| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 LAccepted-AOC | L1 | Accepted-AOC Lowest Price | |
| 2 | L2₹4.9 L+₹180 (0.04%)Rejected-Finance | L2 | Rejected-Finance Highest Price | |
| 3 | L3₹4.9 L+₹3,477 (0.71%)Rejected-Finance | L3 | Rejected-Finance Highest Price | |
| 4 | L4₹4.9 L+₹5,277 (1.08%)Rejected-Finance | L4 | Rejected-Finance Highest Price |
| Sl No | Description | Qty | Unit | V KALPANA L4 | KAY YES CONSTRUCTIONS L3 | SRI KRISHNA MANPOWER SUPPLIERS AGENCY L2 | K.DURAI KANNU L1 |
|---|---|---|---|---|---|---|---|
| 1.00 | Earthwork excavation for foundation in all soils and sub soils in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders and to full depth as may be directed,except in hard rock,requiring blasting including shoring and shuttering and bailing out of water wherever necessary,refilling the sides of foundation with excavated earth or sand in layer of not more than 15cm thick.well rammed and consolidated and depositing on bank with initial lead and lift of 10m & initial lift of 2m and depositing the surplusr earth within the compound in places shown by the departmental officers with iniital lead and lifts,clearing and levelling the site etc., complete as per SS20B and as directed by departmental Engineers(TNBP No.17,23,24). | 90 | m3 | 150 ₹13,500 | 130 ₹11,700 | 122 ₹10,980 | 120 ₹10,800 Lowest |
| 2.00 | Supplying and filling in foundation and basement with Stone Dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 15 | m3 | 270 ₹4,050 | 270 ₹4,050 | 265 ₹3,975 Lowest | 265 ₹3,975 Lowest |
| 3.00 | Plain Cement Concrete 1:4:8 mix (One Cement, Four Fine Aggregate and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). | 15 | m3 | 5,320 ₹79,800 | 5,320 ₹79,800 | 5,310 ₹79,650 Lowest | 5,310 ₹79,650 Lowest |
| 4.00 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | 299 | m2 | 315 ₹94,185 | 315 ₹94,185 | 309 ₹92,391 Lowest | 309 ₹92,391 Lowest |
| 5.00 | Plain Cement Concrete 1:2:4 mix (One Cement, Two Sand and Four Coarse Aggregate) Using 20mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). | 30 | m3 | 6,600 ₹1,98,000 Lowest | 6,600 ₹1,98,000 Lowest | 6,600 ₹1,98,000 Lowest | 6,600 ₹1,98,000 Lowest |
| 6.00 | Plastering with CM 1:4 (One part of cement & Four parts of sand) mix for 12mm thick including cost and conveyance of all materials to work site and including all labour charges for mixing, laying, curing,finishing etc., complete as per standard specifications and as directed by departmental Engineers – (TNBP No:56&57) | 42 | m2 | 585 ₹24,570 | 585 ₹24,570 | 576 ₹24,192 Lowest | 576 ₹24,192 Lowest |
| 7.00 | Removal of Excavated Excess Earth away from the site to 5K.M including loading and transportation charges etc, complete as per standard specification. For 1M3 | 60 | m3 | 70 ₹4,200 | 70 ₹4,200 | 67 ₹4,020 Lowest | 67 ₹4,020 Lowest |
| 8.00 | GST 18% | 1 | No | 74,377 ₹74,377 Lowest | 74,377 ₹74,377 Lowest | 74,377 ₹74,377 Lowest | 74,377 ₹74,377 Lowest |
Tender Value
₹5 L
EMD Value
₹10,001
Closing Date
13 Mar 2026, 3:00 pmClosed
Commissioner
Infantry Road, Vellore Corporation, Vellore-632001.
Construction of Strom Water Drain at Gandhi Nagar 11th Cross Street in Ward No.54 at Zone - III, Vellore Corporation.
2026_MAWS_671773_1
4079/2025/E3/GF-25-26/Z3/P13
Open Tender
Civil Works
Works
180 days
Vellore
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹10,001
16 Oct 2026
7 Mar 2026
13 Mar 2026
7 Mar 2026
13 Mar 2026
7 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork excavation for foundation in all soils and sub soils in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders and to full depth as may be directed,except in hard rock,requiring blasting including shoring and shuttering and bailing out of water wherever necessary,refilling the sides of foundation with excavated earth or sand in layer of not more than 15cm thick.well rammed and consolidated and depositing on bank with initial lead and lift of 10m & initial lift of 2m and depositing the surplusr earth within the compound in places shown by the departmental officers with iniital lead and lifts,clearing and levelling the site etc., complete as per SS20B and as directed by departmental Engineers(TNBP No.17,23,24). | 90 | m3 | - | - |
| 2 | Supplying and filling in foundation and basement with Stone Dust in layers of not more than 15cm thick well rammed watered and compacted etc., complete complying with standard specification. | 15 | m3 | - | - |
| 3 | Plain Cement Concrete 1:4:8 mix (One Cement, Four Fine Aggregate and Eight Coarse Aggregate) Using 40mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). | 15 | m3 | - | - |
| 4 | Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | 299 | m2 | - | - |
| 5 | Plain Cement Concrete 1:2:4 mix (One Cement, Two Sand and Four Coarse Aggregate) Using 20mm ISS HBG metal for foundation and basement including dewatering if found necessary and laid in layer of not more than 15cm thick and consolidated including all cost conveyance of materials and labour charges etc. complete as per standard specifications and as directed by departmental Engineers(TNBP No.28). | 30 | m3 | - | - |
| 6 | Plastering with CM 1:4 (One part of cement & Four parts of sand) mix for 12mm thick including cost and conveyance of all materials to work site and including all labour charges for mixing, laying, curing,finishing etc., complete as per standard specifications and as directed by departmental Engineers – (TNBP No:56&57) | 42 | m2 | - | - |
| 7 | Removal of Excavated Excess Earth away from the site to 5K.M including loading and transportation charges etc, complete as per standard specification. For 1M3 | 60 | m3 | - | - |
| 8 | GST 18% | 1 | No | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_807299.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.76 MB
BOQ_807299.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .