Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 CrAccepted-Finance | ₹1.6 Cr | L1 | Accepted-Finance Lowest rate for estimate rate |
| 2 | L2₹1.6 Cr+₹1.2 L (0.73%)Accepted-Finance 5 6 JOTHI NAGAR TRICHY CHENNAI BYPASS ROAD TRICHY | TIRUCHIRAPPALLI | TAMIL NADU | 620001 | ₹1.6 Cr+₹1.2 L (0.73%) | L2 | Accepted-Finance Above rate for estimate rate |
Tender Value
Refer Docs
EMD Value
₹1.6 L
Closing Date
10 May 2023, 3:00 pmClosed
JOINT DIRECTOR/PROJECT DIRECTOR
1st floor, DRDA, Collectorate campus,Tiruvarur
1.Sembiyamalalai road km 0/0-1/708 2. Deepamangalam Othaveedu km 0/0- 1/710
2023_RDTN_308387_1
DIPR/2018/Tender/2023 dt 06.04.2023 nlmpack3
Open Tender
Civil Works - Roads
Item Rate
180 days
Nannilam Block
As per Tender document
3 documents required · 3 mandatory
₹0
₹1.6 L
12 Jul 2023
29 Apr 2023
10 May 2023
29 Apr 2023
10 May 2023
29 Apr 2023
Amount
1)R-26 -Strengthening of Deepamangalam Othaveedu Road KM 0/0-1/710
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for base-course and side berms.
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method)
Providing and laying WBM 75mm compacted thickness using Grade II metal using one cubic metre of 75 – 22.4mm IRC size HBG metal with 0.24 cubic metre of gravel of blindage per 10 sqm including cost and conveyance of all materials labour charges for stacking spreading road side and stack to them departmental gauge including all labour charges for spreading metal and sand gravel mix hand packing to compac watering with all leads for water and compaction by 8-10 tones power roller including hire charges and fuel charges for power rollwr water sprinkler and all other tools and plants employed barrcating etc.,completed as per clause 404 of M.O.R.T.specification.
Providing and laying WBM 75mm compacted thickness using Grade III metal using one cubic metre of 63 – 11.2mm IRC size HBG metal with 0.24 cubic metre of gravel of blindage per 10 sqm including cost and conveyance of all materials labour charges for stacking spreading road side and stack to them departmental gauge including all labour charges for spreading metal and sand gravel mix hand packing to compac watering with all leads for water and compaction by 8-10 tones power roller including hire charges and fuel charges for power rollwr water sprinkler and all other tools and plants employed barrcating etc.,completed as per clause 404 of M.O.R.T.specification.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Applying tack coat over WBM surface (not treated with primer) using 2.5Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates
BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Bitumen modified cubes Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Provision of Rumble Strips with premix Bituminous carpet Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20mm high at centre, 250mm wide placed at 1m centre-to-centre approved locations to control speed, marked with while strips of road marking paint. Rumble Strips = 3 X 3.0X 0.25 = 2.25
Road Marking With Hot Applied Thermoplastic Compound With reflectorising Glass Beads on Bituminous Surface:- Providing and laying of hot applied thermoplastic compound 2.50mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35, The finished surface to be level uniform and free from streaks and holes etc complete as per MORTH&H specification No.803
Provision for kilometre stones
Provision for Hectametre stones
Provision for Nameboard & Citizen information Board charges
Provision for sign boards
2) R-63 -Strengthening of Sembiyamzhalai Road KM 0/0-1/708
Clearing the Scrub jungle including all labour charges for burryingng and burning etc.,Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201. etc. comp.
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content and hire fuel charges for powerroller, watersprinkler and all other incidental charges such as traffic barricading and providing dangerlights etc. comp for base-course and side berms.
Providing and laying WBM 75mm compacted thickness using Grade II metal using one cubic metre of 75 – 22.4 mm IRC size HBG metal with 0.24 cubic metre of gravel of blindage per 10 sqm including cost and conveyance of all materials labour charges for stacking spreading road side and stack to them departmental gauge including all labour charges for spreading metal and sand gravel mix hand packing to compac watering with all leads for water and compaction by 8-10 tones power roller including hire charges and fuel charges for power rollwr water sprinkler and all other tools and plants employed barrcating etc.,completed as per clause 404 of M.O.R.T.specification.
Providing and laying WBM 75mm compacted thickness using Grade III metal using one cubic metre of 63-11.2mm IRC size HBG metal with 0.24 cubic metre of gravel of blindage per 10 sqm including cost and conveyance of all materials labour charges for stacking spreading road side and stack to them departmental gauge including all labour charges for spreading metal and sand gravel mix hand packing to compac watering with all leads for water and compaction by 8-10 tones power roller including hire charges and fuel charges for power rollwr water sprinkler and all other tools and plants employed barrcating etc.,completed as per clause 404 of M.O.R.T.specification.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Applying tack coat over WBM surface (not treated with primer) using 2.5Kg of bituminous emulsion per 10 Sqm. including cost of bituminous emulsion which will be supplied departmentally at section stores and cost of which will be recovered at the rates
BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Bitumen modified cubes Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Provision of Rumble Strips with premix Bituminous carpet Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20mm high at centre, 250mm wide placed at 1m centre-to-centre approved locations to control speed, marked with while strips of road marking paint. Rumble Strips = 3 X 3.0X 0.25 = 2.25
Road Marking With Hot Applied Thermoplastic Compound With reflectorising Glass Beads on Bituminous Surface:- Providing and laying of hot applied thermoplastic compound 2.50mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35, The finished surface to be level uniform and free from streaks and holes etc complete as per MORTH&H specification No.803
Provision for kilometre stones
Provision for Hectametre stones
Provision for Nameboard & Citizen information Board charges
Provision for sign boards
Construction of Pipe culvert @ Ch. 1/230
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 4 : 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 3 : 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below Sill)
Supply and erecting centering and shuttering with steel materials including all labour charges etc.,complete
Providing and laying reinforced cement concrete pipe NP3 900 mm Dia for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry
Gravel filling between body wall including cost and conveyance of gravel, labour for filling, watering and compacting etc complete complying with standard specification and as directed by the departmental officer.
Construction of Protective work @ Ch.1/230
Earth work Excavation for Foundation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and requiring the sides of foundation.
Supplying and Filling foundation and basement with filling sand in layers not more than 15cm . Thick well ramed, watered and compacted Complete complying with stanard specification.
Cement concrete 1 : 4: 8 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed.
Cement concrete 1 : 3: 6 mix using 40mm HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. (Below Sill)
Supply and erecting centering and shuttering with steel materials including all labour charges etc.,complete
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
Maintenance cost for 1)R-26 -Strengthening of Deepamangalam Othaveedu Road KM 0/0-1/710
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Maintenance cost for R-63 -Strengthening of Sembiyamzhalai Road KM 0/0-1/708
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
Dhinakaran and Co
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .