All repairs and maintenance of P. way zonal works for a period upto 30/9/2026 from Km. 515.00 to 572.13 between Gangadharpur - Ganjam station under SSE(P.Way)/ Rambha of Khurda Road Division.
e-TenderSouthKUR-312-2025~ECOR
e-TenderSouthKUR-312-2025
Open
Works - General
12 Months
Khordha, Odisha
₹0
₹2.0 L
24 Dec 2025
1 Dec 2025
10 Dec 2025
A-Execution of all works covered under USSOR-2021 of East Coast
B-Execution of items related to Transportation of P.Way materials.
C-Unless otherwise specified, the unit rates for the Items of Sch-C
D-Unless otherwise specified, the unit rates for the Items of Sch-D
related to transportation of P.Way materials, loading and unloading covered under Schedule- B).
Item- 1 Please see Item Breakup for details.
S No. Item Description of Item Unit Qty Rate Amount
Dismantling and removing rail of all section &
length from track, laid on any type & density of
sleeper by removing fish plates, fastenings &
fish bolts and other materials including stacking
all released materials within an average
distance of 500 metres as directed by Engineer
in-charge. Note: 1.Cutting of rails shall be paid
separately. 2.Work to be done under traffic
1 061022 For Casual/Scattered Rail Renewal work RM 425.00 33.06 14050.50
Insertion of rails of all types & length in track,
laid on any type & density of sleeper to the
specified gauge under traffic block. Rates
include fastening of rail with sleepers with
standard set of fastenings and fixing of fish
plates and bolts or, if required, providing gap
for welding and stacking of released material
without infringement within 250m as directed
by Engineer-in-Charge. Note: Rail drilling and
cutting to be paid separately.
2 061032 For Casual/Scattered Rail Renewal work RM 425.00 34.99 14870.75
Through Sleeper Renewal (TSR) with PSC
sleepers involving removal existing sleepers of
any type along with fittings from track, insertion
of PSC sleepers lying along the cess / formation
/ slope / toe within 5 metres height with all
fittings to specified spacing, gauge and
squareness, one round of through packing to
make track fit for 20 kmph speed, dressing of
ballast to standard profile, all in accordance
with the latest provisions of IRPWM and
stacking of all released material neatly at
specified places within an average lead of 100
m as directed by Engineer in-charge.
3 062012 For location of work involving deep screening Each 800.00 176.01 140808.00
(deep screening to be paid separately).
4 062014 For PSC wider base sleepers - For location of Each 5000.00 184.81 924050.00
work involving deep screening. (deep screening
to be paid separately)
KHURDA ROAD DIVISION-ENGINEERING/ECOR
5 063030 Through Fitting Renewal (TFR) on PSC track, Sleeper 5500.00 24.75 136125.00
comprising of renewal of Grooved Rubber Pads,
Liners and ERCs without damaging PSC
sleepers. Scope includes removal of all fittings,
cleaning of rail seat, rail flange at liner seats,
and eye of Inserts with wire brushes and
applying Grease Graphite Grade "O" (IS:408) to
eye of insert and central leg of ERC with
contractor's grease of Railway's specification,
fixing all fittings in correct position and sealing
liner edges with grease all complete including
collection and stacking of released materials at
nominated locations within SSE Jurisdiction as
directed by Engineer-in-Charge. Note: All the
fittings will be supplied at SSE/Stores/Depot.
6 063060 Opening and refixing of Joggled fish plates Set 650.00 48.53 31544.50
provided to weld joints/rail of any rail section
under traffic to enable examination of weld/rail
by departmental official nominated by Engineer
In charge and lubrication of fishplates by
applying departmental Grease graphite grade
'O' (IS:408) to fishing planes and bolts by
departmental black oil as per procedure laid
down in latest version of IRPWM, including all
tools required and as directed by Engineer-in-
charge. Note: 1. Grease Graphite, black oil, fish
bolts, K.Oil, wire brush, required for work shall
be given by department and issued at
concerned SSE/PW Stores. 2.Jammed fish bolts
shall be cut using chisel and hammer and
replaced with new bolt.
7 063090 Lubrication of ERCs and its liner contact area by ERC 6500.00 4.08 26520.00
removal of ERCs and Metal / GFN liners in rail
panel, cleaning of rust / scale of ERC, Metal /
GFN liners & SGCI insert by using wire brush,
scrapper / sand emery paper etc supply and
application of graphite grease, as prescribed by
Railway for under side of liners & corresponding
area of rail foot & SGCI insert with ERCs and re-
fixing the same as per procedure prescribed in
latest edition of IRPWM with contractors grease
and all other tools & plants complete and as
directed. Note: Each ERC in this item shall
constitute 1 ERC and its Liner Contact area.
8 063100 Removing seized ERC from SGCI inserts of ERC 120.00 59.81 7177.20
existing track by using suitable approved
chemicals and re-fixing after greasing of insert
eye and ERC with Contractor's grease of
specified quality as per provisions of IRPWM, as
directed by Engineer in-charge. Note: 1.List of
Seized ERC along with location shall be
prepared after inspection of SSE/P.Way and
marked prior to execution of this item. 2. Due
care shall be taken to avoid any damage to the
sleeper 3.A penalty of 50% of the basic cost of
new sleeper in nearest sleeper factory shall be
levied on each, if SGCI insert is broken or
sleeper gets cracked in the process.
Gas cutting of rail of various sections with
contractor's tools & plants, as directed by
engineer in-charge :
KHURDA ROAD DIVISION-ENGINEERING/ECOR
10 065020 Renewal of existing SEJ with improved SEJ with Set 2.00 7899.44 15798.88
PSC sleepers under traffic block conditions as
per approved drawing including fixing of special
size bearing plate, rubber pad and other sleeper
/ rail fittings, greasing to the fittings, leading
rails, sleepers & fittings to site, leading and
stacking of released materials within a lead of
250m, cutting of Rails, drilling of holes, fixing of
related fittings, providing temporary connection
with fishplates till welding of SEJ is done and
sleepers shall be given initial packing to make
track fit for 20KMPH speed. Note: (1) Rail
cutting and hole drilling shall be paid
separately. (2) One set comprise complete SEJ
on both rails at SEJ.
11 065040 Dismantling & removing existing SEJ (Switch Set 2.00 8671.14 17342.28
Expansion Joint) assembly during line block and
its replacement with plain track as of adjoining
section with all fittings including rail cutting and
drilling of holes and renewal of special sleepers
with PSC Sleepers as directed and aligning rails,
providing fishplates and bolts/ temporary
connection with adequate welding gap with
adjoining rail and ensuring proper track
geometry for 30 kmph speed. The release
material shall be stacked as directed by
Engineer in charge.
Casual renewal of PSC sleepers on points and
crossings, derailing switches and diamonds
portion of any layout including packing under
new sleepers. All the released materials shall be
stacked at specified location in a countable
manner within the lead of 250m & all lift, clear
of infringements, crossing of track, if any
complete, as directed with contractor's vehicles,
consumables, stores, labour etc. complete, as
directed by Engineer in-charge. Note: Approach
and Exit sleepers shall be paid as normal
sleepers under relevant item.
13 074012 Sleepers of length more than 2.85 m and up to Each 150.00 776.72 116508.00
Renewal of CMS Crossing of all rail sections with
CMS crossing or with WCMS crossing complete
with fastenings including replacement of worn-
out rubber pads, liners and ERC, as required. All
the released materials shall be stacked at
specified location in a countable manner within
the lead of 500m & all lift, clear of
infringements, crossing of track, if any
complete, as directed. with contractor's
vehicles, consumables, stores, labour etc.
complete, as directed by engineer in-charge.
Note: Rail cutting and drilling shall be paid
separately under relevant item.
KHURDA ROAD DIVISION-ENGINEERING/ECOR
Through Switches Renewals of existing
curved/Thick web switches with Thick Web
Switches on 60Kg Points and crossings including
approach rails as required, on PSC sleepers,
removing and re-fixing or replacing fittings,
fastenings, stretcher bar, blocks etc., with
housing of tongue rails as per requirement of
signaling etc. including preparation for
operation of traffic block, under line block
conditions and packing of any disturbed
sleepers and boxing of ballast to profile, picking
of slacks of track at switch portion, crossing of
track wherever necessary. All the released
materials shall be stacked at specified location
in a countable manner within the lead of 250m
& all lift, clear of infringements, crossing of
track, if any complete, as directed with
contractor's vehicles, consumables, stores,
labour etc. complete, as directed by engineer
in-charge. Note: Rail cutting and Hole Drilling
shall be paid under relevant item.
Manual deep screening of Plain track/ turnouts
as per procedure prescribed in IRPWM, June
2020 or latest, on PSC sleepers of any density
and throwing away screened muck arising out
of screening on toe of bank or on cess, if low or
on spoil banks above top of cutting (including
throwing and leveling, if required beyond
minimum 5m from the edge of cutting which are
up to 3m deep or alternatively carting it up to
50m for disposing it off beyond cutting or
platforms) as per direction of Engineer in-
charge, including cutting cess for effective
drainage on both sides, one round of kutcha
packing with screened ballast and further
attending to track parameter to make track fit
for 20 kmph speed complete in all respect. Note
: Payment shall be made for length along main
line only for turnouts.
19 081024 Depth of 300 mm below bottom of sleeper - For TRM 3200.00 539.16 1725312.00
20 081028 Depth of 300 mm below bottom of sleeper for TRM 250.00 862.66 215665.00
Unloading of ballast from Railway's Hopper
Wagons, quantity distribution as per pre-
defined site requirement, clearing
infringements/jammed ballast, distributing the
unloaded ballast uniformly over the track,
profiling and boxing following all prescribed
KHURDA ROAD DIVISION-ENGINEERING/ECOR
25mm gap 'in-situ' welding during traffic block
using Railway's welding portion and finishing of
weld to meet the prescribed tolerances and
pass all stipulated tests with all required labour,
materials, consumables, tools, equipments etc.
to complete the work in all respect as per IR's
"Manual for Fusion Welding of Rails by Alumino
- Thermic Process" with latest correction slips,
including marking of welded joint, painting weld
collar with anticorrosive paint, restoration of
track near weld joint to original position and
fixing of joggled fish plate at new weld, to be
removed after passing of weld in USFD test as
directed by Engineer in charge. Note: 1.
Welding portion and related accessories as per
Annexure - I shall be supplied by Railways. All
other items required shall be supplied by the
Contractor. 2. Welding shall be carried out only
by trained welder having valid competency
certificate. 3. Hydraulic Weld trimmer shall be
used for chipping and profile Grinder for
finishing. 4. Required nos. of Joggled fish plates
shall be supplied by Railway at nearest P. Way
Stores and the same shall be returned at
nearest P. Way Store or at other location as per
direction of Engineer-in-Charge after release
crucible fitted with Automatic Tapping Thimble
Technology, 3 pieces Mould (Zircon washed)
and Compressed Air Petrol heating technique.
25mm gap Cess Welding with Railway's welding
portion and finishing of weld to meet the
prescribed tolerances and pass all stipulated
tests with Contractor's labour, materials,
consumables, tools, equipments etc. to
complete the work in all respect as per IR's
"Manual for Fusion Welding of Rails by Alumino
- Thermic Process" with latest correction slips,
including all required handling and rehandling
of rails, marking of welded joint, painting weld
collar with anticorrosive paint, as directed by
Engineer in charge. Note: 1 . Only welding
portion and related accessories as per
Annexure - I shall be supplied by Railways. 2.
Welding shall be carried out only by trained
welder having valid competency certificate. 3.
Hydraulic Weld trimmer shall be used for
chipping and profile Grinder for finishing.
crucible fitted with Automatic Tapping Thimble,
3 pieces Mould (Zircon washed) and
Compressed Air Petrol/LPG pre heating
24 104040 In-situ reconditioning of MCI insert of points & Each 150.00 243.03 36454.50
crossings sleeper by reclaiming the worn-out
portion to the desired height, grinding of the
finished profile for regaining the toe load lost.
The reconditioning to be done by using TERRA C
I-94 - Electrodes of make L & T, Advani Oerlicon,
Diffusion, SHARP - 650, or equivalent approved
by RDSO for reconditioning of Cast iron alloys.
removing and refixing the required fittings for
reconditioning in traffic condition. The cost
includes all labour, lead lift, transportation of
men and material, cost of consumables, hiring
of machinery required etc, complete and as
directed by the Engineer-in -charge.
KHURDA ROAD DIVISION-ENGINEERING/ECOR
First or Second Through Packing of track of all
sleeper density including giving a general lift,
as desired to eliminate sag after Deep
Screening work, lifting of track, lowering of
track and major realignment of curves and
formation rehabilitation as per procedure
prescribed in latest edition of IRPWM. Note:
General lift is normally 25 mm and isolated lift
may be up to 50 mm.
25 131031 For PSC Sleeper Track with Sleeper Density of TRM 900.00 116.14 104526.00
26 131032 For PSC Sleeper Track with Sleeper Density of TRM 3000.00 127.76 383280.00
Third or subsequent Through Packing of track
for all sleeper density including picking of
slacks, as required after second through
packing, subsequent to Deep Screening work as
per procedure prescribed in latest edition of
IRPWM. This item can also be used after
lifting/regrading/realignment works also. Note:
General lift is normally 25 mm and isolated lift
may be up to 50 mm.
27 131041 For PSC Sleeper Track with Sleeper Density of TRM 900.00 89.34 80406.00
28 131042 For PSC Sleeper Track with Sleeper Density of TRM 3000.00 98.28 294840.00
Through packing of points and crossings,
derailing switches including gauging, fittings
recoupment, ballasting as required, elimination
of sag and to the required alignment after Deep
Screening as per procedure prescribed in latest
edition of IRPWM complete as per direction of
Engineer-in-charge. Note: This work shall be
operated in exceptional cases with written
approval at DEN level when UNIMAT is not
available and immediate packing is required to
pass train over it.
31 131060 Packing of isolated loose PSC sleepers on plain Sleeper 9000.00 75.21 676890.00
track below the bottom of t h e sleepers and
surrounding through out its length duly opening
two galas on either side of the renewed
sleepers and packing the sleeper to bring the
track to normal speed including gauging,
aligning, squaring of sleepers and sectioning of
ballast to the required profile with all
contractor's labour, tools and plant etc.
including all lead and lift and crossing of tracks
where ever necessary complete and as directed
by the Engineer-in-charge.
KHURDA ROAD DIVISION-ENGINEERING/ECOR
De-stressing of LWR/CWR track of any density
under traffic line block with contractor's
labours, tools, equipments and consumables
inclusive of all lead & lift. Activities include
cutting of LWR/CWR into convenient panels of
specified length, removal of ERCs, liners,
greasing of ERCs and liner contact area, lifting
rails and keeping them on rollers provided at
every 15 sleepers, working out elongation of
rail ends depending on prevailing site
conditions, pulling rails with the help of
Hydraulic Tensor to achieve the desired
elongation, cutting rails, as required, removing
rollers and placing rail in position, re-fixing
ERCs & liners and adjustment of gap at SEJs :
Note: (1) Welding of rail joints will be paid
separately. (2) Rail cutting and Hole drilling
shall be paid separately. (3) Opening and
closing of LC if required will be paid separately.
(4) As per procedure prescribed in latest edition
of IRPWM & CE's Circulars for destressing of
LWR/CWR, if any.
Fixing Joggled Fish Plates with bolt / clamp
(supplied by Railway from nearest SSE Store) in
running track conditions at welds on rail, as
directed by engineer in-charge (drilling of holes
in rail, if required, shall be paid separately).
34 136060 Replacing existing glued joint rail with cut rails Each 65.00 1685.87 109581.55
or with glued joint rail or insertion of glued joint
by cutting existing track under traffic condition
by cutting rails, refixing with all rail sleeper
fastenings and providing required gaps for
carrying out welding as an alternative to drilling
holes or joining rails with fish plates duly drilling
holes as required including stacking of released
material and as directed by engineer in-charge.
Note: (1) Drilling holes & rail cutting will be paid
separately. (2) Transportation of materials to
the site of work from supply points, if more than
250m, shall be paid separately.
Fixing of Wooden Distance Block of size 1.0m x
0.3m x 0.15m between track and platform wall.
36 136090 Cleaning of side drains along the track including RM 3200.00 29.98 95936.00
disposing of muck beyond Railway boundary as
per instructions of Engineer in-charge to keep
drains clean and clear in cuttings etc.
37 136100 Removing weeds & bushes in ballast section TRM 32000.00 13.80 441600.00
and cess up to 3.95m from centre line of track
in mid section & station yard, as specified by
Engineer in-charge including disposal of
branches, bushes outside cess/yard.
KHURDA ROAD DIVISION-ENGINEERING/ECOR
Carrying out pre-tamping, during tamping and
post-tamping work for tamping track with all
types of rails, sleepers & sleeper density by
various Track Tamping machines, like
CSM,DUO/3X Machines which include : (1) Re-
adjustment of ballast, heaping-up of ballast,
filling-up of cavities in tamping zone by picking
ballast from stacks / shoulders / crib of
adjoining track up to lead of 50 m to ensure
effective packing; (2) Clearing of ballast on
sleepers to make them visible to operator, (3)
Clearing of ballast over rail foot to facilitate
holding of rail by rollers of TTRM; (4) Digging,
screening and replenishment of ballast at mud
pumping / rounded ballast in sleeper crib
location; (5) Tightening of loose fittings
immediately before & after tamping; (6)
Replacement of broken / missing fittings
supplied by Railway; (7) Correcting displaced
sleepers to position along with squaring; (8) Re-
setting of worked-out / fallen fittings. (9)
Removing and re-fixing joggled fish plates &
wooden blocks, wherever necessary; (10)
Manual consolidation of ballast in crib /
shoulders; (11) Removing and refixing of
traction bonds during the block in electrified
sections (12) Dressing of ballast Note: 1.
Tamping blocks are not identical & it may be
given at any time either during day or night. 2.
Stages of payment a) 30% of the rate will be
paid on completion of pre tamping attention, b)
Balance 70% of the rate will be paid on
completion of post tamping. 3. Recovery at the
rate of twice the above applicable rate will be
effected in case contractor fails to carry out
pre/during/post operation. 4.Payment shall be
made only once in irrespective of numbers of
TTRM packing round and after restoration of
normal speed and restoration of complete
ballast profile.
Providing lighting arrangements with halogen
lamps on and around machine during machine
working in night time blocks, with contractor's
generator, consumables, all necessary electrical
fittings, operators etc. Note: 1. Lighting
arrangement is to be provided as per advance
planning of Night Blocks and written
communication. 2. In case lighting arrangement
is made available but not used due to non-
availability of block, payment @ 60% of the
item rate shall be made. 3. In place of Halogen,
LED lamps of equal lumen capacity may be
used with the approval of Engineer -in-Charge.
4. If lighting arrangement fails during block,
recovery shall be made twice the rate per day.
generator and 8x500 W)
Quick cutting with abrasive rail cutter of all
types of rail sections including wear resistant,
head hardened rails up to 110 UTS, with
contractors tools & plants, equipment,
consumable with all lead & lift etc. complete as
directed by Engineer in-charge. Abrasive Rail
Cutter will be as per RDSO Specification No.
TM/SM/1 (Rev. 01 of 2012) with latest status of
RDSO; Rail Cutting Wheel Abrasive Disc will be
as per RDSO Specification No.TM/SM/2 (Rev. 01
KHURDA ROAD DIVISION-ENGINEERING/ECOR
Drilling holes of 16 mm to 32 mm dia. with Rail
Drilling machine including chamfering with
appropriate chamfering tools in all types of rail
section with contractor's tools & plants,
equipment, consumable with all lead & lift etc.
complete, as directed by Engineer in-charge.
Rail Drilling Machine will be as per RDSO
Specification No. TM/SM/3, dated 24.04.1991.
44 161050 Drilling holes of specified size for bond holes Each 160.00 41.16 6585.60
with 7.2mm dia drill twist to correct spacing and
location on 60kg/52kg rails on cess or under
traffic block with contractor's tools and plant,
equipment, consumable, labour etc complete as
directed by the Engineer in charge at site.
Overhauling of level crossing by digging out up
to 50mm below sleeper, screening of shoulder
& crib ballast, replacing unserviceable sleepers
& fastenings as necessary, removal of check
rails for examination of running rails and check
rails, scrapping of rails and painting running
rails and check rails and all fixtures with two
coats of coal tar emulsion, greasing of ERCs,
MCI inserts and liners oiling all the bolts,
correcting cross level, gauge, alignment,
surfacing and packing etc., re-fixing check rails
duly ensuring standard clearances, re-inserting
screened ballast, making good deficient ballast
with Railway's ballast from stacks /
heaps/borrowing from adjacent length of
adjoining track within 50m lead, ramming &
levelling road surface and refixing concrete
slabs/making motarable road surface as
required excluding re surfacing with bitumen as
directed by Engineer in-charge.
45 182012 Level crossings with concrete blocks road Sqm 160.00 485.14 77622.40
Fixing of wooden blocks of approximate size of
150mm x 300mm x 1200mm on end of check
rails including sizing at level crossings with
contractor's labour, tools & plants and as
Manufacturing, fabricating and supplying retro-
reflective Level Crossing Indicator boards, made
of 2mm thick aluminium sheet or 3mm thick
aluminium composite sheet, face to be fully
covered with high intensity encapsulated type
heat activated retro-reflective sheeting
conforming to type-IV of ASTM-D4956-01 in
yellow & black or other colour combination
including subject matter, message, symbols,
borders etc. as approved by Engineer In-charge
or as per IRPWM guidelines, pasted on substrate
by an adhesive backing which shall be activated
by applying heat and pressure conforming to
class-2 of ASTM-D-4956-01 and fixing the same
with suitable sized aluminium alloy rivets @ 20
cm c/c to back-support frame of M.S. angle iron
of size 25mm x 25mm x 3mm provided all
along the edges of board with theft resistant
measures, back side of board shall be with non-
peelable weather-proof paint, consisting of one
coat of zinc chromate primer and two coats of
epoxy paint. Vertical post shall have black &
white anti-corrosive paint or powder coating
complete, as directed.
KHURDA ROAD DIVISION-ENGINEERING/ECOR
47 202011 Bilingual Whistle Boards for level crossing of Set 12.00 7274.09 87289.08
size 600mm x 600mm of each board with back
support frame welded to vertical post of MS T
section of size 75mm x 75mm x 6mm x
48 202012 Speed Breaker / Rumble Strips Board of size Set 12.00 6720.24 80642.88
900 mm equilateral triangular shape and
600mmx200mm boards with back support
frame welded to vertical post of MS T section of
size 80mmx80mmx8mmx3650mm
49 202014 Manned Level Crossing Indicator Board of size Set 12.00 6203.03 74436.36
900 mm equilateral triangular shape with back
support frame welded to vertical post of MS T
section of size 80mmx80mmx8mmx3650mm
Manufacturing, fabricating and supplying retro-
reflective Engineering Indicator boards, made of
2mm thick aluminium sheet or 3mm thick
aluminium composite sheet, face to be fully
covered with high intensity encapsulated type
heat activated retro-reflective sheeting
conforming to type-IV of ASTM-D4956-01 in
yellow & black or other colour combination
including subject matter, message, symbols,
borders etc. as approved by Engineer In-charge
or as per IRPWM guidelines, pasted on substrate
by an adhesive backing which shall be activated
by applying heat and pressure conforming to
class-2 of ASTM-D-4956-01 and fixing the same
with suitable sized aluminium alloy rivets @ 20
cm c/c to back-support frame of M.S. angle iron
of size 25mm x25mm x 3mmprovided all along
the edges of board with theft resistant
measures back side of board shall be with non-
peelable weatherproof paint, consisting of one
coat of zinc chromate primer and two coats of
epoxy paint. Vertical post shall have black &
white anti-corrosive paint or powder coating
complete, as directed.
1400mmx400mm with back support frame fixed
to vertical post of MS angle of size
50mmx50mmx6mm of 3650 mm long
51 202022 Speed Indicator Board of equilateral triangular Each 6.00 5205.56 31233.36
shape having each side of 1000mm with back
support frame fixed to vertical post of MS angle
of size 50mmx50mmx6mm of 3650 mm long
52 202024 Termination Indicator Board of Circular shape Each 6.00 7362.86 44177.16
having diameter of 1000mm with back support
frame welded to vertical post of MS angle of
size 50mmx50mmx6mm of 3950 mm long
Manufacture and supply of Drill Twist, made of
High Speed Steel (HSS) of various sizes of
Addison / I.T. make or equivalent, as directed by
the Engineer in-charge.
57 211120 Fixing vertically the unserviceable PSC sleepers Each 42.00 139.70 5867.40
at locations of tress-passing, railway boundary
or to make temporary store by excavating
trench, fixing PSC sleeper in trench and filling
back open trench.
KHURDA ROAD DIVISION-ENGINEERING/ECOR
58 211130 Providing and fixing Trolley Refuge of size 3.0m Each 18.00 3924.17 70635.06
x3.0m on cess, placing with released
unserviceable PSC sleepers and keeping them
at all four sides of refuge and also placing as
matting inside the refuge by keeping them in
upside down position with a minimum of 14
sleepers including levelling with earth,
excavation, all lead and lift, crossing of tracks,
leading the sleepers with in a free lead and lift,
handling etc., with all contractor's men material
complete and as directed by the Engineer-in-
charge. Note: Earth-work will to be paid
separately under relevant item.
Hiring of machinery for minor miscellaneous
works for short duration including
operator/driver, fuel, lubricants and
consumable. The contractor shall arrange all
statutory permits as required by rules and
regulations prevailing in the area of work.
Payment shall be made for actual working
59 211202 Hydra or similar tyre mounted Pick-n-Carry Hour 14.00 1134.57 15883.98
crane of 12T capacity for misc. works of
handling of material
Schedule C-Unless otherwise specified, the unit rates for the Items of Sch-C shall include the cost of
following. a) All labour and materials, tools and plants, equipment's, machinery etc. b) All lead, lift,
ascent, descent etc. c) All handling, rehandling, loading, unloading, freight, consumable stores
fuels, lubricants, transportation, vehicles, diplorring and when & where required and crossing one
or more lines if necessary. d) All taxes including octroi on materials, royalty, GST and all incidental
charges complete.
Item- 1 Please see Item Breakup for details.
S No. Item Description of Item Unit Qty Rate Amount
1 1 Supply of Oxygen gases in the working site as Each 10.00 300.00 3000.00
directed by Engineer in Charge. Cylinder
2 2 Supply of DA gases in the working site as Each 5.00 300.00 1500.00
directed by Engineer in Charge. Cylinder
3 3 Supply of Rail Thermometer metal body Each 50.00 1121.00 56050.00
(Magnetic base type) as per RDSO specification
No. TM/67 (Rev. 01 of 2010.Overall length: 200
+ 5mm (including casing), Overall length of
capillary tube: 186 +2 mm, Least Count: 1.00 C,
Temperature Range: - 50 to +850C, Weight:
Within 120gms., Temperature Recording Time:
Within six minute.
4 4 Supply of Box type Gauge cum Level (BG) as Each 50.00 2856.00 142800.00
per RDSO Specification No. TM/58 Dt.
11.06.2001 with 2 year warranty.
7 7 Supply of Anticorrosive bituminous paint Litre 200.00 105.80 21160.00
Schedule D-Unless otherwise specified, the unit rates for the Items of Sch-D shall include the cost of
following. a) All labour and materials, tools and plants, equipment's, machinery etc. b) All lead, lift,
ascent, descent etc. c) All handling, rehandling, loading, unloading, freight, consumable stores
fuels, lubricants, transportation, vehicles, diplorring and when & where required and crossing one
or more lines if necessary. d) All taxes including octroi on materials, royalty, GST and all incidental
charges complete.
Item- 1 Please see Item Breakup for details.
S No. Item Description of Item Unit Qty Rate Amount
KHURDA ROAD DIVISION-ENGINEERING/ECOR
1 1 Removing of Burrs on stock rails, Tongue rails & Turn- 20.00 325.00 6500.00
other locations near points & crossings zone on out
track in yards where required with all
contractor's lead, lift, labour, materials, loading,
unloading, transportation, tools & plants, taxes
etc complete as directed by the Engineer in
charge or his authorised representative at work
2 2 Rendering track circuit bond at rail joints and Per Joint 100.00 11.04 1104.00
traction bonds between rails and OHE masts
with contractor's materials.
3 3 Painting of inservice guard rails two coats with Per 700.00 42.00 29400.00
brush after surface preparation with contractors Metre
anticorrosive bituminous black paint to IS 9862 - of Rail
4981 to a thickness of 100 microns per each
coat on flange, web finishing plane and guage
face on both GF & NGF sides including top of
head i.e. complete round the rails on both the
rails including surface preparation and painting
of rails screws and washers for 52 Kg rails with
all contractors, labour, tools, plant, lead, lift,
brushes, paints, transportation including surface
preparation and painting of rails as per the
procedure given in procedural order for painting
and latest instruction and correction slip on the
subject and as specified including crossing of
track, handling of rails and as directed by
Engineer-in-charge.
Opening and dressing of unloaded ballast. Track
5 5 Renewal of broken/ defective Spl. PSC sleepers Per 100.00 130.00 13000.00
on SEJ's including carrying of sleepers & fittings Sleeper
and stacking of released materials with a free
lead of 100mtr including two rounds of packing.
6 6 Painting and lettering gradient posts, km posts, Each 1000.00 101.86 101860.00
curve plates, boundary pillars/marks etc two
coats (both sides) along the railway tracks.
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .