| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.4 CrAccepted-AOC | ₹1.4 Cr | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹1.4 Cr+₹2.1 L (1.49%)Rejected-Finance | ₹1.4 Cr+₹2.1 L (1.49%) | L2 | Rejected-Finance Highest rate |
Tender Value
₹1.4 Cr
EMD Value
₹1.4 L
Closing Date
8 May 2023, 11:00 amClosed
Project Director,DRDA, Virudhunagar
DRDA, Collectorate, Virudhunagar
Strengthening and 5 Years Routine Maintenance of Roads- 3 nos.in Package no. MGSMT-30/2022-23 at Srivilliputhur Block of Virudhunagar District under MGSMT-2022-23.
2023_RDTN_300713_6
DIPR/2018/Tender/2023
Open Tender
Civil Works - Roads
Works
180 days
Srivilliputhur Block
Two Cover System. Refer tender document
5 documents required · 5 mandatory
₹0
₹1.4 L
DRDA, Collectorate, Virudhunagar
1 Jun 2023
20 Apr 2023
8 May 2023
20 Apr 2023
8 May 2023
30 Apr 2023
30 Apr 2023
Amount
Part-1:- SH 42 Road to Nakkamangalam Road KM0.000-1.000
Part-A:- Strengthening work
Clearing & Grubbing of wild Vegetation, Grass, Bushes etc., upto 300 mm with removal of stumps of trees which cut earlier and disposal of unserviceable materials & stacking of serviceable materials to be auctioned upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm as per technical specification.,
Picking the existing bituminous road surface to the depth of 100 mm & disposed with a lift upto 3 m lead upto 1000 m as per technical specification
Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacting with power roller, watering, including all hire and fuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For embankment / sub grade
Providing laying and compacting red gravel in accordance with requirements of the specification materials shall be in one or more layers as necessary including watering, consolidating by the power roller rolling and all labour charges for soiling including hire charges for consolidation etc. complete. Km 0/0- 1/0
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack coat surface with Bitumen (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on granular surface treated with primer cleaned with hydraulic broom as per clause 503 of MORTH 5
BITUMINOUS CONCRETE USING cmp (Grade-II) Providing and laying Bituminious concrete using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 include 8% plastic waste heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectoising glass beads @ 250 gms per Sqm area , Thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC :35 . The finished surface to be level , uniform and free streaks and holes etc complete as per MORT & H specification No.803 - Road Marking - Edge line
CD Works-1:- CONSTRUCTION OF SLAB CULVERT
Earth Work excavation for foundation in all soils and to full depth as may as be directed in hard rock requiring plastering but inclusive of shorting, strutting and baling out water wherever necessary and refilling the sides of foundation with excavated earth as per SS20B
CC 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of materials and all labour charges etc., (For Foundation)
CC 1:3:6 mix using 40mm ISS HBG metal including cost and conveyance of materials and all labour charges etc., (for Below sill)
CC 1:3:6 mix using 40mm ISS HBG metal including cost and conveyance of materials and all labour charges etc., (for above sill)
Supplying and Fabricating and placing in position MS steel or Ribbed Tor Steel for all Reinforced Cement Concrete works as per the design given including cost of steel and binding wire in all floors etc, Complete complying with stanard specification.(MS rod or RTS bar will be supplied departmentally at section stores and cost will be recoverd at issue rate). the binding wire shall supplied by the contactor.
Supplying and erecting centering are strutting including neceassary supports for place surface for RCCcolumns fottings and pedestal beems crtitical pears erc., using mild steel angles of sizes 90x60x10cm gauge stiffness welded mild steel angles of sizes
Sub structure
Super structure
PCC 1:2 :4 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement and including all labour charges etc., complete as directed by the Engineer (Bed block)
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works including cost of Rein forcement and fabricating charges, centering and shuttering but including curing and shall be finished smooth with cement mortar 1:3, 12mm thick. and with kraft paper without claiming extra as directed by the departmental officers complete complying with standard specifications.
Back filling with Good gritty gravel behind the Abutment & inbetween the wings including all labour charges etc., complete
Provision for Expansion joint inbetween the dirt wall & Deck in Abutment and inbetween deck in Pier in standard specification
Providing and laying Kraft paper barring between deck slab and bed block to the full width of seating
Providing Hectametre stone of size
Providing Kilometer stone of size
Providing Reflector
Providing Name board cum Citizen Board
Providing sign board
Providing speed breaker
Providing 60 cm equilateral triangle cautionary board (to be provide at places like schools, side road left & right X junction etc.,)
Providing Road marker/Reflector
Maintenance Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part-2:- Malli-Pandithanpatti road KM0.000-1.276
Part-A:- Strengthening work
Clearing & Grubbing of wild Vegetation, Grass, Bushes etc., upto 300 mm with removal of stumps of trees which cut earlier and disposal of unserviceable materials & stacking of serviceable materials to be auctioned upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm as per technical specification.,
Picking the existing bituminous road surface to the depth of 100 mm & disposed with a lift upto 3 m lead upto 1000 m as per technical specification
Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacting with power roller, watering, including all hire and fuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For embankment / sub grade
Providing laying and compacting red gravel in accordance with requirements of the specification materials shall be in one or more layers as necessary including watering, consolidating by the power roller rolling and all labour charges for soiling including hire charges for consolidation etc. complete. Km 0/0- 1/0
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack coat surface with Bitumen (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on granular surface treated with primer cleaned with hydraulic broom as per clause 503 of MORTH 5
BITUMINOUS CONCRETE USING cmp (Grade-II) Providing and laying Bituminious concrete using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 include 8% plastic waste heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectoising glass beads @ 250 gms per Sqm area , Thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC :35 . The finished surface to be level , uniform and free streaks and holes etc complete as per MORT & H specification No.803 - Road Marking - Edge line
Providing Hectametre stone of size
Providing Kilometer stone of size
Providing Nameboard cum Citizen Board
Providing sign board
Providing speed breaker
Providing 60 cm equilateral triangle cautionary board (to be provide at places like schools, side road left & right X junction etc.,)
Providing Reflector
Maintenance Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part-3:- NH208 Road To Pannai road KM 0.000-1.428
Part-A:- Strengthening work
Clearing & Grubbing of wild Vegetation, Grass, Bushes etc., upto 300 mm with removal of stumps of trees which cut earlier and disposal of unserviceable materials & stacking of serviceable materials to be auctioned upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm as per technical specification.,
Picking the existing bituminous road surface to the depth of 100 mm & disposed with a lift upto 3 m lead upto 1000 m as per technical specification
Earthwork excavation in all classes of soils except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B including cost of all labour charges, materials, tools, equipments and all incidental charges, including compacting with power roller, watering, including all hire and fuel charges for all tools and plants, removal of other deleterious matter and obstructions, trimming of bottom of excavation back filling, clearing up the site and disposal of all surplus materials etc., complete as per standard specification. For embankment / sub grade
Providing laying and compacting red gravel in accordance with requirements of the specification materials shall be in one or more layers as necessary including watering, consolidating by the power roller rolling and all labour charges for soiling including hire charges for consolidation etc. complete. Km 0/0- 1/0
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying Prime Coat over WBM/ WMM surface using 7 Kg of Emulsion Bitumen (SS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack coat surface with Bitumen (RS1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on granular surface treated with primer cleaned with hydraulic broom as per clause 503 of MORTH 5
BITUMINOUS CONCRETE USING cmp (Grade-II) Providing and laying Bituminious concrete using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 include 8% plastic waste heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectoising glass beads @ 250 gms per Sqm area , Thickness of 2.5 mm is exclusive of surface applied glass beads as per IRC :35 . The finished surface to be level , uniform and free streaks and holes etc complete as per MORT & H specification No.803 - Road Marking - Edge line
Providing Hectametre stone of size
Providing Kilometer stone of size
Providing Nameboard cum Citizen Board
Providing sign board
Providing 60 cm equilateral triangle cautionary board (to be provide at places like schools, side road left & right X junction etc.,)
Providing Reflector
Maintenance Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to the above Government Contract Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
V SAKTHIVEL
stage.html
html • 0.04 MB
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .