Tender Value
₹3.0 L
EMD Value
₹6,000
Closing Date
31 Jul 2026, 1:00 pm5d left
EE-WS(W)
KMC, 212, Rashbehari Avenue, Kolkata -700019
REPAIRING OF LEAKS OF 100 MM, 150 MM. AND 200 MM. DIA. MAINS AT DIFFERENT LOCATIONS (13 G. J. KHAN RD, 29 TILJALA LN, 32 S. R. RD. ETC.) IN WARD NO. 66.
2026_KMC_1032171_1
KMC/WS/PG_66/T-12/26-27
Open Tender
CIVIL WORKS
Percentage
12 days
AT DIFFERENT LOCATIONS (13 G. J. KHAN RD, 29 TILJA
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹6,000
Yes
13 Jul 2026
13 Jul 2026
4 Aug 2026
13 Jul 2026
31 Jul 2026
14 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 6. Hire and labour charges for shoring work (including necessary close plank walling, framing, Eucalyptus/Jhou bulla piling, strutting etc) complete as per direction of the Engineer-in charge for foundation excavation (vertical surface are in contact with supported earth is to be measured.) (This item should be executed on specific direction of the Enginner in charge).(a) Depth upto 1.5 m. | 94.5 | SQM | 386 | ₹36,477 |
| 2 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.1 Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. | 118.5 | %M3 | 119.27 | ₹14,133.49 |
| 3 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 3. Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) (a) With earth obtained from excavation of foundation. | 118.5 | %M3 | 77.54 | ₹9,188.49 |
| 4 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.8 Hire and labour charges for 75 mm dia bamboo railing on Jhau/Eucalyptusor other approved timber\bamboo posts 1.4 m above G.L and 0.60 m below G.L including tying strongly with coir ropes and boring holes for posts in any soil/ concrete surface/Bituminious surface packing the sides etc including cost of carriage of all materials and labour complete including cost of restoration to the damages of the ground to its original condition as per direction of Engineer in charge after removing the barricade.(Cost of restoration would be paid seperately. a) 75mm. dia bamboo railing & 125mm. Dia Jhau/Eucalyptus/other approved timber posts @ 1.60m apart (i) Railing with 4 rows. | 268 | MTR | 57 | ₹15,276 |
| 5 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.4 Excavation of trial pit (3.0 m x 1.0 m x (upto) 3.0 m) for fixing of pumping main, washout line raking every detection against damage of S.W. pipe line electrical cable etc. as underground obstruction including 37.5 mm timber shuttering, earth cutting, dewatering, barricading and back filling etc. as per directionj of E-I-C | 6 | EA | 1,867 | ₹11,202 |
| 6 | CHAPTER - III TAKING OUT PIPES AND SPECIALS Cast Iron / Ductile Iron Pipes and Specials M.S. Pipes and Specials Shifting house connection or stand post connection from existing main to new main after excavation through any kind of soil and road materials up to required depth. dismantling existing ferrule with all fittings. plugging hole of old main with G.I. plug. drilling and tapping the new main. refixing the ferrule on the new main with serviceable old G.I pipes and other specials (New G.l. pipes and other specials. if required to be installed shall be paid extra) and back filling the trench with excavated materials all complete as per specification and direction of the Engineer- in-Charge. | 11 | EA | 1,427 | ₹15,697 |
| 7 | BUILDING WORKS. (T)MISCELLANEOUS WORKS: A. SPECIAL WORKS. III. EVENT MANAGEMENT : 18) Supplying sign-board made of 25 mm thick sal plank with frame on all side of sal batten 50 mm x 32 mm with nailed on post 3.15mx100mmx100mm and fitting fixing such with digging holes of dia 300 mm and depth 750 mm in all sorts of soil and repacking and consolidating the gap around the post with cement concrete (1 : 3 : 6) painting 2 coats including cost of nails, bolts and nuts etc. complete in all respect as per direction of the Engineer-in-charge.Payment of concrete and painting to be made separately. (ii) 900 mm. x 600 mm. size of board. | 2 | EA | 813 | ₹1,626 |
| 8 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.14 Signalling arrangement at both sides of site to avoid any accident during working period 4 nos. red flags during sunlight at 4 corners and 2 nos light (lamp) in other than sunlight. | 7 | DAY | 202 | ₹1,414 |
| 9 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC. 1.13 Hire & labour charges for diesel generating set for lighting including fuel,300M wire, 11 points with 200 Watt bulb with post for hanging & maintaining the same for day & night for the period. | 6 | DAY | 1,650 | ₹9,900 |
| 10 | CHAPTER - I [ SUPPLEMENTARY ] EXCAVATION, SHORING, BAMBOO PILING, FENCING & SIGN BOARD, LIGHTING & SIGNALING AND SITE CLEANING ETC.1.3 Filling in foundation or plinth by silver sand in layers not exceeding 150 mmas directed and consolidating the same by thorough saturation with water,ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) | 11.85 | %M3 | 936.21 | ₹11,094.09 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.05 MB
BOQ_2534636.xls
BOQ • 0.33 MB
tbid.pdf
Tender Documents • 0.92 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].