| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.2 LAccepted-AOC | ₹8.2 L | L1 | Accepted-AOC AOC |
| 2 | L2₹8.5 LRejected-Finance | ₹8.5 L | L2 | Rejected-Finance Reject due to higher rate quoted |
| 3 | Not Admitted-Fee/PreQual/Technical GSTIN: 06AAGAT4295F1ZA | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹8.2 L
EMD Value
₹16,496
Closing Date
16 Feb 2026, 11:00 amClosed
SATPAL
Municipal Council Hodal
Repair / construction of road and drain from h/o santa sujwadi wale to bhuri singh and h/o sonu kamriya to h/o Bir singh master in ward no 05 mc hodal.
2026_HRY_501357_1
2026A4D5E09A FFEA 4E3F B0AE 28C0B25361FA329ULB
Open Tender
Civil Works
255 days
Hodel
2 documents required · 2 mandatory
₹1,000
₹16,496
Yes
13 May 2026
9 Feb 2026
16 Feb 2026
9 Feb 2026
16 Feb 2026
9 Feb 2026
[10.100.2]Cement Concrete 1:8:16 Flooring 2. Cement Concrete 1:8:16 with stone aggregate 40 mm size in foundation and plinth. [Through Rate]
[11.5.4]12 mm cement plaster of mix : 4. 1:6 (1 cement: 6 fine sand) [Through Rate]
[17.15.2]Granular Sub-Base with Coarse Graded Material - Grading-I or II or III (Table:- 400-2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORTandH specifications 2. Grading II material [Through Rate]
[17.23.1]Water Bound Macadam Grading - II 1. Water Bound Macadam (63mm to 45 mm) Grading I with screening Type “A” (13.2 mm aggregates) Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/ binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density complete as per technical clause 404 of MORT&H specifications [Through Rate]
[17.5.3]Compacting Original Ground 3. Compaction of Earthwork Compaction of & preparation of sub grade including loosening, levelling of earth 225 mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 3000-2 as per technical clause 305 of MORT&H specifications [Through Rate]
[17.69.2]Interlocking Concrete Block Pavement 2. Providing and Laying 80 mm thick ISI marked Interlocking Paver Blocks conforming to IS 15658:2006/IRC SP 63: 2004 of all shapes and colours in design mix cement M 40 over the bed of 30 mm thick fine sand complete in all respect. [Through Rate]
[17.70]Removal of existing IPB by manual means and disposal of dismantled material with all lead and lift as per technical specification clause 202.3. [Through Rate]
[17.71]Relaying of available (removed and stacked) Interlocking Paver Block Pavement having thickness 100mm/80 mm/ 60 mm (average = 80mm) as per drawings and Technical Specification Clause 1504 [Through Rate]
[21.53]Constructing standard drain type I drain moulded and laid over lime concrete foundation rendered and finished smooth with 6 mm thick rendering concrete to be of 1.3.6 parts by volume of cement sand stone bajri and rendering to be 1:1 cement sand mortar [Through Rate]
[3.1.2]By Mechanical Transport including loading, unloading and stacking 2. Earth [5km]
[4.33]Excavating, supplying and filling of local earth (including royalty) by mechanical transport up to a lead of 1 km also including ramming and watering of the earth in layers not exceeding 20 cm in trenches, plinth, sides of foundation etc. complete. [Through Rate]
[6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.14.1]Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1. 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III): 3 graded stone aggregate 20 mm nominal size) [Through Rate]
[6.34.3]Steel reinforcement for R.C.C. work, where not included in the complete rate of RCC, including straightening, cutting, bending, placing in position, binding, wastage, overlaps, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire etc. complete in all respect above plinth level Note:- Reinforcement shall be measured in length including hooks, if any, separately for different diameters as actually used in work , excluding overlaps. Wastage, overlaps, couplings, welded joints, spacer bars, chairs, stays, hangers and annealed steel wire or other methods of binding & placing shall not be measured and cost of these items shall be deemed to be included in the rates for reinforcement. 3. Cold twisted bars [Through Rate]
[7.21.2]Brick work with common burnt clay non-modular bricks of class designation 10.5 in foundation and plinth in: 2. Cement mortar 1:6 (1 cement : 6 coarse sand) [Through Rate]
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.71 MB
BOQ_579992.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid