| Sl No | Description | Qty | Unit | jayashree construction | V R R AND COMPANY |
|---|---|---|---|---|---|
| 1.00 | Charges for cutting the B.T surface to 5 to 7 cm depth using milling machine, conveying the Milled waste materials to at least for 5 km distance including hire and running charges for the machine, conveyance charges, unloading at unobjectionable place, cleaning the milled surface as to avoid slippery including all other incidental and unforeseen item etc. complete as per the direction of the departmental officers | 7,514.25 | M2 | 11,27,137.5 ₹13.3 L | 8,34,081.75 ₹9.8 L |
| 2.00 | Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. | 269.38 | M3 | 6,73,450 ₹7.9 L | 6,59,981 ₹7.8 L |
| 3.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications | 2,691.75 | M2 | 2,69,175 ₹3.2 L | 2,44,949.25 ₹2.9 L |
| 4.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications | 2,691.75 | M2 | 80,752.5 ₹95,287.95 | 51,143.25 ₹60,349.04 |
| 5.00 | Providing and laying tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 7,514.25 | M2 | 3,75,712.5 ₹4.4 L | 2,17,913.25 ₹2.6 L |
| 6.00 | Providing and laying BM 50mm compacted thick Dense Bituminous Macadam using 0.24cum of 26.50 – 13.20 mm, 0.25cum of 13.20-2.36 mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30 / VG40 bitumen for premixing per 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 tonnes capacity, conveying the mix by Tipper trucks to worksite, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 tonnes CMP with bitumen Boiler, Tipper trucks, Paver finisher / 9m Paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 of MORTH Rev-5. | 511 | M3 | 53,65,500 ₹63.3 L | 52,45,926 ₹61.9 L |
| 7.00 | Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00 – 9.50 mm, 0.17cum of 9.50 - 2.36 mm and 0.26cum of 2.36mm & below with 45.27 Kgs of 60/70 bitumen &50.30kg of plastic waste from garbage collected at free of cost (Total 50.30kg) and for premixing per 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 tonnes capacity, conveying the mix by Tipper trucks to paver site, spreading the mix to uniform thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes Vibratory / Pneumatic roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 tonnes CMP with bitumen Boiler, Tipper trucks, Paver finisher / 9m Paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 MORTH Rev-5. | 307 | M3 | 33,46,300 ₹39.5 L | 33,09,460 ₹39.1 L |
Updated dates
Tender Value
₹1.3 Cr
EMD Value
₹1.3 L
Closing Date
28 Jan 2026, 3:00 pmClosed
The Commissioner
Muthurangam Street,West Tambaram,Chennai - 45
TCMC - Providing BT Surface at Ward No.70 Package No.43
2026_DMA_642807_17
16/2026/E1
Open Tender
Civil Works - Roads
90 days
Tambaram City Municipal Corporation Zone V
Please refer Tender documents.
3 documents required · 3 mandatory
₹10,000
₹1.3 L
Tambaram City Municipal Corporation
2 Jun 2026
13 Jan 2026
28 Jan 2026
13 Jan 2026
28 Jan 2026
13 Jan 2026
14 Jan 2026
Charges for cutting the B.T surface to 5 to 7 cm depth using milling machine, conveying the Milled waste materials to at least for 5 km distance including hire and running charges for the machine, conveyance charges, unloading at unobjectionable place, cleaning the milled surface as to avoid slippery including all other incidental and unforeseen item etc. complete as per the direction of the departmental officers
Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications.
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications
Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev-5 Specifications
Providing and laying tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying BM 50mm compacted thick Dense Bituminous Macadam using 0.24cum of 26.50 – 13.20 mm, 0.25cum of 13.20-2.36 mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30 / VG40 bitumen for premixing per 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 tonnes capacity, conveying the mix by Tipper trucks to worksite, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 tonnes CMP with bitumen Boiler, Tipper trucks, Paver finisher / 9m Paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 of MORTH Rev-5.
Providing and laying Bituminous Concrete to 30mm thick using 0.13cum of 19.00 – 9.50 mm, 0.17cum of 9.50 - 2.36 mm and 0.26cum of 2.36mm & below with 45.27 Kgs of 60/70 bitumen &50.30kg of plastic waste from garbage collected at free of cost (Total 50.30kg) and for premixing per 10 sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 tonnes capacity, conveying the mix by Tipper trucks to paver site, spreading the mix to uniform thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes Vibratory / Pneumatic roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 tonnes CMP with bitumen Boiler, Tipper trucks, Paver finisher / 9m Paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 MORTH Rev-5.
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.29 MB
BOQ_770260.xls
BOQ • 0.34 MB
43.pdf
Tender Documents • 0.87 MB
Download all tender documents and submit your bid