| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.9 LAccepted-AOC 3 6E PARK JUNCTION THIRUVARAMBU | ₹2.9 L | L1 | Accepted-AOC L1 |
| Sl No | Description | Qty | Unit | NISSI ELECTRICALS L1 |
|---|---|---|---|---|
| 1.01 | Loading&unloading of 9m PSC pole | 13 | Each | 7,800 ₹9,204 |
| 2.01 | Excavation of 9m pole pits(1.25m*0.6m*1.83m) in Normal Ground | 13 | per pit | 9,750 ₹11,505 |
| 3.01 | Erection of 9m PSC pole in Normal Ground | 13 | per pole | 10,400 ₹12,272 |
| 4.01 | Transportation of 9m PSC pole from road side to pole pit upto 2KM | 13 | Each Pole | 10,400 ₹12,272 |
| 5.01 | Loading&unloading of 8m PSC pole | 37 | Each | 14,800 ₹17,464 |
| 6.01 | Excavation of 8m pole pits(1.25m*0.5m*1.5m) in Normal Ground | 37 | per pit | 18,500 ₹21,830 |
| 7.01 | Erection of 8m PSC pole in Normal Ground | 37 | per pole | 20,350 ₹24,013 |
| 8.01 | Transportation of 8m PSC pole from road side to pole pit upto 2KM | 37 | Each Pole | 22,200 ₹26,196 |
| 9.01 | Erection of Guarding X arm | 2 | Each | 500 ₹590 |
| 10.01 | Erection of V X arm 4.5 feet | 5 | Each | 2,000 ₹2,360 |
Tender Value
Refer Docs
EMD Value
₹2,920
Closing Date
21 Jan 2026, 2:00 pmClosed
EE/TKY
TNEB TKY
Eos for 1no Domestic Service Connection to Thiru S Vincent Raj at Vendalicode under Urban Kulasekharam Section in Thuckalay division
2026_EB_640148_1
EE/D/TKY/ETW 25/Dt.07.01.2026
Open Tender
Electrical Works
90 days
EE/TKY
As specified tender
3 documents required · 3 mandatory
₹0
₹2,920
Yes
7 Mar 2026
7 Jan 2026
22 Jan 2026
8 Jan 2026
21 Jan 2026
8 Jan 2026
8 Jan 2026 - 21 Jan 2026
Loading&unloading of 9m PSC pole
Excavation of 9m pole pits(1.25m*0.6m*1.83m) in Normal Ground
Erection of 9m PSC pole in Normal Ground
Transportation of 9m PSC pole from road side to pole pit upto 2KM
Loading&unloading of 8m PSC pole
Excavation of 8m pole pits(1.25m*0.5m*1.5m) in Normal Ground
Erection of 8m PSC pole in Normal Ground
Transportation of 8m PSC pole from road side to pole pit upto 2KM
Erection of Guarding X arm
Erection of V X arm 4.5 feet
Fixing of HT/LT TI fittings
Erection of Tapping channel X arm
Fixing of HT pin insulator
Fixing of HT strain disc 11KV
Fixing of LT S phase cross arm
Fixing of LT 3 phase cross arm
Fixing of LT pin insulator
Fixing of shackle
Fixing of aluminium knob
Excavation of stay pit (1.00m*0.5m*1.5m) in normal ground
Erection of stay set complete in normal ground
Paving and stringing of LT ACSR 7/2.59 conductor in pin point
Paving and stringing of LT ACSR 7/2.59 conductor in cut point
Paving and stringing of HT ACSR 7/4.09 conductors equivalent conductor in cut point
Coil earthing per pole & pole earthing
Concreting of poles as per board standards(2'*2'*5'). The material such as sand jelly etc have to be supplied by the contractor cement supplied by the contractor (Cement concrete mix 1:4:8 using 40mm hard broken stone including cost of labour charges for placing transporting of sand jelly from box and water curing for 14 days etc complete)
Loading&unloading of line materials
Transportation of line materials from Section Office to work spot up to 20 KM
Drilling/less than 23mm hole per hole/slatted hole
Ordinary tree clearance
Erection of Single phase Service connection
Erection of Three phase Service connection
Dismantling of Single phase Service connection
Dismantling of Three phase Service connection
Dismantling & refixing of V X arm 4.5 feet
Dismantling & refixing of TI fittings
Dismantling & refixing of HT pin insulator
Dismantling & refixing of tapping cross arm 4.5 feet
Dismantling & refixing of LT S phase cross arm
Dismantling & refixing of LT 3 phase cross arm
Dismantling & refixing of LT pin insulator
Dismantling & refixing of shackle
Dismantling & refixing of aluminium knob
Dismantling & Restringing of LT ACSR 7/2.59 conductors in pin point
Dismantling of 9mtr PSC pole
Dismantling of 8mtr RCC,REC, PSC &metal pole including the closing of the pit
Dismantling of conductors of 7/4.09mm ACSR or other equivalent conductor in cut point
Dismantling of conductors of 7/4.09mm ACSR or other equivalent conductor in pin point
Dismantling of conductors of ACSR 7/2.59 Conductor in cut point
Dismantling of conductors of ACSR 7/2.59 Conductor in pin point
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.75 MB
Tendernotice_2.pdf
PDF • 1.37 MB
BOQ_766487.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid