| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.9 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹22.6 L+₹4.3 L (23.8%)Rejected-Finance | L2 | Rejected-Finance Other than lowest bidder | |
| 3 | L3₹22.8 L+₹4.6 L (25.0%)Rejected-Finance | L3 | Rejected-Finance Other than lowest bidder | |
| 4 | L4₹23.1 L+₹4.8 L (26.4%)Rejected-Finance | L4 | Rejected-Finance Other than lowest bidder | |
| 5 | L5₹30.4 L+₹12.2 L (66.7%)Rejected-Finance MAHAMUNI PARA BOGAFA P S P O SANTIRBAZAR SOUTH TRIPURA | GOMATI | TRIPURA | 799125 | L5 | Rejected-Finance Other than lowest bidder |
Tender Value
₹34.6 L
EMD Value
₹69,200
Closing Date
22 Apr 2021, 6:00 pmClosed
GE (N) Bikaner
GE (N) Bikaner Mil Stn Bikaner
OUTSOURCING FOR OPERATION OF EXTERNAL WATER SUPPLY AND ELECTRIC SUPPLY INSTALLATION AT VARIOUS LOCATION AND OTHER CONNECTED ITEMS AT EAST,SOUTH AND DBS CAMP AT MFFR UNDER GE (N) BIKANER
2021_MES_428614_2
CA NO GE (N) BKN-Token/74 /2020-21
Open Tender
Miscellaneous Works
Item Rate
330 days
GE (N) Bikaner
Class D Category d (v)
9 documents required · 9 mandatory
₹500
GE (N) Bikaner
₹69,200
Yes
7 Sept 2021
8 Apr 2021
24 Apr 2021
8 Apr 2021
22 Apr 2021
9 Apr 2021
Amount
Note Applicable for srl item No. 1 to 06 : The rate quoted shall not be less than minimum wages as notified by Government/Local body (For 'C'Area ) whichever is higher . In Case the rates quoted are less than the minimum wages as notified by the Government of India/State Government/Local body whichever is higher , his tender will be treated as NON BONAFIDE and willl not be considered for acceptance. In such case, the lowest tender shall be determind by the lowest amount amongst valid/bonofied bids only). Outsourcing of services for South Camp water supply installation with DG set including all operating activities for smooth functioning of installation, mixing of alum in raw water tank and pumping the raw water in slow sand filter tank and chlorination of clear water in collection/clear water storage tank and pumping the same treated water to RCC overhead tank and distribution the drinking water to all camp & Adm area and supply to lorry filling points as and when required by operating sluice valve/gate valve by providing one trade man (FGM) (Semiskilled ) in each shift incl Sunday and holiday in two shift per day (each shift of 08 hrs duration etc complete all as specified and directed by Engineer-in-Charge. Note :- Transport/Vehicle & manpower for loading/unloading of FOL will be arranged by the contractor for collection of Fuel/FOL for DG set from KSP North Camp (approx. 65 Kms).The cost of the same shall be deemed to be included the unit rate quoted Note Applicable for srl item No. 1 to 06(serial item no - one to six): - a) All the electric equipment/panels installed in pump house/External electric panels will be maintained properly by contractor. b) Timing and location of deployed staff will be decided by Engr-in-Charge. c) General cleaning of installations area to be upkeep by the staff employed by contractor & removing all vegetation nearby installations & cutting grass & vegetation time to time. d) Staff employed by the contractor at installation having the general knowledge of operating generator, pumping motor, electric panels & all necessary operation required to supply water to all camp area i.e. South, East,, DBS, RD-535 & RD-160. e) Cost of log sheet and relevant document to be maintain by contractor which is included in the item rate quoted as per requirement for operating pump house installations/electric installation included in lump sum quoted rate. f) Necessary cleaning of slow sand filter tank and excavation work required to filter media at every operation included in the quoted rate. g) Cost of petty items required for smooth functioning of installation such as grease for moving parts of pumps, glands, cotton waste, brooms, testing kits for chlorination testing to be provide by the contractor on each installation. (Note for Srl Item No 01 here in before above contd...(h) Contractor provide necessary conveyance for collection of P.O.L. for generator from North Camp to all installation as and when required at installation.(j) Contractor provide all required T&P at installation for operation/outsourcing and other safety equipments, ladder, over combination, grass, vegetation cutter etc. (k) If any loss/damage to govt property is caused by contractor due to operator's fault during operation, the same shall be make good by contractor at the same cost quoted by him for outsourcing. (l) Contractor must submit following documents within 15 days from commencement date and if any Elect/FGM/helper is found absent from duty found Rs. 1000/- day penalty will be deducted from contractor dues: - (aa) Application for issue the identity card/security pass.(ab) Cost of T&P/vehicle reqd for outsourcing & repair work such as fuse wire, insulation tape, working tools to be borne by the contractor & provided by contractor at each installation for daily attendance bio metric is to be installed by contractor for which the cost is to be included in the item rate quoted.(ac) The cost of material will be measured and paid separately (ad) Tradesmen/Helpers will be made Payment through e-payment/cheque and the evidence/proof of the same monthly contractor will provide. (ae) motor will be under warranty for six month after rewinding of motor and contractor will reponsible for burnt winding due to operator fault like two phase opreation or due to water during this period and rewind motor his own expenses
Outsourcing of services for DBS water supply installation with DG set including all operating activities for smooth functioning of installation, mixing of alum in raw water tank and pumping the raw water in slow sand filter tank and chlorination of clear water in collection/clear water storage tank and pumping the same treated water to RCC overhead tank and distribution the drinking water to all camp area and supply to lorry filling points as and when required by operating sluice valve/gate valve by providing one trade man (FGM) (Semiskilled ) each shift incl Sunday and holiday in two shift per day (each shift of 08 hrs duration) complete all as specified and directed by Engineer-in-Charge. Note :- Transport/Vehicle & manpower for loading/unloading of FOL will be arranged by the contractor for collection of Fuel/FOL for DG set from KSP North Camp (approx. 82 Kms).The cost of the same shall be deemed to be included the unit rate quoted
Outsourcing of services for RAW water pump house installed at RD 535 TOP operating the pump to supply raw water to South Camp and DBS water supply installation including filling the raw water tank from IG canal head by providing one trade man (FGM) (Semiskilled) in each shift including Sunday and holiday in two shift per day (each shift of 08 hrs duration) etc complete all as specified and as directed by Engineer-in-Charge
Outsourcing of services for East Camp Phase-II water supply installation with DG set including all operating activities for smooth functioning of installation, mixing of alum in raw water tank and pumping the raw water in slow sand filter tank and chlorination of clear water in collection/clear water storage tank and pumping the same treated water to RCC overhead tank and distribution the drinking water to all camp & Adm area and supply to lorry filling points as and when required by operating sluice valve/gate valve by one trade man (FGM) (Semiskilled ) for a shift incl Sunday and holiday in two shift per day (each shift of 08 hrs duration) complete all as specified and directed by Engineer-in-Charge. Note :- Transport/Vehicle & manpower for loading/unloading of FOL will be arranged by the contractor for collection of Fuel/FOL for DG set from KSP North Camp (approx. 37 Kms).The cost of the same shall be deemed to be included the unit rate quoted
Outsourcing of services for RAW water pump house installed at RD 160 ( East Camp phase-I ) operating the pump to supply raw water to East Camp PH II water supply installation which are 15KM away from pump house including filling the raw water tank from IG canal head by providing one trade men (FGM) (Semiskilled ) in one shift (day shift) & one helper (Unskilled ) will operate the water minor canal head & other general duties as required at site in another shift (evening shift) including Sunday and holiday in each shift per day (each shift of 08 hrs duration) etc complete all as specified and as directed by Engineer-in-Charge
Outsourcing of services for elect supply including substation 11 KV LT side and all day to day repairs required such as security light repair, rectification of faults in LT/HT overhead lines, internal elect supply repairs complete in New Camp (Cul-1,2 & 3) including Adm Camp in South Camp and all other camps i.e. Adm Area with CUL-1 to 3under AGE MFFR by providing one trade man electrician (skilled ) including Sunday and holiday in one shift/day complete all as specified and directed by Engineer-in-Charge.
Supply only bleaching powder in 25 Kg bags ISI marked to the extent required for treatment of water complete all as specified and as directed by Engineer-in-Charge. Make: - Siel/shri Ram etc.
Supply only Alum grade-4 of best quality in 20 KG brick to the extent required in treatment of water complete all as specified and as directed by Engineer-in-Charge. Make- Marudhar etc.
Note for Sl item No. 9 to 50 :- The contractor must attend the complaint witin 12 Hours after geting complaint from MES and resolve the problem within 48 hours. In case contractor failed to rectify the defect within the time limit , a penalty Rs. 1000.00 per day will be imposed as penaulty for the delayed period.) Dismantling of existing defective induction motor of the following size and make from the foundation, disconnecting the electric connecting coupling pulley and taking out to work shop cutting down and removing existing burnt out copper windings, cleaning of slots and rewinding with solid copper conductor (winding wire) complete including varnishing, drying ovening overhauling greeasing and fixing in the same position making necessary electric connection and testing on induction motor complete all as specified and as directed by Engineer-in-Charge. 20 HP capacity, 03 phase, 415 volt 50 HZ any make/type
Ditto all as per item no 9 but capacity of 10/12.5 HP capacity, 03 phase, 415 volt 50 HZ any make/type
Ditto all as per item no 9 but capacity of 5 HP capacity, 03 phase, 415 volt 50 HZ any make/type
Ditto all as per item no 9 but capacity of 3 HP capacity, 03 phase, 415 volt 50 HZ any make/type
Ditto all as per item no 9 but capacity of 1 HP capacity, 01 phase, 240 volt 50 HZ any make/type
Dismantling from foundation frame by disconnecting suction/delivery lines and coupling opening & transport to workshop & re-assembling after repair/replacement of defective parts of centrifugal pump set of capacity 20 HP Make :- any make and replacement of worn out spare parts as mentioned under resective item No-15 here in after.
Supply only the following spare parts for cetrifugal pump of 20 HP capacity make :- kirlosker/CG /Kalsi Inter stage ring
Gland cap CI with Nut bolt
CI Impeller with locking screw & Nut
Shaft sleeve bronze
Set of gasket
Bearing with housing DE
Dismantling from foundation frame by disconnecting suction/delivery lines and coupling opening & transport to workshop & re-assembling after repair/replacement of defective parts of centrifugal pump set of capacity 15/ 12.5 HP Make :- any make and replacement of worn out spare parts as mentioned under resective item No-21 here in after.
Supply and fixed in replacement following items suitable for 12.5/15 HP motor pumping set CI Impeller with locking screw & Nut
Ditto All as per item no 22 but for Ball bearing for motor (SKF/NBC)
Ditto All as per item no 22 but for Ball bearing as per existing for Pump (SKF/NBC)
Dismantling from foundation frame by disconnecting suction/delivery lines and coupling opening & transport to workshop & re-assembling after repair/replacement of defective parts of centrifugal pump set of capacity 7.5/ 10HP Make :- any make and replacement of worn out spare parts as mentioned under resective item No-25 here in after.
Supply & Fix in replacement of the following parts of mono-block capacity 7.5 to 10 HP, Make-Kirloskar, Discharge 540 LPM at head 2980 RPM CI Impeller with locking screw & Nut
Ditto ll as per item no 26 but for Ball bearing as per existing for pump/motor
Supply & fix in replacement of the following parts of mono-block capacity 3/5 HP, Make-Kirloskar, Discharge 540 LRM at 16 head 2840 RPM CI Impeller with locking screw & Nut
Ditto ll as per item no 28 but for Ball bearing as per existing for pump/motor
Supply and fixing in replacement of cast iron sluice valve 80 mm, heavy duty class PN 1:6 ISI marked (IS-14846-2000), long body, both ends flanged, complete with high tensile stainless steel spindle, cast iron hand operated wheel and cap top, nuts, bolts, washers including 3mm thick rubber gasket joints, suitable for 80 mm bore GI/PVC pipe any type any size and also including testing and commissioning complete all as specified and as directed. Make - Leader/Sant/Kirlosker
Ditto all as per serial item No. 30 here in before but suitable for 100mm bore.Make - Leader/Sant/Kirlosker
Ditto all as per serial item No. 30 here in before but suitable for 150mm bore.Make - Leader/Sant/Kirlosker
Supply and fixing in replacement of existing flexible hose pipe (as per sample) of 80 mm dia suiatable for lorry filling point all as specified & directed by the Engineer-in-Charge.
Supply and Fixing in replacement of Reflex Valve/NRV/Dual plate check valve, PN 1.6 rating of size 80 mm dia with all necessary accessories and testing complete all as specified & directed. Make - Leader/Sant/Kirlosker
Supply and Fixing in repair foot valve of any type & in any condition CI Foot Valve size 80 mm dia conforming to IS suitable for 80mm bore pipe any type i.e thread/flanged type complete all as required at site. Make - Leader/Sant/Kirlosker
S&F in replacement of cast iron ditechable joints suitable for 200mm dia DI/GI pipe line including clamps, nuts, bolts, washers,sockets,elbow etc and all necessary arrangement and testing complete all as required at site and as directed.(Note:- Excavation shall be measured and paid for separately)
All as per item No 36 above but size 150mm suitable for 150mm dia GI/DI pipe line
All as per item No 36 above but size 100mm suitable for 100mm dia GI/DI pipe line
S&F in replacement of PVC ditechable joints suitable for 200mm dia HDPE/PVC pipe line including clamps, nuts, bolts, washers,sockets,elbow etc and all necessary arrangement and testing complete all as required at site and as directed.(Note:- Excavation shall be measured and paid for separately)
All as per item No 39 above but size 150/160mm suitable for 160/150mm dia HDPE/PVC pipe line
All as per item No 39 above but size 100mm suitable for 100mm dia HDPE/PVC pipe line
Suuply and Fixing in replacement of automatic starter typ any size suitable for 20HP pump set 415 volt, 50 Hz, 3 phase, by using lugs/thimbles complete all as specified and as directed by Engineer-in-Charge. Make :- L&T/Siemens/BCH/ABB/C&S
Suuply and Fixing in replacement of automatic starter any size suitable for 15 HP pump set 415 volt, 50 Hz, 3 phase, by using lugs/thimbles complete all as specified and as directed by Engineer-in-Charge. Make :- L&T/Siemens/BCH/ABB/C&S
Suuply and Fixing in replacement of automatic starter any size suitable for 10 HP pump set 415 volt, 50 Hz, 3 phase, by using lugs/thimbles complete all as specified and as directed by Engineer-in-Charge. Make :- L&T/Siemens/BCH/ABB/C&S
Suuply and Fixing in replacement of automatic starter typpe any size suitable for 7.5 HP pump set 415 volt, 50 Hz, 3 phase, by using lugs/thimbles complete all as specified and as directed by Engineer-in-Charge. Make :- L&T/Siemens/BCH/ABB/C&S
Suuply and Fixing in replacement of automatic DOL starter Oil Immersed type any size suitable for upto 5 HP pump set 415 volt, 50 Hz, 3 phase, by using lugs/thimbles complete all as specified and as directed by Engineer-in-Charge. Make :- L&T/Siemens/BCH/ABB/C&S
Suuply and Fixing in replacement of automatic DOL starter Oil Immersed type any size suitable for upto 3 HP pump set 415 volt, 50 Hz, 3 phase, by using lugs/thimbles complete all as specified and as directed by Engineer-in-Charge. Make :- L&T/Siemens/BCH/ABB/C&S
S&F in replacement of four pole offload changeover switch 200 Amps, 415 Volts with sheet steel enclosure including disconnecting existing cable connection and reconnecting after fixing the same as directed by Engineer-in-Charge complete all as specified and as directed by Engineer-in-Charge.Make :- L&T/Siemens/Havells/C&S
S&F in replacement of four pole offload changeover switch 100 Amps, 415 Volts with sheet steel enclosure including disconnecting existing cable connection and reconnecting after fixing the same as directed by Engineer-in-Charge complete all as specified and as directed by Engineer-in-Charge.Make :- L&T/Siemens/Havells/C&S
S&F in replacement of four pole offload changeover switch 63mps, 415 Volts with sheet steel enclosure including disconnecting existing cable connection and reconnecting after fixing the same as directed by Engineer-in-Charge complete all as specified and as directed by Engineer-in-Charge.Make :- L&T/Siemens/Havells/C&S
MAJOR REFREGERATION AND ELECTRICALS
singh enterprises
Gupta Suppliers
BHARAT NIRMAN INFRASTRUCTURE COMPANY
RUHI ASSOCIATES
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .