| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹5.9 LAccepted-AOC | 1 | Accepted-AOC The lowest rate quoted by the contractor RAVI V | |
| 2 | 2₹6.0 L+₹2,291.40 (0.39%)Rejected-Finance | 2 | Rejected-Finance Admitted |
| Sl No | Description | Qty | Unit | RAVI V L1 | RAMASAMY KANNAN L2 |
|---|---|---|---|---|---|
| 1.00Construction of Kariyamedai in Mathur village at Mathur Panchayat in Acharapakkam Panchayat Union in Chengalpattu District under SFC (District Panchayat-General Fund)2025-26 Having Package NO: 03/ 2025-26. Estimate Amount : Rs.6.00 Lakhs | |||||
| 2.00 | Earth work excavation in all classes ofsoil with intial lead and lift etc., completeas per SS 20 B for foundation. | 7.56 | cum | 263 ₹1,988.28 Lowest | 269 ₹2,033.64 |
| 3.00 | Supplying and Filling foundation and basement with filling M.sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification. | 2.58 | cum | 1,736 ₹4,478.88 Lowest | 1,739 ₹4,486.62 |
| 4.00 | Cement concrete 1:4:8 Mix using 40mm ISS HBG metal including cost and conveyance of materials to site including cost and labour charges for compacting curing and all incidental charges etc. complete | 3.53 | cum | 5,442 ₹19,210.26 Lowest | 5,446 ₹19,224.38 |
| 5.00 | Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.Upto Basement | 2.33 | cum | 9,326 ₹21,729.58 Lowest | 9,328 ₹21,734.24 |
| 6.00 | Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.Above Basement | 10.35 | cum | 9,467 ₹97,983.45 Lowest | 9,469 ₹98,004.15 |
| 7.00 | Brick work in cement mortar 1:5 mix using Chamber brick including cost and other conveyance of all etc. | 7.56 | cum | 6,144 ₹46,448.64 Lowest | 6,148 ₹46,478.88 |
| 8.00 | Supplying and fabrication of steel including cost and conveyance and cutting, bending, tying and placing in position | 0.86 | mt | 91,858 ₹78,997.88 Lowest | 91,859 ₹78,998.74 |
| 9.00 | Supplying and erecting centering of sides and soffits including supports and strutting up to height for plane surfaces in all floors etc. complete. Upto Basement | 19.63 | Sqm | 547 ₹10,737.61 Lowest | 549 ₹10,776.87 |
| 10.00 | Supplying and erecting centering of sides and soffits including supports and strutting up to height for plane surfaces in all floors etc. complete.Above Basement | 82.11 | Sqm | 1,095 ₹89,910.45 Lowest | 1,099 ₹90,238.89 |
Tender Value
₹6 L
EMD Value
₹6,000
Closing Date
12 Nov 2025, 3:00 pmClosed
Block Development Officer (BP) Acharapakkam
Block Development Office (BP) Acharapakkam
Construction of Kariyamedai in Mathur village at Mathur Panchayat in Acharapakkam Panchayat Union in Chengalpattu District under SFC (District Panchayat-General Fund)2025-26
2025_RDTN_620672_1
No DIPR/181/CDP A2
Open Tender
Civil Works
Item Rate
90 days
Mathur
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹6,000
Yes
Block Development Office (BP) Acharapakkam
10 Mar 2026
7 Nov 2025
12 Nov 2025
7 Nov 2025
12 Nov 2025
7 Nov 2025
7 Nov 2025
Amount
Construction of Kariyamedai in Mathur village at Mathur Panchayat in Acharapakkam Panchayat Union in Chengalpattu District under SFC (District Panchayat-General Fund)2025-26 Having Package NO: 03/ 2025-26. Estimate Amount : Rs.6.00 Lakhs
Earth work excavation in all classes ofsoil with intial lead and lift etc., completeas per SS 20 B for foundation.
Supplying and Filling foundation and basement with filling M.sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1:4:8 Mix using 40mm ISS HBG metal including cost and conveyance of materials to site including cost and labour charges for compacting curing and all incidental charges etc. complete
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.Upto Basement
Reinforced Cement concrete 1:1.5:3 mix using 20mm HBG metal for foundation and basement etc. complete.Above Basement
Brick work in cement mortar 1:5 mix using Chamber brick including cost and other conveyance of all etc.
Supplying and fabrication of steel including cost and conveyance and cutting, bending, tying and placing in position
Supplying and erecting centering of sides and soffits including supports and strutting up to height for plane surfaces in all floors etc. complete. Upto Basement
Supplying and erecting centering of sides and soffits including supports and strutting up to height for plane surfaces in all floors etc. complete.Above Basement
Providing the following thickness of Granolithic pattern floor finish with Plain Cement concrete 1 : 2 : 4 mix using 20mm ISS HBG metal and the top rubed smooth etc., complete
Finishing the top of roof with one course of machine pressed tiles of size 20 x 20 x 2cm of approved quality laid in CM 1:3, 12mm thick.
Plastering with cement mortar 1:5 mix, 12 mm thickness including cost and conveyance
Supplying and applying of two coats of putty of 3mm thick over the exposed RCC surface of ceiling including finishing the joints smoothy with grinding machine and the surface shall be thoroughly cleaned out of dust and scrubbing. The Surface shall then be allowed to dry for atleast 48 hours. It shall then be sand papered (waterproof abrasive sheet) to give a smooth and even surface. Any unevenness shall be made good by applying 1st coat of putty mixed with water on the entire surface including filling up the undulations and applying 2nd coat of putty after 6 hours of 1st coat of putty and then sand papering (waterproof abrasive sheet) the same after it is dry and finishing the surface smoothly, etc., complete complying with standard specifications and as directed by the Departmental Officers. [ The rates are inclusive of hire charges for grinding machine with wheel, cost of sand paper (waterproof abrasive sheet), cost of putty blade, labour charges for grinding the joints and sand papering, two coat of putty, scrapping the putty area to level the surface smooth, etc., complete]. The Putty shoule be got approved by the Executive Engineer before use on work.
Painting two coats with ready mixed plastic emulsion of first class quality paint and of approved colour over priming coat including scrapping clean removal etc complete and including necessary plaster of putty wherever required.
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
RAMASAMY KANNAN (BID ID -1506371)
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.55 MB
BOQ_742198.xls
BOQ • 0.27 MB
Technical.pdf
Tender Documents • 1.00 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .