| 1 | L-1₹57.6 CrAccepted-AOC | ₹57.6 Cr | L-1 | Accepted-AOC Awarded being valid and eligible L-1 Bidder as per Tender Committee evaluation. Awarded value is as per ONLINE Bid Price inclusive of Goods and Service Tax (GST) Components. |
| 2 | L-2₹59.1 CrRejected-Finance CHANDANI CHOWK RAIGARH CHHATTISGARH 496001 | RAIGARH | CHHATTISGARH | 496001 | ₹59.1 Cr | L-2 | Rejected-Finance Rejected not being L1 Bidder. |
| 3 | L-3₹62.2 CrRejected-Finance | ₹62.2 Cr | L-3 | Rejected-Finance Rejected not being L1 Bidder. |
| 4 | L-4₹62.3 CrRejected-Finance | ₹62.3 Cr | L-4 | Rejected-Finance Rejected not being L1 Bidder. |
| 5 | L-5₹63.6 CrRejected-Finance | ₹63.6 Cr | L-5 | Rejected-Finance Rejected not being L1 Bidder. |
Tender Value
₹80.2 Cr
EMD Value
₹50 L
Closing Date
29 Jul 2023, 5:00 pmClosed
General Manager (Civil)/HoD, SECL
Office of GM (Civil)/HoD, SECL Bhawan, Seepat Road, Bilaspur, CG, PIN-495006. Contact No. 09422293565/ 09425531210/ 07880128817email - gmcivilhod.secl(at)gmail.com and/or gmcivil.secl(at)coalindia.in
Construction of WBM Haul Road from Inpit crusher up to Sarangi Chowk along one side of conveyor and from new HEMM Workshop up to TRS-2 including 05 years maintenance at Kusmunda Expansion Opencast Project (KOCP) Area.
2023_SECL_282390_1
GM(C)/SECL/BSP/e-T/KSM/2023/17 dt.26.06.2023
Open Tender
Civil Works - Roads
2095 days
Kusmunda Area, Distt-Korba, CG
Please refer Tender documents.
5 documents required · 5 mandatory
₹50 L
30 Oct 2023
28 Jun 2023
31 Jul 2023
28 Jun 2023
29 Jul 2023
29 Jun 2023
28 Jun 2023 - 22 Jul 2023
Amount
Excavation in Soil using Hydraulic Excavator and Tippers with disposal upto 1000 metres. Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location with all lifts and lead upto 1000m as per relevent clauses of section-300 of specification
Construction of Embankment with Material Deposited from Roadway Cutting Construction of embankment with approved materials CBR>7 deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-1, 300-2 and as per relevent clauses of section-300.
Water Bound Macadam Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per clause 404 of specification. Grading- I (63 to 45mm) Using Screening Type-B (11.2mm Agg.)
Water Bound Macadam Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening/binding Materials to fill up the interstices of coarse aggregate, watering and compacting to the required density as per clause 404 of specification. Grading- II (53 to 22.4mm) Using Screening Type-B (11.2mm Agg.)
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level: 1:3:6 (1 Cement : 3 coarse sand : 6 graded stone aggregate 40 mm nominal size)
Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement : 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size)
Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size).
Providing, hoisting and fixing up to floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement, with 1:2:4 (1cement : 2coarse sand : 4graded stone aggregate 20 mm nominal size).
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level. Cold twisted bars
Centering and shuttering including strutting, propping etc. and removal of form for : Foundations, footings, bases of columns, etc. for mass concrete
Centering and shuttering including strutting, propping etc. and removal of form for : Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Centering and shuttering including strutting, propping etc. and removal of form for : Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Providing and fixing unplasticised Regid PVC rain water pipes conforming to IS:13592 Type A, for weap holes as per instruction of Engineer-in-charge. Single socketed pipes 110mm diameter
Repair & maintenance of haul road for a period of five (05) years from the date of completion of construction work will includes repairing of all components of haul roads like GSB,Base process, Wearing surfaces, dressing/ repairing of shoulders, repairing & cleaning of drains and culverts as & when required and as per instruction of Engineer-in-charge with provision of fortnightly joint inspection of the road. Maintenance include removal of coal spillage from tippers/ dumpers from the road surface. However, payment for maintenance work will be restricted to the amount earmarked for each year.
First year
Second year
Third year
Fourth year
Fifth year
Total impact of GST for the purpose of CTC
HILL BROW METALLICS AND CONSTRUCTION PVT LTD
ASHOK KUMAR MITTAL (JV)
MKG AND ABPL JV
Shrikishan And Company Pvt. Ltd.
SBI-BIKASH (J.V)
M/S VKJ-AA(JV)
M/s. B. B. Verma
SRC-KLA JV
Triveni Engicons Private Limited
stage.html
html • 0.07 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid