S.E.PMGSY Circle PWD Prayagraj
Office of the S.E.PMGSY Circle PWD Prayagraj
Construction work of residential and non-residential building of 02 unit fire station in Gram Bani Block Bahadurpur of Phoolpur Assembly Constituency of Prayagraj district. including electrical work
2026_CEPMP_1137497_2
516/Nivida(Bhavan)pmgsy/26 Date- 07.04.2026
Open Tender
Civil Works - Buildings
365 days
Gram Bani Block Bahadurpur Phoolpur Prayagraj
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,714
₹19 L
Office of the S.E.PMGSY Circle PWD Prayagraj
16 May 2026
16 Apr 2026
29 Apr 2026
16 Apr 2026
29 Apr 2026
16 Apr 2026
23 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation in ordinary soil (loam clay or sand) including lift upto 1.50 meter and lead upto 30 meter and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of sur-plus earth as directed by the Engineer incharge up to a distance of 30 meters from the foundation trenches. 0.00 LVL. TO 1.50 MTR.as per DSR-2023_ 2.8.1 | 0.18 | CUM | - | - |
| 2 | Excavation in foundation in ordinary soil (loam clay or sand) including lift upto 1.50 meter and lead upto 30 meter and including filling, watering and ramming of excavated earth into the trenches or into the space between the building and sides of foundation trenches or into the plinth and removal and disposal of sur-plus earth as directed by the Engineer incharge up to a distance of 30 meters from the foundation trenches. 1.50 LVL. TO 3.00 MTR.as per DSR-2023_ 2.8.1+2.26.1 | - | CUM | - | - |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m. Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.as per DSR-2023_ 2.25 | - | CUM | - | - |
| 4 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 cement : 4 coarse sand (zone-iii) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources) Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:4:8 (1 cement : 4 coarse sand (zone-iii) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)as per DSR-2023_ 4.1.8 | 0.77 | CUM | - | - |
| 5 | Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 kms. from the site of work and including watering, dressing etc rate to include cost of all materials labour T & P etc required for proper completion of work. Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 kms. from the site of work and including watering, dressing etc rate to include cost of all materials labour T & P etc required for proper completion of work.as per DSR-2023_ 2.27 | 1 | CUM | - | - |
| 6 | Providing and injecting chemical emulsion for pre constructional antitermite treatment and creating a chemical barrier under and alround the column pits wall trenches basement excavation top surface if plinth filling junction of wall and floor, along the the external perimeter of binding expansion joints, surrounding of pipes and conduits etc, complete.(plinth area of the building at ground floor only shall be measured as per I.S.6313 (PartII 1981) Alderine emulsifiable concentrate or any other approved material such as Heptrachlor or Chlordane will be used. The rate of application of chemical emulsion shall be as follows : (1) Treatment for masonary & foundation 5 liters per sqm. (2) Back fill in immediate contact with foundation 7.5 liters/sqm (3) Treatment of top surface of plinth filling 5 liters/sqm (4) Treatment junction of wall and the floor 7.5 liters /sqm (5) Treatment of soil along external perimeter of building 7.5 liters/sqm (6) Treatment of soil under apron along external perimter 5 liters/sqm. (As per manufacturer's standard dilution)as per DSR-2023_ 2.35.3.1 | 0.24 | SQM | - | - |
| 7 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement.Concrete of M25 grade with minimum cement content of 330 kg /cum R.C.C. work Upto plinth Lvl. (M-25) R.C.C. Tie Beamas per DSR-2023_ 5.33.1.1 | - | CUM | - | - |
| 8 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement.Concrete of M25 grade with minimum cement content of 330 kg /cum R.C.C. work Upto plinth Lvl. (M-25) R.C.C. Footing or Raftas per DSR-2023_ 5.33.1.1 | 1 | CUM | - | - |
| 9 | Providing and laying in position ready mixed or site batched design mix cement concrete for reinforced cement concrete work; using coarse aggregate and fine aggregate derived from natural sources, Portland Pozzolana / Ordinary Portland /Portland Slag cement, admixtures in recommended proportions as per IS: 9103 to accelerate / retard setting of concrete, to improve durability and workability without impairing strength; including pumping of concrete to site of laying, curing, carriage for all leads; but excluding the cost of centering, shuttering, finishing and reinforcement as per direction of the engineer-in-charge, for the following grades of concrete.: Note: Extra cement up to 10% of the minimum specified cement content in design mix shall be payable separately. In case the cement content in design mix is more than 110% of the specified minimum cement content, the contractor shall have discretion to either re-design the mix or bear the cost of extra cement.Concrete of M25 grade with minimum cement content of 330 kg /cum R.C.C. work Upto plinth Lvl. (M-25) R.C.C. Columnas per DSR-2023_ 5.33.1.1 | 1 | CUM | - | - |
| 10 | M-150 brick work in one cement & six coarse sand 2.25 F.M. mortar in foundation and plinth including supply of all materials labour, tools and plants etc. required for proper completion of the work. as per DSR-2023_ 6.1.2 | 0.78 | CUM | - | - |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.49 MB
BOQ_2124151.xls
BOQ • 0.85 MB
CBD.pdf
Tender Documents • 2.84 MB
Download all tender documents and submit your bid