Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹3.1 L
Closing Date
22 Oct 2026, 5:00 pm
Eo Npp Hamirpur
Nagar Palika Parishad Hamirpur
Construction of RCC drains and covers from Sumit Jewellers house to Shyam Agarwal house, from Abrar house to Bholu Nigam house, from Ramsajivan house to Munnalal Gupta house, from Lallu Dhuriya house to Dinesh Rathore house, and from Manu Singh hou
2026_DOLBU_1191431_15
826/PW/VthSFC/2026-27 DATED 29.09.2026
Open Tender
Civil Works
Percentage
120 days
Hamirpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,610
Yes
Executive Officer
₹3.1 L
Yes
Nagar Palika Parishad Hamirpur
30 Sept 2026
30 Sept 2026
23 Oct 2026
30 Sept 2026
22 Oct 2026
30 Sept 2026
6 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Photography work etc. | 1 | Job | 500 | ₹500 |
| 2 | Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m, as directed by Engineer-in- Charge:(All kinds of soil)
As per DSR-2.1.1 | 386 | Cum | 94 | ₹36,284 |
| 3 | Supplying and filling in plinth with sand under floors, including watering,ramming, consolidating and dressing complete.As per DSR-2.27 | 78.6 | Cum | 1,546 | ₹1,21,515.6 |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources).As per DSR-4.1.8 | 52.4 | Cum | 4,960 | ₹2,59,904 |
| 5 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size) :.As per DSR-5.2.2 | 136.5 | Cum | 7,900 | ₹10,78,350 |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting,bending, placing in position and binding all complete upto plinth level. Mild steel and Medium Tensile steel bars.As per DSR-5.22.1 | 96.62 | Qtl. | 7,700 | ₹7,43,974 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form work for :Foundations, footings, bases for columns.As per DSR-4.3.1 | 1,312 | Sqm | 285 | ₹3,73,920 |
| 8 | Providing & laying RCC PRE CAST Cover Size 1000x600x100 mm with 2 mm thick ms sheet in outer side of cover and 2 number round manhole PVC cover katori including all cost of material labour t&p etc all complete.(As per Analysis Rate) | 40 | No. | 1,826.64 | ₹73,065.6 |
| 9 | Providing & laying RCC PRE CAST Cover Size 800x600x100 mm with 2 mm thick ms sheet in outer side of cover and 2 number round manhole PVC cover katori including all cost of material labour t&p etc all complete.(As per Analysis Rate) | 50 | No. | 1,545.03 | ₹77,251.5 |
| 10 | Providing & laying RCC PRE CAST Cover Size 1000x500x75 mm with 2 mm thick ms sheet in outer side of cover and 2 number round manhole PVC cover katori including all cost of material labour t&p etc all complete.(As per Analysis Rate) | 35 | No. | 1,264.74 | ₹44,265.9 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.88 MB
Tendernotice_2.pdf
PDF • 1.19 MB
BOQ_2247320.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .