| 1.00Name of Work: Construction of Community Hall Building at Kettiammalpuram Village in Vellur in Vellur Panchayat in Srivaikundam Panchayat Union | |||||
| 2.00 | Earthwork excavation and depositing on bank with initial lead and lift in hard gravelly soil for foundation etc. complete | 110.5 | cum | 276.97 ₹30,605.19 | 263.65 ₹29,133.33 Lowest |
| 3.00 | Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyance of all materials to site and labour charges etc. complete | 26.3 | cum | 5,661.18 ₹1,48,889.03 | 5,388.9 ₹1,41,728.07 Lowest |
| 4.00 | Brick work in Cement 1:5 mix using country Bricks of size 23x11.5x7.5cms for the following including mixing mortar and all other labour charges etc. complete. | 72.07 | cum | 6,412.1 ₹4,62,120.05 | 6,103.71 ₹4,39,894.38 Lowest |
| 5.00 | Filling with Collected Gravel including all labour charges etc. | 89.52 | cum | 416.36 ₹37,272.55 | 396.33 ₹35,479.46 Lowest |
| 6.00 | Supplying and erecting shttering including necessary support for plane surface in foundation Basement and Roof labs strutting upto 3.29M height for plane surfaces for floors for RCC column footings columns plinth beam and connected with foundations (Below Ground level) | 181.63 | cum | 574.88 ₹1,04,415.45 | 547.23 ₹99,393.38 Lowest |
| 7.00 | Supplying and erecting shttering including necessary support for plane surface in foundation Basement and Roof labs strutting upto 3.29M height for plane surfaces for floors for RCC column footings columns plinth beam and connected with foundations (Above Ground level) | 401.06 | cum | 1,149.75 ₹4,61,118.74 | 1,094.45 ₹4,38,940.12 Lowest |
| 8.00 | Supplying, fabricating and placing in position mild steel or ribbed to steel and all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc. complete. | 8.5 | MT | 96,490.07 ₹8,20,165.6 | 91,849.35 ₹7,80,719.48 Lowest |
| 9.00 | RCC 1:1.5:3 using 20mm HBG metal including cost and conveyance of materials and labour charges etc. complete | 78.93 | cum | 9,579.35 ₹7,56,098.1 | 9,118.63 ₹7,19,733.47 Lowest |
| 10.00 | Weathering course with best quality broken brick jelly of size 20mm uniform gauge in pure slaked lime (no sand to be listed) over the RCC roof slab in the proposition being brickjelly to lime 32:12:1/2 by volume and laid over into a single layer and cons | 11.2 | cum | 4,254.94 ₹47,655.33 | 4,050.29 ₹45,363.25 Lowest |
Tender Value
₹53.8 L
EMD Value
₹54,000
Closing Date
10 Feb 2026, 3:00 pmClosed
Joint Director/Project Director
DRDA Thoothukudi
TN Tut 06 2026 27 Construction of Community Hall at Kettiyammalpuram Village in Vellur Panchayat in Srivaikundam Union in Thoothukudi District PKG 06
2026_RDTN_650536_6
RDTUT/370/2025/A13 dated 31.01.26
Open Tender
Civil Works - Buildings
Item Rate
360 days
DRDA THOOTHUKUDI
As per Tender Document
4 documents required · 4 mandatory
₹0
₹54,000
05.02.2026
13 May 2026
4 Feb 2026
10 Feb 2026
4 Feb 2026
10 Feb 2026
4 Feb 2026
5 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Name of Work: Construction of Community Hall Building at Kettiammalpuram Village in Vellur in Vellur Panchayat in Srivaikundam Panchayat Union | - | - | - | - |
| 2 | Earthwork excavation and depositing on bank with initial lead and lift in hard gravelly soil for foundation etc. complete | 110.5 | cum | - | - |
| 3 | Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyance of all materials to site and labour charges etc. complete | 26.3 | cum | - | - |
| 4 | Brick work in Cement 1:5 mix using country Bricks of size 23x11.5x7.5cms for the following including mixing mortar and all other labour charges etc. complete. | 72.07 | cum | - | - |
| 5 | Filling with Collected Gravel including all labour charges etc. | 89.52 | cum | - | - |
| 6 | Supplying and erecting shttering including necessary support for plane surface in foundation Basement and Roof labs strutting upto 3.29M height for plane surfaces for floors for RCC column footings columns plinth beam and connected with foundations (Below Ground level) | 181.63 | cum | - | - |
| 7 | Supplying and erecting shttering including necessary support for plane surface in foundation Basement and Roof labs strutting upto 3.29M height for plane surfaces for floors for RCC column footings columns plinth beam and connected with foundations (Above Ground level) | 401.06 | cum | - | - |
| 8 | Supplying, fabricating and placing in position mild steel or ribbed to steel and all reinforced cement concrete works as per the design given including cost of steel and binding wire in all floors etc. complete. | 8.5 | MT | - | - |
| 9 | RCC 1:1.5:3 using 20mm HBG metal including cost and conveyance of materials and labour charges etc. complete | 78.93 | cum | - | - |
| 10 | Weathering course with best quality broken brick jelly of size 20mm uniform gauge in pure slaked lime (no sand to be listed) over the RCC roof slab in the proposition being brickjelly to lime 32:12:1/2 by volume and laid over into a single layer and cons | 11.2 | cum | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.29 MB
TechnicalBid06.pdf
Tender Documents • 0.81 MB
BOQ_780356.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .