| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.7 CrAccepted-AOC FRIENDS COLONY NEAR RAJ HOTEL GAUSHALA ROAD RAMGARH CANTT | RAMGARH CANTT | RAMGARH | JHARKHAND | 829122 | ₹17.7 Cr | L1 | Accepted-AOC for being L1 |
| 2 | L2₹17.9 Cr+₹18.0 L (1.01%)Rejected-Finance | ₹17.9 Cr+₹18.0 L (1.01%) | L2 | Rejected-Finance for not being L1 |
| 3 | L3₹18.3 Cr+₹61.5 L (3.47%)Rejected-Finance | ₹18.3 Cr+₹61.5 L (3.47%) | L3 | Rejected-Finance for not being L1 |
| 4 | L4₹18.4 Cr+₹63.3 L (3.57%)Rejected-Finance | ₹18.4 Cr+₹63.3 L (3.57%) | L4 | Rejected-Finance for not being L1 |
| 5 | L5₹18.8 Cr+₹1.1 Cr (6.05%)Rejected-Finance | ₹18.8 Cr+₹1.1 Cr (6.05%) | L5 | Rejected-Finance for not being L1 |
| Sl No | Description | Qty | Unit | Shyam Infra Nirman Private Limited L9 | M/S SCS AND PCC (JV) L7 | AASHI ENGINEERING AND CONSTRUCTION PRIVATE LIMITED JV L3 | LNT Construction JV L5 | M/S R.S AGRAWAL L6 | SHRIHARI DURO SOLUTIONS JOINT VENTURE L2 | SPS TC JV L8 | M/s S.T.C.P.L. And G.D. JV L1 | SHREE RAM SSS JV L4 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1.00Item Description/ Heading | ||||||||||||
| 1.01 | Earthwork in excavation in foundation trenches in ordinary soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 m including all lifts, levelling , ramming the foundation trenches, removing roots of trees, serbs all complete as per approved design,building specification & direction of E/I. | 3,685.82 | CUM | 134 ₹4,93,899.88 | 140 ₹5,16,014.8 | 127.14 ₹4,68,615.15 | 130.41 ₹4,80,680.24 | 131.93 ₹4,86,276.06 | 123.26 ₹4,54,314.17 | 200 ₹7,37,164 | 122.97 ₹4,53,260.77 Lowest | 127.36 ₹4,69,432.66 |
| 1.02 | Extra for earthwork in hard soil as per specification and direction of E/I. (vide classification of soil item-B) | 1,110.3 | CUM | 32 ₹35,529.6 | 12 ₹13,323.6 Lowest | 12.98 ₹14,411.69 | 13.32 ₹14,792.63 | 13.48 ₹14,964.83 | 12.49 ₹13,867.65 | 300 ₹3,33,090 | 12.56 ₹13,948.81 | 13.01 ₹14,446.49 |
| 1.03 | Providing coarse clean local sand in filling in foundation trenches or in plinth including ramming and watering in layer not exceeding 150mm thick with all leads and 1.5M lifts including cost of all materials, labours, royalty and taxes all complete as per building specification and direction of Engineer Incharge (Mode of measurement compacted volume) | 926.5 | CUM | 749 ₹6,93,948.5 | 680 ₹6,30,020 | 493.71 ₹4,57,422.32 | 506.39 ₹4,69,169.49 | 512.28 ₹4,74,631.3 | 514.73 ₹4,76,897.35 | 1,200 ₹11,11,800 | 477.5 ₹4,42,406.62 Lowest | 494.54 ₹4,58,191.25 |
| 1.04 | Earth filling in foundation trenches and plinth in layers not exceeding 150mm thick well watered, rammed, fully compacted and fine dressed with earth obtained from excavation foundation trenches within a lead of 50M and lift of 1.5M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 1,504.43 | CUM | 88 ₹1,32,389.84 | 50 ₹75,221.5 | 46.29 ₹69,640.06 | 47.49 ₹71,438.64 | 48.04 ₹72,270.29 | 42.52 ₹63,968.36 Lowest | 80 ₹1,20,354.4 | 44.78 ₹67,363.56 | 46.37 ₹69,767.03 |
| 1.05 | Filling in foundation trenches and plinth in layers. Not exceeding 150 mm thick well watered, rammed fully compacted and fine dressed with earth obtained after cutting within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 800.47 | CUM | 132 ₹1,05,662.04 | 120 ₹96,056.4 | 107.93 ₹86,394.73 | 110.71 ₹88,618.37 | 112 ₹89,650.01 | 104.79 ₹83,881.25 | 200 ₹1,60,094 | 104.39 ₹83,563.3 Lowest | 108.12 ₹86,544.76 |
| 1.06 | Providing designation 75B one Brick Flat Soling joints with local sand including cost of watering taxes royalty all complete as per building specification & direction of E/I. | 1,775.93 | SQM | 394 ₹6,99,716.42 | 280 ₹4,97,260.4 | 276.65 ₹4,91,311.03 | 283.76 ₹5,03,941.56 | 287.07 ₹5,09,808.16 | 276.02 ₹4,90,192.2 | 330 ₹5,86,056.9 | 267.58 ₹4,75,195.18 Lowest | 277.12 ₹4,92,149.67 |
| 1.07 | Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration | 1,600.93 | SQM | 229 ₹3,66,612.97 | 210 ₹3,36,195.3 | 186.23 ₹2,98,141.19 | 191.02 ₹3,05,802.97 | 193.24 ₹3,09,362.96 | 182.07 ₹2,91,481.33 | 250 ₹4,00,232.5 | 180.12 ₹2,88,359.03 Lowest | 186.55 ₹2,98,647.4 |
| 1.08 | Supplying chemical emulsion in sealed containers including delivery as specified. Chlorpyriphos/ Lindane emulsifiable concentrate of 20% | 889.45 | LITRE | 267 ₹2,37,483.15 | 160 ₹1,42,312 | 146.06 ₹1,29,913.07 | 149.82 ₹1,33,255.79 | 151.56 ₹1,34,807.08 | 140.45 ₹1,24,923.25 Lowest | 174 ₹1,54,764.3 | 141.27 ₹1,25,654.47 | 146.31 ₹1,30,137.7 |
| 1.09 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size) | 87.05 | CUM | 6,379 ₹5,55,291.95 | 3,900 ₹3,39,495 | 3,372.72 ₹2,93,595.28 | 3,459.31 ₹3,01,133.22 | 3,499.58 ₹3,04,638.84 | 3,243.06 ₹2,82,308.37 Lowest | 4,800 ₹4,17,840 | 3,261.98 ₹2,83,955.65 | 3,378.37 ₹2,94,086.91 |
Tender Value
₹21.9 Cr
EMD Value
₹27.4 L
Closing Date
21 Aug 2025, 5:00 pmClosed
Office of GM(C)/Welfare and Services , CCL, Ranchi
Office of General Manager (C)/Welfare and Services , CCL,Darbhanga House, Ranchi-834029
Construction of 300 bedded Sports Hostel at Khelgaon, Hotwar, Ranchi through Tourism, Art, Culture Sports and Youth Affairs Department GoJ, under CSR of CCL (Retender).
2025_CCL_339645_1
CCL/GM(WnS)/NIT/25-26/2211-24 Dt. 15.07.2025
Open Tender
Civil Works - Buildings
Item Rate
630 days
Khelgaon
As per NIT
5 documents required · 5 mandatory
₹27.4 L
7 Feb 2026
22 Jul 2025
23 Aug 2025
22 Jul 2025
21 Aug 2025
23 Jul 2025
22 Jul 2025 - 14 Aug 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Item Description/ Heading | |||||
| 1.01 | Earthwork in excavation in foundation trenches in ordinary soil (vide classification of soil item-A) and disposal of excavated earth as obtained to a distance upto 50 m including all lifts, levelling , ramming the foundation trenches, removing roots of trees, serbs all complete as per approved design,building specification & direction of E/I. | 3,685.82 | CUM | 151.82 | ₹5,59,581.19 |
| 1.02 | Extra for earthwork in hard soil as per specification and direction of E/I. (vide classification of soil item-B) | 1,110.3 | CUM | 15.51 | ₹17,220.75 |
| 1.03 | Providing coarse clean local sand in filling in foundation trenches or in plinth including ramming and watering in layer not exceeding 150mm thick with all leads and 1.5M lifts including cost of all materials, labours, royalty and taxes all complete as per building specification and direction of Engineer Incharge (Mode of measurement compacted volume) | 926.5 | CUM | 589.51 | ₹5,46,181.02 |
| 1.04 | Earth filling in foundation trenches and plinth in layers not exceeding 150mm thick well watered, rammed, fully compacted and fine dressed with earth obtained from excavation foundation trenches within a lead of 50M and lift of 1.5M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 1,504.43 | CUM | 55.28 | ₹83,164.89 |
| 1.05 | Filling in foundation trenches and plinth in layers. Not exceeding 150 mm thick well watered, rammed fully compacted and fine dressed with earth obtained after cutting within a lead of 50 M and lift of 1.5 M all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 800.47 | CUM | 128.88 | ₹1,03,164.57 |
| 1.06 | Providing designation 75B one Brick Flat Soling joints with local sand including cost of watering taxes royalty all complete as per building specification & direction of E/I. | 1,775.93 | SQM | 330.34 | ₹5,86,660.72 |
| 1.07 | Treatment of soil under existing floors using chemical emulsion @ one litre per hole, 300 mm apart including drilling 12 mm diameter holes and plugging with cement mortar 1 :2 (1 cement : 2 Coarse sand) to match the existing floor: With Chlorpyriphos/Lindane E.C. 20% with 1% concentration | 1,600.93 | SQM | 222.37 | ₹3,55,998.8 |
| 1.08 | Supplying chemical emulsion in sealed containers including delivery as specified. Chlorpyriphos/ Lindane emulsifiable concentrate of 20% | 889.45 | LITRE | 174.41 | ₹1,55,128.97 |
| 1.09 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:3:6 (1 Cement : 3 coarse sand (zone-III): 6 graded stone aggregate 40 mm nominal size) | 87.05 | CUM | 4,027.14 | ₹3,50,562.54 |
stage.html
html • 0.07 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
BOQ_352098.xls
BOQ • 0.51 MB
176356141.pdf
Tender Documents • 3.20 MB
176356143.html
Tender Documents • 0.05 MB
178030004.pdf
Tender Documents • 1.53 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .