| Sl No | Description | Qty | Unit | M Karthik L2 | G.Prakash L1 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand,silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering, ,and baling out water and cleaning and levelling the site etc.,complete | 51 | cum | 126 ₹6,426 | 120 ₹6,120 Lowest |
| 2.00 | Supplying and filling in foundation, basement, etc with filling sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. | 17 | cum | 1,900 ₹32,300 | 1,811 ₹30,787 Lowest |
| 3.00 | Plain Cement Concrete 1:4:8 (One Cement, Four sand and Eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and curing etc. complete complying with standard specification | 17 | cum | 5,966 ₹1,01,422 | 5,687 ₹96,679 Lowest |
| 4.00 | Supplying and filling the basement with Good Earth filling in layers of not more than 15cm thick well rammed watered and compacted - etc., complete complying with standard specification. | 1,882 | cum | 290 ₹5,45,780 | 276 ₹5,19,432 Lowest |
| 5.00Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | |||||
| 5.10 | Plinth beam | 504 | sqm | 600 ₹3,02,400 | 572 ₹2,88,288 Lowest |
| 6.00 | Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. | 68 | sqm | 322 ₹21,896 | 307 ₹20,876 Lowest |
| 7.00 | Supplying and fixing of MS grills with Door and windows with one coat of Red oxide with primer including all costs such as welding, grinding and fabrication charges, cost and conveynace of all materials to site etc, compete as per standard specification. | 720 | kg | 117 ₹84,240 | 111 ₹79,920 Lowest |
| 8.00 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat etc., complete complying with standard specification. (The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) | 111 | sqm | 172 ₹19,092.69 | 164 ₹18,204.66 Lowest |
| 9.00 | Supplying and painting the walls with two coats of cement paint as instructed by the departmental officers including preparation of surface curing, etc., complete in all floors complying with standard specifications (The colour and shade of the cement paint shall be got approved by the Executive Engineer before use of work). | 512 | sqm | 183 ₹93,696.73 | 175 ₹89,600.7 Lowest |
Tender Value
₹49 L
EMD Value
₹49,000
Closing Date
13 Feb 2026, 3:00 pmClosed
The Commissioner, Thiruverkadu Municipality
Municipal office, Thiruverkadu, Chennai
Providing of Childrens Park and Development works to Balakrishna Nagar Park in ward No.01
2026_MAWS_652067_22
1245/2025/E1
Open Tender
Civil Works - Others
Works
Municipal office, Thiruverkadu, Chennai
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹49,000
20 Jul 2026
9 Feb 2026
13 Feb 2026
9 Feb 2026
13 Feb 2026
9 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand,silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering, ,and baling out water and cleaning and levelling the site etc.,complete | 51 | cum | - | - |
| 2 | Supplying and filling in foundation, basement, etc with filling sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. | 17 | cum | - | - |
| 3 | Plain Cement Concrete 1:4:8 (One Cement, Four sand and Eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and curing etc. complete complying with standard specification | 17 | cum | - | - |
| 4 | Supplying and filling the basement with Good Earth filling in layers of not more than 15cm thick well rammed watered and compacted - etc., complete complying with standard specification. | 1,882 | cum | - | - |
| 5Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | |||||
| 5.1 | Plinth beam | 504 | sqm | - | - |
| 6 | Plastering with Cement Mortar 1:5 (One cement and Five sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. | 68 | sqm | - | - |
| 7 | Supplying and fixing of MS grills with Door and windows with one coat of Red oxide with primer including all costs such as welding, grinding and fabrication charges, cost and conveynace of all materials to site etc, compete as per standard specification. | 720 | kg | - | - |
| 8 | Painting new iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with two coats of best approved first quality and colour of synthetic enamel paint over the existing red oxide priming coat in all floors excluding cost of priming coat etc., complete complying with standard specification. (The make, quality and colour of paint should be got approved by the Executive Engineer before use on works.) | 111 | sqm | - | - |
| 9 | Supplying and painting the walls with two coats of cement paint as instructed by the departmental officers including preparation of surface curing, etc., complete in all floors complying with standard specifications (The colour and shade of the cement paint shall be got approved by the Executive Engineer before use of work). | 512 | sqm | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.59 MB
BOQ_782045.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].