Improvement work of T-junction in Maudaha-Biwar-Jalalpur-Kupra road (MDR-55B)
2026_CEBAN_1126413_1
534/30C-Hamirpur Circle/2025 Date 13.03.2026
Open Tender
Civil Works
Percentage
90 days
PD PWD Hamirpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,720
₹4.0 L
S.E., Hamirpur Circle PWD Hamirpur
28 Mar 2026
18 Mar 2026
24 Mar 2026
18 Mar 2026
24 Mar 2026
18 Mar 2026
20 Mar 2026
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 metres.As per MORTH Data Book & Specification clause 2.04-202(II).
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.As per MORTH Data Book & Specification clause 4.01-401
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with grader in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
Providing and applying primer coat with SS1 grade bitumen emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means.As per MORTH Data Book & Specification clause 5.01-502 A(I)
Providing and applying tack coat with bitumen VG10 using Bitumen pressure distributor at the rate of 0.25 kg per sqm on the prepared bituminous surface cleaned with air compressor.As per MORTH Data Book & Specification clause 5.02-503(II)
Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects.
Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects
Excavation in foundation in ordinary soil ( Loam clay or sand) including lift up to 1.5 meter (5ft) and lead upto 30m (100ft) and including filling,watering & ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as direction by the Engineer-in-charge upto a distance of 30m(100ft) from the foundation trenches.
Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8km (5 miles) from the side of work & including watering ,dressing etc. Rate to include cost of all materials,labour and tools & plants,etc. required for proper completion of the work.
Cement concrete with 4cm (1/2'') gauge approved stone ballast, approved coarse sand. cement in the proportion 8:4:1 including supply of all materials,labour and tools and plants etc. required for proper completion of the work.
Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5 mm), including making drainage opening wherever required complete etc. as per direction of Engineer- in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge).AS per DSR No.-16.69
Class-150 brick work in 1:6 cement and fine sand of 1.25 fineness modulus mortar in foundation and plinth including supply of all materials, labour and tools and plants etc. Required for proper completion of the work.
12mm thick plaster on brick work minimum thickness not less than 10mm with 1part of cement and 4 part of find sand of 1.25 fineness modulus.
Providing and Laying of Rubble moulded Zig Zag Interlocking Concrete Block Pavements having thickness 80 mm as per drawings and Technical Specification Clause 1504.
Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.
Sand Filling in Foundation Trenches as per Drawing & Technical Specification
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.PCC M15
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. M 25
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications.
Providing and laying of hot applied thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.
Providing and laying of hot applied thermoplastic compound 5 mm thick including reflectorising glass beads @ 250 gms per sqm area, thickness of 5 mm is exclusive of surface applied glass beads as per IRC:35 .The finished surface to be level, uniform and free from streaks and holes.
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 mad of high intensity grade sheeting vide clause 801.3, fixed cover aluminium shting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x75 mm x6 mm firmly fixed to th ground by means of properly dsignd foundation with M-15 grade cment conc. 45 cm x 45 cm x 60 cm, 60 cm below ground lvel as per approved drawing (As per Lucknow SOR) Caution Board 80 x60 mm rectangular with diffinitation plate (20 x 60 cm) T-Junction
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 mad of high intensity grade sheeting vide clause 801.3, fixed cover aluminium shting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x75 mm x6 mm firmly fixed to th ground by means of properly dsignd foundation with M-15 grade cment conc. 45 cm x 45 cm x 60 cm, 60 cm below ground lvel as per approved drawing (As per Lucknow SOR) 90 cm Equilateral tringle with diffinitation plate size (20 x 60 cm) Speed Breaker
Providing and fixing of retro-reflectorised cautionary, mandatory and informatory sign as per IRC:67 mad of high intensity grade sheeting vide clause 801.3, fixed cover aluminium shting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x75 mm x6 mm firmly fixed to th ground by means of properly dsignd foundation with M-15 grade cment conc. 45 cm x 45 cm x 60 cm, 60 cm below ground lvel as per approved drawing (As per Lucknow SOR) Traffic Sign Stop Board (90 cm high octagon) Stop Board
Constroction of Speed Table
Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5 mm), including making drainage opening wherever required complete etc. as per direction of Engineer- in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge).AS per DSR No.-16.69
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.15 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.61 MB
Tendernotice_2.pdf
PDF • 8.15 MB
Tendernotice_3.pdf
PDF • 7.04 MB
BOQ_2100586.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .