| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹90,332.15Accepted-AOC | ₹90,332.15 | L1 | Accepted-AOC Accept |
| 2 | L2₹93,849.21Rejected-AOC | ₹93,849.21 | L2 | Rejected-AOC Accept |
| 3 | L3₹1.0 LRejected-AOC KAVANUR | VELLORE | TAMIL NADU | ₹1.0 L | L3 | Rejected-AOC Accept |
| Sl No | Description | Qty | Unit | S UDAYAKUMAR L2 | D.Meganathan L3 | BEEMJI ENTERPRISE L1 |
|---|---|---|---|---|---|---|
| 1.00Vellore District Construction of drainage and deck slab opposite ponniyamman koil in Pasumathur Panchayat K.V. KUPPAM Block General Fund 2025-2026 Package no 89 | ||||||
| 2.00 | Earthwork excavation and depositing on bank with initial lead and lift in all clauses of soil including cost of labour etc complete SS20B | 8.42 | cu.m | 250.59 ₹2,109.97 | 267.89 ₹2,255.63 | 240 ₹2,020.80 |
| 3.00 | P.C.C 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all etc.. Complete | 1.87 | cu.m | 5,334.83 ₹9,976.13 | 5,703.21 ₹10,665 | 5,000 ₹9,350 |
| 4.00 | Supplying and erecting centering for all PCC items including cost and conveyance of all etc.. Complete | 46.68 | sq.m | 520.13 ₹24,279.67 | 556.04 ₹25,955.95 | 480 ₹22,406.40 |
| 5.00 | Cement Concrete 1:3:6 mix using 20mm metal including cost and conveyanceof all materials to work site and all labour charges etc. | 4.69 | cu.m | 6,050.21 ₹28,375.48 | 6,467.99 ₹30,334.87 | 6,000 ₹28,140 |
| 6.00 | Plastering in cm 1:4, 20mm thick including cost and conveyance of all etc.. Complete | 7.65 | sq.m | 553.1 ₹4,231.22 | 591.29 ₹4,523.37 | 500 ₹3,825 |
| 7.00 | Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works including cost and conveyanceof all materials to work site and all labour charges etc. | 0.79 | cum | 8,879.84 ₹7,015.07 | 9,493.02 ₹7,499.49 | 9,000 ₹7,110 |
| 8.00 | Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification. | 35.17 | kg | 87.31 ₹3,070.69 | 93.33 ₹3,282.42 | 91 ₹3,200.47 |
| 9.00 | Letering and Painting Name board | 1 | No.s | 475 ₹475 | 507.8 ₹507.80 | 500 ₹500 |
| 10.00 | GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column "BB" for all works in this package} | 1 | Each | 14,315.98 ₹14,315.98 | 15,304.42 ₹15,304.42 | 13,779.48 ₹13,779.48 |
Tender Value
Refer Docs
EMD Value
₹2,000
Closing Date
5 Feb 2026, 3:00 pmClosed
The Block Development Office KV Kuppam
The Block Development Office KV Kuppam
Vellore District Construction of drainage and deck slab opposite ponniyamman koil in Pasumathur Panchayat K.V. KUPPAM Block General Fund 2025-2026 Package no 89
2026_RDTN_647241_1
A3/3236/2025 KVKM JAN 02-26
Open Tender
Civil Works
180 days
The Block Development Office KV Kuppam
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹2,000
7 Apr 2026
26 Jan 2026
5 Feb 2026
26 Jan 2026
5 Feb 2026
26 Jan 2026
Vellore District Construction of drainage and deck slab opposite ponniyamman koil in Pasumathur Panchayat K.V. KUPPAM Block General Fund 2025-2026 Package no 89
Earthwork excavation and depositing on bank with initial lead and lift in all clauses of soil including cost of labour etc complete SS20B
P.C.C 1:4:8 mix using 40mm ISS HBG metal including cost and conveyance of all etc.. Complete
Supplying and erecting centering for all PCC items including cost and conveyance of all etc.. Complete
Cement Concrete 1:3:6 mix using 20mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Plastering in cm 1:4, 20mm thick including cost and conveyance of all etc.. Complete
Cement Concrete 1:1-1/2:3 (One Cement, One and a half crushed stone M.Sand and Three hard broken stone jelly) using 20 mm gauge hard broken granite stone jelly for all RCC items of works including cost and conveyanceof all materials to work site and all labour charges etc.
Supplying, fabricating and placing in position Mild Steel / Ribbed Tor Steel grills for all RCC works as per design given including cost of steel and G.I. binding wire in all floors etc. complete complying with standard specification.
Letering and Painting Name board
GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_775901.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.72 MB
Tendernotice_2.pdf
PDF • 0.37 MB
BOQ_775901.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid