| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.0 LAccepted-AOC TAMIL NADU TN | TIRUVANNAMALAI | TAMIL NADU | 604407 | ₹10.0 L | L1 | Accepted-AOC L1 bidder |
| 2 | L2₹10.3 LRejected-AOC | ₹10.3 L | L2 | Rejected-AOC L2 bidder |
| Sl No | Description | Qty | Unit | G. Suresh L2 | A THIRUVENGADAM L1 |
|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete SS.20B 10 cum Manual/mechanical excavation of pits sized 3 ft x 3 ft x 3 ft depth.Removal of loose soil and debris.Ensuring level base and vertical sides.Disposed soil to be shifted to designated area or site boundary. | 16 | cum | 95 ₹1,520 | 90 ₹1,440 |
| 2.00 | Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification | 3 | cum | 5,400 ₹16,200 | 5,370 ₹16,110 |
| 3.00 | Suppling and fabricating and placing in position MS (or) R.T.S. bar for reinforcement to all RCC works as per the design given including cost of steel and binding wire also in all floors. | 104 | Kgs | 95 ₹9,880 | 92 ₹9,568 |
| 4.00 | Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers - | 2 | cum | 8,600 ₹17,200 | 8,550.61 ₹17,101.22 |
| 5.00 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | 15 | sqm | 710 ₹10,650 | 701.97 ₹10,529.55 |
| 6.00 | Supplying and filling in foundation and basement with stone dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 8 | cum | 310 ₹2,480 | 308.5 ₹2,468 |
| 7.00 | Brick work in CM 1:5 (one cement & Five Crushed Stone Sand (M- Sand)) using II class ground moulded bricks of size 9" X 43/8"X 2 3/4" including finishing, curing, etc., complete complying with standard specification - | 4 | cum | 7,520 ₹30,080 | 7,515 ₹30,060 |
| 8.00 | Laying of 4" PVC pipes at adequate intervals for better slope and water drainage through the entire lenght of the brickwork at 15 feet intervals | 3.6 | Rm | 280 ₹1,008 | 275 ₹990 |
| 9.00 | Plastering with cement mortar 1:3 (One part of Cement and Three part of Plastering Sand (P- Sand)), 10mm thick in all floors including cost and conveyance of all materilas to site and labour charges etc,complete as per standard specifications | 92 | sqm | 340 ₹31,280 | 330 ₹30,360 |
| 10.00 | Supplying, fabricating, erecting structural steel work for roofing welded or bolted type using MS channels, angles, plates and round bars etc. conforming to IS specification including primer coating and enamal painting as per Design given by the departmental officers etc, complete as per standard specification | 1,197 | Kgs | 120 ₹1.4 L | 110 ₹1.3 L |
Tender Value
₹12 L
EMD Value
₹12,000
Closing Date
23 Sept 2025, 3:00 pmClosed
The Commissioner, Tambaram Corporation
1, Muthuranga Mudali St, West Tambaram, Tambaram, Chennai, Tamil Nadu 600045
Construction of Pickle Ball Court in Arul Pandiyan Park at Ward No.11 TCMC Zone No.01
2025_DMA_603513_1
2515/2025/E1/Z1
Open Tender
Civil Works
Pammal Zone No.01
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹12,000
5 May 2026
12 Sept 2025
23 Sept 2025
12 Sept 2025
23 Sept 2025
12 Sept 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_721420.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.52 MB
BOQ_721420.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid