| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.2 CrAccepted-AOC | ₹1.2 Cr | L1 | Accepted-AOC L1 Bidder |
| 2 | L2₹1.2 CrRejected-AOC | ₹1.2 Cr | L2 | Rejected-AOC L2 Bidder |
| Sl No | Description | Qty | Unit | M.K.Construction L1 | N.S CONSTRUCTION L2 |
|---|---|---|---|---|---|
| 1.00Strengthening of the Road at km1/4 Madhanur Ulli Road to Koppampatti Road in Ulli Panchayat of Gudiyatham Block (R-180) (km 0/0-1/680) | |||||
| 2.00 | Clearing the scrub jungles including cutting the scrubs and removing away from site etc complete | 1,896 | Sqm | 6.36 ₹12,058.56 | 6.49 ₹12,305.04 |
| 3.00 | Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m | 1,882.5 | Sqm | 23.36 ₹43,975.20 | 23.83 ₹44,859.98 |
| 4.00 | Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 A | 453.6 | Cum | 140.44 ₹63,703.58 | 143.26 ₹64,982.74 |
| 5.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 125mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 855.28 | Cum | 2,383.65 ₹20.4 L | 2,431.57 ₹20.8 L |
| 6.00 | Providing and laying of Prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 5,701.88 | Cum | 86.61 ₹4.9 L | 88.35 ₹5.0 L |
| 7.00 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 5,701.88 | Sqm | 20.28 ₹1.2 L | 20.69 ₹1.2 L |
| 8.00 | Bituminous Macadam (Grade-II) 50mm Thick Using VG30
Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 34.04 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5 | 285.09 | Cum | 8,844.33 ₹25.2 L | 9,022.11 ₹25.7 L |
| 9.00 | BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 141.8 | Cum | 11,412.26 ₹16.2 L | 11,641.67 ₹16.5 L |
| 10.00Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS | |||||
Tender Value
₹1.2 Cr
EMD Value
₹1.2 L
Closing Date
16 Feb 2026, 3:00 pmClosed
The project Director
The Project Director, DRDA,Vellore
Vellore District Strengthening of the Road from Madhanur Ulli Road to Koppampatti Road in Ulli Panchayat R180 MGSMT Savings Fund 2025-26 at Gudiyatham Block
2026_RDTN_654248_1
A7/6191/2024
Open Tender
Civil Works
180 days
DRDA
Please refer Tender documents.
6 documents required · 6 mandatory
₹0
₹1.2 L
Yes
23 Mar 2026
10 Feb 2026
16 Feb 2026
10 Feb 2026
16 Feb 2026
10 Feb 2026
Strengthening of the Road at km1/4 Madhanur Ulli Road to Koppampatti Road in Ulli Panchayat of Gudiyatham Block (R-180) (km 0/0-1/680)
Clearing the scrub jungles including cutting the scrubs and removing away from site etc complete
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Earth work excavation and depositing on bank within initial lead and lift in hard gravelly soil for Cutting sidedrain etc, complete. as per SS20 A
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 125mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of Prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
Bituminous Macadam (Grade-II) 50mm Thick Using VG30 Providing, laying 50mm consolidated thick Bituminous Macadam using 0.20cum of 26.50- 13.20mm, 0.43cum of 13.20-2.36mm and 0.08cum of 2.36mm & below size IRC metal with 34.04 Kgs of VG30 Grade bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen, aggregate and mixing them in required temperature using Central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory Roller to the required density etc., including labour for attending to paver to site etc., including hire and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including all other incidental charges etc., complete as per specification using CMP as per clause 504 of MORTH Rev-5
BC 25/30/40mm Thick (Grade-II) Using VG30 Bitumen Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for SHOULDERS
roviding and laying if hot applied Thermoplastic compound 2.5mm thick including reflectirising glass beads @ 250 gms per Sq.M area. Thickness of 2.5mm is exclusive of surface applied glass beads as per IRC 35. The finished surface to be level uniform and free from streaks and holes etc. complete as per MORT&H specification No.803.
Provision of 15 Nos. of Rumble Strips covered with premix bituminous carpet, 15-20 mm High at centre, 250 mm wide placed at 1 m center - to center at approved locations to control speed, marked with shite srips of road marking paint.
Construction of Retaining Wall 0/400 & 0/900
Earth work excavation and depositing on bank with initial lead and lift in hard gravelly soil, in hard stiff clay, as per SS 20B complete.
Retaining Wall @ CH 400
Retaining Wall @ CH 900
Cement Concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Retaining Wall @ CH 400
Retaining Wall @ CH 900
Cement Concrete 1:3:6 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc.
Retaining Wall @ CH 400
Retaining Wall @ CH 900
Supplying and erecting centring sor sides and soffits with M.S sheets laid over silver oak joists with casurina props for supporting,labour charges etc.,complete
Retaining Wall @ CH 400
Retaining Wall @ CH 900
Provision for Hectometer stone
Provision for Kilometer stone
Provision for 60 CM Equilateral Cautionary Sign Board Charges
GST Amount for providing service to Government contract works for the above construction works. { GST amount is the Total GST amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.20 MB
Tendernotice_2.pdf
PDF • 0.80 MB
Tendernotice_3.pdf
PDF • 0.36 MB
BOQ_784515.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid