| 1 | L 1₹2.6 CrAccepted-AOC BYE PASS ROAD MIRIK DARJEELING 734214 | MIRIK | DARJEELING | WEST BENGAL | 734214 | ₹2.6 Cr | L 1 | Accepted-AOC Accepted |
| 2 | L 2₹2.6 CrRejected-Finance FK 16 JYANGRA DAKHIN MATH KOLKATA 700059 | KOLKATA | 24 PARAGANAS NORTH | WEST BENGAL | 700059 | ₹2.6 Cr | L 2 | Rejected-Finance Rejected, higher bid value |
| 3 | L 3₹2.6 CrRejected-Finance | ₹2.6 Cr | L 3 | Rejected-Finance Rejected, higher bid value |
Tender Value
₹2.6 Cr
EMD Value
₹5.3 L
Closing Date
11 Mar 2026, 3:00 pmClosed
SE NBHC
SE NBHC SAKTIGARH SILIGURI
Mirik Bye pass Road form 0.00 kmp to 3.30 km, Surfacing work by Mastic Asphalt, Drain work, Protective work and Road Safety work under Darjeeling Highway Division in the district of Darjeeling
2026_SH_1004264_1
WBPWD/PW(R)/SE/NBHC/NIeT No. 43 OF 2025-26
Open Tender
CIVIL WORKS
Percentage
120 days
MIRIK DARJEELING
Please refer Tender documents.
4 documents required · 4 mandatory
₹5.3 L
Yes
OFFICE OF SE NBHC
11 May 2026
11 Feb 2026
13 Mar 2026
11 Feb 2026
11 Mar 2026
13 Feb 2026
13 Feb 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | PART A ROAD WORK
Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and cleaning the exposed surface by scraping and stacking the material as directed.
By manual means
From 25 mm to 50 mm thick. | 1,481.04 | M2 | 22.6 | ₹33,471.5 |
| 2 | Maintenance of Non-bituminous Base and Sub-Base or WBM Road
Patching of potholes by draining water, cutting the pothole area to rectangular shape with vertical edges, removing all loose materials, screening and stacking the same for reuse with new materials as per requirement, filling the pothole area with additional volume of crushed stone materials / laterite / Jhama / broken shingles / coated stones of Pakur variety etc. and screenings as applicable, and compacting the same with static roller as per Water Bound Macadam Specification, including cost of all materials and machineries.
Using PAKUR variety materials (with stacking) | 34.71 | M3 | 3,155.05 | ₹1,09,511.79 |
| 3 | Prime Coat
Providing and applying primer coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 and requisite quantity on prepared surface of granular base including cleaning of road surface and spraying primer using Mechanical means including cost and carriage of bitumen emulsion and all other incidental costs of work complete as per Clause 502 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
For WBM / WMM Surface:
Using Bitumen emulsion (SS I TYPE) (Packed) @ 0.85 KG /m2 | 462.83 | M2 | 35.02 | ₹16,208.31 |
| 4 | Tack Coat
Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
On Bituminious Surface
Using Bitumnen emulsion (RS 1 TYPE) (Packed) @ 0.25 KG / m2 | 1,481.04 | M2 | 10.11 | ₹14,973.31 |
| 4.01 | On Granular Surface treated with primer
Using Bitumnen emulsion (RS 1 TYPE) (Packed) @ 0.275 KG / m2 | 462.83 | M2 | 10.98 | ₹5,081.87 |
| 5 | Repairing pot-holes and making up small depressions with ramming or power rolling including screening, cleaning chips or metals and washing, drying as necessary and heating the chips or metal where necessary, cutting pot holes to regular shapes with vertical edges, cleaning the disintegrated materials, heating matrix and applying tack coat (including sides), finishing the top of repaired surface levelled with adjoining area, including cost and carriage of stone aggregates and matrix, excluding cost of applying tack coat. [Tack coat is to be considered separately]
[Payment to the Contractor is to be made on the basis of loose net volume of coarse aggregate only excluding key aggregates]
i) With premixed Chips or Bajrees with 54 kg of bitumen per m3 of loose net volume of stone chips using concrete mixer machine. (The payment is to be made on the basis of loose net volume of stone materials consumed in the work)
Using PAKUR variety materials (with stacking)
Using Mobile HMP (Light duty)
VG - 10 (Packed) Bitumen | 18.51 | M3 | 4,889.56 | ₹90,505.76 |
| 6 | Mastic Asphalt
Providing and laying Mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29 using approved coarse aggregate, fine aggregate, filler material and bitumen, prepared by using Mastic cooker including cost and carriage of all ingredients, cost of heating aggregates and binder, mixing in specified proportions conforming to approved Job Mix Formula and laid to required level and slope after cleaning the surface, compacting, sealing the construction joints and surface finishing conforming to specifications including providing antiskid surface with bitumen pre-coated fine-grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100°C, protruding 1 mm to 4 mm over mastic surface, including the hire charges of all tools and plants and machinery, pay of operators, cost of fuel and lubricants and all other incidental charges and quality control all complete as per Clause 516 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
25 mm thickness
Using PAKUR Variety stone chips
10/20 Grade(Packed) Bitumen
VG - 10 (Packed) Bitumen | 18,667.28 | M2 | 514.85 | ₹96,10,849.11 |
| 7 | Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power roller
to proper camber and grade as per direction and satisfaction of Engineer-in-charge including uprooting and removing plants and jungles when and where necessary.
Depth upto 350 mm | 1,377.5 | M2 | 33.4 | ₹46,008.5 |
| 8 | Dry Rubble Flooring
Construction of dry rubble flooring at cross drainage
works for relatively less important works. | 213.01 | M3 | 1,987.23 | ₹4,23,299.86 |
| 9 | Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved stout props with wooden planks/ply wood/steel sheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert, crossdrain etc. The rate is inclusive of fitting, fixing and striking out after completion of work as per specification and direction.
Where staging is not required. | 328 | M2 | 214 | ₹70,192 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.21 MB
BOQ_2462257.xls
BOQ • 0.32 MB
2911new.pdf
Tender Documents • 0.49 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].