per Technical Part of Bidding Document for the following periods:
First year after expiry of defect liability
Second year after expiry of defect liability
Third year after expiry of defect liability
Fourth year after expiry of defect liability
Fifth year after expiry of defect liability
Annual charges for Post Warranty maintenance for MMS as per Technical Part of Bidding Document for the following periods:
First year after expiry of defect liability
Second year after expiry of defect liability
Third year after expiry of defect liability
Fourth year after expiry of defect liability
Fifth year after expiry of defect liability
Description of Work / Item(s)
Amount
UTILITY GUARANTEES FOR EPCC–1 AS PER BIDDING DOCUMENT
GUARANTEED POWER CONSUMPTION FOR ROTATING EQUIPMENT [AS IDENTIFIED AT SR. NO. 1 TO 48 OF TABLE-A OF SCC ANNEXURE A-X(ii)]
GUARANTEED POWER CONSUMPTION FOR DESALTER PACKAGE (401-M-003) [AS IDENTIFIED AT SR. NO. 49 OF TABLE-A OF SCC ANNEXURE A-X(ii)]
GUARANTEED MP STEAM CONSUMPTION FOR VACUUM SYSTEM (401-M-010) [AS IDENTIFIED AT SR. NO. 1 OF TABLE-B OF SCC ANNEXURE A-X(ii)]
GUARANTEED COOLING WATER CONSUMPTION FOR VACUUM SYSTEM (401-M-010) [AS IDENTIFIED AT SR. NO. 1 OF TABLE-B OF SCC ANNEXURE A-X(ii)]
CBI LLC
Petrofac International UAE LLC
CBI LLC
Petrofac International UAE LLC
L & T HYDROCARBON ENGINEERING LIMITED
Petrofac International UAE LLC
CBI LLC
Petrofac International UAE LLC
L & T HYDROCARBON ENGINEERING LIMITED
Petrofac International UAE LLC
L & T HYDROCARBON ENGINEERING LIMITED
CBI LLC
Bidder Name
L & T HYDROCARBON ENGINEERING LIMITED
Petrofac International UAE LLC
CBI LLC
US Dollar
European Euro
British Pound
Japanese yen
Singapore Dollar
US Dollar
US Dollar
US Dollar
US Dollar
US Dollar
US Dollar
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid