GEMC-511687711435631
Awarded to NITIN KUMAR CONTRACTOR
₹44.4 L
Products
| Product | Brand / Model | HSN | Quantity | Unit Price | Amount |
|---|---|---|---|---|---|
| Mill House Item No 1 | NA | 0000000000 | 10 Each Roller | 3,015.57 | 30,155.7 |
| Mill House Item No 2 | NA | 0000000000 | 675 Per Meter | 28.26 | 19,075.5 |
| Mill House Item No 3 | NA | 0000000000 | 120 Each Link | 76.96 | 9,235.2 |
| Mill House Item No 4 | NA | 0000000000 | 100 Each Link | 76.96 | 7,696 |
| Mill House Item No 5 | NA | 0000000000 | 2 Per boot | 1,873.51 | 3,747.02 |
| Mill House Item No 6 | NA | 0000000000 | 20 Each ring | 1,765.82 | 35,316.4 |
| Mill House Item No 7 | NA | 0000000000 | 150 Per Meter | 155.28 | 23,292 |
| Mill House Item No 8 | NA | 0000000000 | 18 Each pinion | 6,434.58 | 115,822.44 |
| Mill House Item No 9 | NA | 0000000000 | 3 Each Box | 5,159.67 | 15,479.01 |
| Mill House Item No 10 | NA | 0000000000 | 10 Each cover | 1,715.71 | 17,157.1 |
| Mill House Item No 11 | NA | 0000000000 | 200 Per meter | 566.82 | 113,364 |
| Mill House Item No 12 | NA | 0000000000 | 70 Per sq meter | 907.96 | 63,557.2 |
| Mill House Item No 13 | NA | 0000000000 | 210 Per feet | 37.22 | 7,816.2 |
| Mill House Item No 14 | NA | 0000000000 | 180 Per feet | 35.96 | 6,472.8 |
| Mill House Item No 15 | NA | 0000000000 | 115 Per sq meter | 169.08 | 19,444.2 |
| Mill House Item No 16 | NA | 0000000000 | 50 Each | 472 | 23,600 |
| Mill House Item No 17 | NA | 0000000000 | 1 Each | 6,919 | 6,919 |
| Mill House Item No 18 | NA | 0000000000 | 4 Each | 7,815.91 | 31,263.64 |
| Mill House Item No 19 | NA | 0000000000 | 30 Each | 156.21 | 4,686.3 |
| Mill House Item No 20 | NA | 0000000000 | 2 L S each | 18,763.7 | 37,527.4 |
| Mill House Item No 21 | NA | 0000000000 | 18 Each | 1,481.52 | 26,667.36 |
| Mill House Item No 22 | NA | 0000000000 | 2 L S | 11,916.11 | 23,832.22 |
| Mill House Item No 23 | NA | 0000000000 | 1,500 nos | 47.5 | 71,250 |
| Mill House Item No 24 | NA | 0000000000 | 2 nos | 7,720.73 | 15,441.46 |
| Mill House Item No 25 | NA | 0000000000 | 1 no | 10,093.93 | 10,093.93 |
| Mill House Item No 26 | NA | 0000000000 | 60 nos | 37.22 | 2,233.2 |
| Mill House Item No 27 | NA | 0000000000 | 4 nos | 11,733.27 | 46,933.08 |
| Mill House Item No 28 | NA | 0000000000 | 34 nos | 2,333.12 | 79,326.08 |
| Mill House Item No 29 | NA | 0000000000 | 1 job | 2,523.49 | 2,523.49 |
| Mill House Item No 30 | NA | 0000000000 | 2 nos | 12,112.73 | 24,225.46 |
| Mill House Item No 31 | NA | 0000000000 | 20 nos | 320.6 | 6,412 |
| Mill House Item No 32 | NA | 0000000000 | 8 nos | 3,784.59 | 30,276.72 |
| Mill House Item No 33 | NA | 0000000000 | 2 nos | 4,415.77 | 8,831.54 |
| Mill House Item No 34 | NA | 0000000000 | 5 nos | 3,062 | 15,310 |
| Mill House Item No 35 | NA | 0000000000 | 1 set | 9,676 | 9,676 |
| Mill House Item No 36 | NA | 0000000000 | 1 job | 30,237.5 | 30,237.5 |
| Mill House Item No 37 | NA | 0000000000 | 24 per Meter square | 2,492.05 | 59,809.2 |
| Mill House Item No 38 | NA | 0000000000 | 1 job | 36,285 | 36,285 |
| Mill House Item No 39 | NA | 0000000000 | 280 nos | 134.85 | 37,758 |
| Mill House Item No 40 | NA | 0000000000 | 1 job | 18,323.93 | 18,323.93 |
| Mill House Item No 41 | NA | 0000000000 | 50 nos | 1,832.39 | 91,619.5 |
| Mill House Item No 42 | NA | 0000000000 | 130 nos | 641.33 | 83,372.9 |
| Mill House Item No 43 | NA | 0000000000 | 115 nos | 415.34 | 47,764.1 |
| Boiler House Item No 1 | NA | 0000000000 | 2 nos | 4,358.17 | 8,716.34 |
| Boiler House Item No 2 | NA | 0000000000 | 1 no | 12,225.43 | 12,225.43 |
| Boiler House Item No 3 | NA | 0000000000 | 1 no | 12,225.43 | 12,225.43 |
| Boiler House Item No 4 | NA | 0000000000 | 100 per mts | 566.82 | 56,682 |
| Boiler House Item No 5 | NA | 0000000000 | 2 nos | 9,735 | 19,470 |
| Boiler House Item No 6 | NA | 0000000000 | 108 per Sq Mts | 169.08 | 18,260.64 |
| Boiler House Item No 7 | NA | 0000000000 | 15 nos | 2,201.63 | 33,024.45 |
| Boiler House Item No 8 | NA | 0000000000 | 52 Metric tons | 11,733.27 | 610,130.04 |
| Boiler House Item No 9 | NA | 0000000000 | 6 nos | 4,358.17 | 26,149.02 |
| Boiler House Item No 10 | NA | 0000000000 | 2 nos | 7,402.86 | 14,805.72 |
| Boiler House Item No 11 | NA | 0000000000 | 8 nos | 2,177.1 | 17,416.8 |
| Boiler House Item No 12 | NA | 0000000000 | 1 nos | 5,992 | 5,992 |
| Boiler House Item No 13 | NA | 0000000000 | 8 per MT | 21,650 | 173,200 |
| Boiler House Item No 14 | NA | 0000000000 | 516 meter | 28.4 | 14,654.4 |
| Boiler House Item No 15 | NA | 0000000000 | 30 per nos | 2,207.42 | 66,222.6 |
| Boiler House Item No 16 | NA | 0000000000 | 4 per nos | 9,008.15 | 36,032.6 |
| Boiler House Item No 17 | NA | 0000000000 | 1 per nos | 8,637 | 8,637 |
| Boiler House Item No 18 | NA | 0000000000 | 5 per nos | 7,328 | 36,640 |
| Boiler House Item No 19 | NA | 0000000000 | 4 per nos | 15,897.31 | 63,589.24 |
| Boiler House Item No 20 | NA | 0000000000 | 3 per nos | 20,656.26 | 61,968.78 |
| Boiler House Item No 21 | NA | 0000000000 | 1 per nos | 5,045.18 | 5,045.18 |
| Boiler House Item No 22 | NA | 0000000000 | 1 per nos | 6,939.27 | 6,939.27 |
| Boiler House Item No 23 | NA | 0000000000 | 3 per nos | 4,214.1 | 12,642.3 |
| Boiler House Item No 24 | NA | 0000000000 | 2 per boiler | 16,283 | 32,566 |
| Boiler House Item No 25 | NA | 0000000000 | 4 nos | 2,523.5 | 10,094 |
| Boiler House Item No 26 | NA | 0000000000 | 1 Per I D Fan | 14,359.43 | 14,359.43 |
| Boiler House Item No 27 | NA | 0000000000 | 1 Per I D Fan | 16,800.27 | 16,800.27 |
| Boiler House Item No 28 | NA | 0000000000 | 8 per nos | 1,653.1 | 13,224.8 |
| Boiler House Item No 29 | NA | 0000000000 | 3 ton | 23,932.38 | 71,797.14 |
| Boiler House Item No 30 | NA | 0000000000 | 2 sets | 5,047 | 10,094 |
| Boiler House Item No 31 | NA | 0000000000 | 2 per nos | 6,095.75 | 12,191.5 |
| Boiler House Item No 32 | NA | 0000000000 | 3 sets | 17,537.75 | 52,613.25 |
| Boiler House Item No 33 | NA | 0000000000 | 30 per nos | 366.47 | 10,994.1 |
| Boiler House Item No 34 | NA | 0000000000 | 30 per nos | 366.47 | 10,994.1 |
| Boiler House Item No 35 | NA | 0000000000 | 20 per nos | 366.47 | 7,329.4 |
| Boiler House Item No 36 | NA | 0000000000 | 160 per nos | 172.3 | 27,568 |
| Pan calandria work | NA | 0000000000 | 1 Lumpsum | 421,850 | 421,850 |
| Spray item no 1 | NA | 0000000000 | 1 Lumpsum | 38,025.5 | 38,025.5 |
| Vaccuum crystalizer | NA | 0000000000 | 1 Lumpsum | 538,670 | 538,670 |
| schedule work 1 | NA | 0000000000 | 120 per feet | 10.23 | 1,227.6 |
| schedule work 2 | NA | 0000000000 | 150 per feet | 15.35 | 2,302.5 |
| schedule work 3 | NA | 0000000000 | 80 per feet | 20.46 | 1,636.8 |
| schedule work 4 | NA | 0000000000 | 75 per feet | 30.69 | 2,301.75 |
| schedule work 5 | NA | 0000000000 | 40 per feet | 40.93 | 1,637.2 |
| schedule work 6 | NA | 0000000000 | 20 per feet | 51.16 | 1,023.2 |
| schedule work 7 | NA | 0000000000 | 6 per nos | 92.56 | 555.36 |
| schedule work 8 | NA | 0000000000 | 8 per nos | 123.41 | 987.28 |
| schedule work 9 | NA | 0000000000 | 8 per nos | 185.12 | 1,480.96 |
| schedule work 10 | NA | 0000000000 | 8 per nos | 246.82 | 1,974.56 |
| schedule work 11 | NA | 0000000000 | 20 per nos | 16.15 | 323 |
| schedule work 12 | NA | 0000000000 | 8 per nos | 32.32 | 258.56 |
| schedule work 13 | NA | 0000000000 | 8 per nos | 48.47 | 387.76 |
| schedule work 14 | NA | 0000000000 | 8 per nos | 96.95 | 775.6 |
| schedule work 15 | NA | 0000000000 | 10 per nos | 129.26 | 1,292.6 |
| schedule work 16 | NA | 0000000000 | 2 per nos | 160.9 | 321.8 |
| schedule work 17 | NA | 0000000000 | 4 per nos | 201.13 | 804.52 |
| schedule work 18 | NA | 0000000000 | 8 per nos | 58.29 | 466.32 |
| schedule work 19 | NA | 0000000000 | 10 per nos | 87.44 | 874.4 |
| schedule work 20 | NA | 0000000000 | 6 per nos | 116.59 | 699.54 |
| schedule work 21 | NA | 0000000000 | 4 per nos | 145.74 | 582.96 |
| schedule work 22 | NA | 0000000000 | 4 per nos | 185.12 | 740.48 |
| schedule work 23 | NA | 0000000000 | 4 per nos | 246.83 | 987.32 |
| schedule work 24 | NA | 0000000000 | 4 per nos | 33.1 | 132.4 |
| schedule work 25 | NA | 0000000000 | 6 per nos | 53.45 | 320.7 |
| schedule work 26 | NA | 0000000000 | 6 per nos | 106.9 | 641.4 |
| schedule work 27 | NA | 0000000000 | 8 per nos | 142.53 | 1,140.24 |
| schedule work 28 | NA | 0000000000 | 4 per nos | 178.16 | 712.64 |
| schedule work 29 | NA | 0000000000 | 8 per each | 1,639.78 | 13,118.24 |
| schedule work 30 | NA | 0000000000 | 4 Per MT | 2,802 | 11,208 |
| schedule work 31 | NA | 0000000000 | 15 Per meter | 172.81 | 2,592.15 |
| schedule work 32 | NA | 0000000000 | 15 Per meter | 200.37 | 3,005.55 |
| schedule work 33 | NA | 0000000000 | 50 Per meter | 17.98 | 899 |
| schedule work 34 | NA | 0000000000 | 25 Per MT | 757.63 | 18,940.75 |
| schedule work 35 | NA | 0000000000 | 2 Per MT | 757.63 | 1,515.26 |
| schedule work 36 | NA | 0000000000 | 2 Per MT | 2,036 | 4,072 |
| schedule work 37 | NA | 0000000000 | 25 Per MT | 2,036 | 50,900 |
| schedule work 38 | NA | 0000000000 | 30 per meter squar | 920.74 | 27,622.2 |
| schedule work 39 | NA | 0000000000 | 25 per MT | 9,676 | 241,900 |
| schedule work 40 | NA | 0000000000 | 48 per Meter square | 781.82 | 37,527.36 |
| schedule work 41 | NA | 0000000000 | 2 per Nos | 342.62 | 685.24 |
| schedule work 42 | NA | 0000000000 | 2 per Nos | 456.82 | 913.64 |
| schedule work 43 | NA | 0000000000 | 3 per Nos | 685.24 | 2,055.72 |
| schedule work 44 | NA | 0000000000 | 2 per Nos | 1,370.48 | 2,740.96 |
| schedule work 45 | NA | 0000000000 | 2 per Nos | 4,568.28 | 9,136.56 |